Cameron v. Chichagof Min. Co.

82 F. Supp. 665, 12 Alaska 103, 1948 U.S. Dist. LEXIS 3154
CourtDistrict Court, D. Alaska
DecidedSeptember 3, 1948
DocketNo. 4798-A
StatusPublished
Cited by1 cases

This text of 82 F. Supp. 665 (Cameron v. Chichagof Min. Co.) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cameron v. Chichagof Min. Co., 82 F. Supp. 665, 12 Alaska 103, 1948 U.S. Dist. LEXIS 3154 (D. Alaska 1948).

Opinion

FOLTA, District Judge.

All that remains of this action are the plaintiff’s causes of action in which he seeks to recover $1330.13 for unpaid overtime work between October 24, 1938, the effective date of the Act, and February 15, 1941, an equal amount as liquidated damages and attorney fees, under the Fair Labor Standards Act, 52 Stat. 1060, 29 U.S.C.A. § 201 et seq.

Plaintiff was employed as a pumpman at $6 a day of eight hours. The regular work week was 56 hours. Defendant was engaged in gold mining and admits it was subject to the Act during the time here involved except for a brief period which will be later adverted to.

[106]*106On November 18, 1938, following the loss of the ore body, the mine ceased operating, and on January 1, 1939, was placed in a caretaker status. The company then underwent an internal reorganization, and on February 16, 1939, commenced exploratory work which was terminated on May 5, 1939, without the discovery of pay ore. Underground operations were abandoned, and the machinery removed. Contemporaneously, the construction of a flotation plant was undertaken for the purpose of recovering gold from the tailings which had accumulated during the life of the mine, and this project was completed June 14, 1939.

The first question which presents itself is whether, after the mill clean-up and before construction of the flotation plant was begun, during which time the only activity underground was the exploratory work referred to, the company was engaged in the production of goods for commerce, as defined by the Act. More precisely the question may be formulated as follows: Is prospecting for gold by or for one who is not then engaged in the production of gold for commerce, and who will not be so engaged unless such prospecting is successful, within the Act where no gold is discovered ? Unless this is such an overrefinement of the factual situation as the Supreme Court warned against in McLeod v. Threlkeld, 319 U.S. 491, 495, 63 S.Ct. 1248, 87 L.Ed. 1538, it appears to be a question of first impression. The drilling operations, held to be within the Act in Divine v. Levy, D.C., 39 F.Supp. 44, were carried on at the same time that oil was being produced and, hence, it is clear that the drilling was but an incident of the production of oil for commerce. In Warren-Bradshaw v. Hall, 317 U.S. 88, 63 S.Ct. 125, 87 L.Ed. 83, it was held that employees engaged in drilling for oil may be regarded as engaged in a process or occupation necessary to the production of oil, that the connection between drilling wells and the capture of oil is quite substantial, and that such activity bears as “close and immediate a tie” to production as did the services of the building maintenance workers in Kirschbaum v. Walling, [107]*107316 U.S. 517, 62 S.Ct. 1116, 86 L.Ed. 1638. But it should be noted that each drilling job resulted in the production of oil or gas and, hence, the drilling was incidental to the production of oil. Here no gold was discovered and, since, during the entire period in which exploratory work was carried on, no gold was produced by the employer, at the mine involved or elsewhere, it is not perceived how this prospecting could be said to have been incidental, or a process or occupation necessary to the production of gold for commerce. It was the sole activity of the company at that time. The circumstance that it had recently been engaged in the production of gold would, therefore, appear to be immaterial. Its position was that of one who engages in prospecting for something that would ultimately enter into commerce if found. Implicit in the statute is the requirement of actual, not speculative, production and that there be more than a mere tenuous or' remote relationship between the activity and the product. Here not only was there not even a tenuous connection between the prospecting and the production of gold in commerce but the activity was not even remotely related to the product. To say that such an activity is a process or occupation necessary to the production of goods for commerce is to ignore the requirement of production. So construed the Act would include such activities as the unsuccessful and unproductive labors of in-inventors. Cf. Parham v. Austin Co., 5 Cir., 158 F.2d 566. It follows, therefore, that neither the defendant nor, as a consequence, the plaintiff, was engaged in the production of goods for commerce during the time which elapsed between the clean-up of the mill on November 23, 1938, and the commencement of construction work on the flotation plant. The evidence is silent as to the date on which this work was undertaken. It having been shown that the employer was within the Act at the beginning and end of the period for which overtime is claimed, the burden of proving that for some part thereof the Act did not apply was on the defendant.

[108]*108 After the flotation plant was completed, recovery of gold was resumed from the tailings, and plaintiff continued as maintenance man above ground at the same pay and for the same work week as before. However, beginning January 1, 1940, the pay slips showed a different method of computing wages. Thus, in the plaintiff’s case the rates were shown as $5.25 a day straight time and $7.87 a day overtime (Plaintiff’s Exhibits 1, 3 and 4). According to the defendant, this practice was put into effect December 1, 1939, to comply with its understanding of the requirements of the Fair Labor Standards Act. But Plaintiff contends that the notice thereof (Defendant’s Exhibit A) was not posted until August 12, 1940, and then only at an entrance to the Post Office which was seldom used; that, in response to inquiries made by employees as to the meaning of the new rates, they were told that it was merely a change in bookkeeping and that their pay would remain as before. This is corroborated by the depositions of several former employees. Indeed, the general manager testified by deposition that under this arrangement the pay of plaintiff, and others whose wages were the same, would be computed at the rate of $5.25 for five-sevenths of the regular work day of eight hours, and at the rate of $7.87 for the remaining two-sevenths. Essentially, this is the so-called Poxon Plan which was iirvalidated in Walling v. Helmerich & Payne, 323 U.S. 37-40, 65 S.Ct. 11, 89 L.Ed. 29; Robertson v. Alaska Juneau Gold Mining Co., 9th Cir., 157 F.2d 876, certiorari denied; and Walling v. Alaska Pacific Consolidated Mining Co., 9th Cir., 152 F.2d 812, certiorari denied. The Supreme Court has repeatedly pointed out that the regular rate must be the quotient of the amount actually paid divided by the number of hours actually worked; that it must be the actual, not fictitious, rate agreed upon and paid. Concerning such an arrangement as that here involved, it was said in Walling v. Helmerich & Payne, supra, 323 U.S. pages 41, 42, 65 S.Ct. 14, 89 L.Ed. 29:

[109]*109“The vice of respondent’s plan lay in the fact that the contract regular rate did not represent the rate, which was actually paid for ordinary, non-overtime hours, nor did it allow extra compensation to be paid for true overtime hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

De Rose v. Eastern Plastics, Inc.
134 F. Supp. 805 (W.D. Pennsylvania, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
82 F. Supp. 665, 12 Alaska 103, 1948 U.S. Dist. LEXIS 3154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cameron-v-chichagof-min-co-akd-1948.