Camillo v. Olympia & York Properties Co.

157 A.D.2d 34, 554 N.Y.S.2d 532, 1990 N.Y. App. Div. LEXIS 4875
Appellate Division of the Supreme Court of the State of New York·Decided May 1, 1990·Published·Cited by 9 cases

Opinion

OPINION OF THE COURT

Asch, J.

Matthew May was injured when a crane owned by Canron, Inc. (Canron-Canada), under the control of its New York subsidiary, Canron Corporation (Canron-NY), and operated by the latter’s employee, William Geer, collapsed, striking a building across the street and causing pieces of concrete to fall. Olympia & York Properties Company owned the property on which the crane was mounted. O&Y Construction Corp. was the general contractor. Charles M. Shapiro & Sons, P. C. was the crane engineering consultant.

FMC Corporation (FMC) was the parent company of FAVCO International Corp. at the times relevant to the case before us. FAVCO was the United States distributor, supplier and assembler of crane component parts obtained in kits from Favelle Mort, Ltd., an independent Australian corporation, and manufacturer of the crane parts. The crane involved in the instant occurrence was the FAVCO 1500 crane. It was designed to operate from the top of a building structure and to climb up the building as additional stories were added.

In 1973, Canron-Canada purchased the component parts for two FAVCO 1500 cranes from Favelle Mort. Canron-Canada assembled the cranes in Canada. It had used them earlier in connection with construction of a building for the Bank of Montreal in downtown Toronto. In February 1975, an aluminum sheave, a component part of the crane, broke while the crane was lifting a load of steel that was variously estimated at 16 to 20 tons. Arnold Van Hees, Canron-Canada’s construction manager, took note of the broken sheave on one crane and observed a cracked sheave on the second. Canron-Canada immediately ordered replacement sheaves from FMC. FMC provided Canron-Canada with the replacements, which had been manufactured by Favelle Mort in Australia. Upon receipt of the replacements, Van Hees noticed what he considered to be defects in the aluminum replacement sheave, which he described as scruffiness. Even though he did not like the way the sheaves looked, Canron-Canada nevertheless installed them in the crane because they were the only sheaves available at the time. Van Hees asked his superior to make an inquiry of FMC with respect to the sheaves. As a precaution, [40]*40Canron-Canada instituted weekly, rather than the usual monthly, inspections of the part. They performed properly for approximately two months and showed no evidence of cracks, although they had lifted approximately 22-ton loads. Van Hees, as a consequence, thought that the first set of sheaves which originally came with the crane in 1973 might have been a fluke or a bad batch of aluminum castings. Accordingly, Canron-Canada was satisfied with the replacement sheaves.

Canron-Canada did have metallurgical tests performed upon the broken sheaves to determine the cause of their failure. In April 1975, it received a report which concluded that the failure arose from casting deficiencies. The report provided that sheaves should be molded out of a different aluminum alloy. Canron-Canada forwarded a copy of the report to FAVCO International, FMC’s subsidiary. The communication was given to FMC’s service manager on April 22, 1975. He wrote to Favelle Mort, the manufacturer, seeking a credit to FMC’s account, since the claims were under warranty, and requesting that Favelle Mort make a more extensive check on the sheaves before shipping them to the United States. Favelle Mort did not respond to FMC’s letter and FMC made no further inquiry. Likewise, Canron-Canada never followed up on its letter to FMC and never made inquiry of Favelle Mort. Canron-Canada continued to use the sheaves without any additional precautions.

In 1977, FMC received a report from American Bridge, an American company which used the FAVCO 1500 cranes, that cracks had been discovered in their aluminum sheaves. These sheaves were replaced by FMC with steel sheaves which it, rather than Favelle Mort, had manufactured. However, even though it had developed the steel replacement, FMC never notified the other 17 crane owners located in North America of the casting problems with the aluminum sheave or that steel replacements were available.

In 1980, Canron-Canada provided Canron-NY with one of its cranes for use in connection with the construction work to be performed at 466 Lexington Avenue, New York County, on property owned by Olympia & York. The crane was shipped and its various parts inspected prior to and after assembly. There were no noticeable defects. The crane was also tested for overloading, circumstances in which the load exceeded the limit set out on the capacity chart prepared by defendant Charles M. Shapiro & Sons, P. C. The Shapiro engineering firm had been employed by Canron-NY to obtain the appropri[41]*41ate City of New York permits and it had listed the load limit as 27,000 pounds.

In the course of construction, the crane began lifting operations with William Geer as the operator. It attempted a 36,000-pound lift, approximately 9,000 pounds greater than the lift limit set out in the capacity chart. There was a loud sound and then Geer felt a severe vibration. As fluid spewed from a broken hydraulic fitting, rather than pushing the emergency stop button, Geer released the control lever. He abandoned the cab and fled, as the load of steel beams and crane boom began to fall. The boom struck Olympia & York’s building across the street from the construction site, at 245 Park Avenue, dislodging concrete pieces from the building, which hit Matthew May.

The cracking aluminum sheave was deemed the primary cause of the falling boom. A metallurgical and material science professor concluded that the sheaves had numerous preexisting defects, such as porosity and cracks. Thereafter, FMC, on its own initiative, undertook a campaign offering FMC-manufactured steel sheaves as replacements for the Favelle Mort aluminum sheaves. FMC requested all FAVCO crane owners to inspect their sheaves, offering that those with cracks would be replaced without charge.

At the conclusion of plaintiff’s case, the court dismissed, as a matter of law, plaintiff’s claims against Geer, Shapiro and Canron-Canada. The following day, after the remaining defendants rested, the court dismissed plaintiff’s claims against all remaining defendants except FMC. Also, all cross claims and FMC’s third-party action against Canron-Canada were dismissed.

The jury returned a verdict against FMC for $1,845,000 in compensatory damages and $5,000,000 in punitive damages. The jury also found for Canron-Canada, the crane owner, against FMC for property damage to the crane in the sum of $235,385.47.

Defendant FMC contends that the trial court committed reversible error when it dismissed, as a matter of law, all claims and cross claims against defendants-respondents Canron-Canada, Canron-NY, William Geer, Olympia & York Properties Company, O&Y Construction Corp., as well as the claims against Shapiro.

It is black letter law that the trial court may not usurp the assigned responsibility of the jury and on its own decide [42]*42disputed issues of fact, in resolving a motion to dismiss. Accordingly, FMC was entitled to every favorable inference by the court in deciding whether its cross claims and third-party complaint should be dismissed (Blum v Fresh Grown Preserve Corp., 292 NY 241; Glick v City of New York, 139 AD2d 402; Candelier v City of New York, 129 AD2d 145).

The record certainly contains facts which are sufficient to support claims of negligence against various defendants-respondents.

Free access — add to your briefcase to read the full text and ask questions with AI

Camillo v. Olympia & York Properties Co., 157 A.D.2d 34, 554 N.Y.S.2d 532, 1990 N.Y. App. Div. LEXIS 4875 (N.Y. Ct. App. 1990).

157 A.D.2d 34 (Camillo v. Olympia & York Properties Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gadani v. Dormitory Authority
50 A.D.3d 1303 (Appellate Division of the Supreme Court of New York, 2008)
Vanata v. Delta International Machine Corp.
269 A.D.2d 175 (Appellate Division of the Supreme Court of New York, 2000)
Novartis Corp. v. Luppino (In Re Luppino)
221 B.R. 693 (S.D. New York, 1998)
Kaplan v. Sparks
221 A.D.2d 974 (Appellate Division of the Supreme Court of New York, 1995)
Kern v. Frye Copysystems, Inc.
878 F. Supp. 660 (S.D. New York, 1995)
Camillo v. Geer
185 A.D.2d 192 (Appellate Division of the Supreme Court of New York, 1992)
Smith v. Fitzsimmons
180 A.D.2d 177 (Appellate Division of the Supreme Court of New York, 1992)