Camden & Rockland Water Co. v. Maine Public Utilities Commission

432 A.2d 1284, 1981 Me. LEXIS 924
CourtSupreme Judicial Court of Maine
DecidedAugust 6, 1981
StatusPublished
Cited by10 cases

This text of 432 A.2d 1284 (Camden & Rockland Water Co. v. Maine Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camden & Rockland Water Co. v. Maine Public Utilities Commission, 432 A.2d 1284, 1981 Me. LEXIS 924 (Me. 1981).

Opinion

ROBERTS, Justice.

The Camden and Rockland Water Company seeks review under 35 M.R.S.A. §§ 303 and 305 of a decision by the Public Utilities Commission on the Company’s petition for a rate increase. The Company raises several points on appeal addressed to the Commission’s calculations of rate base and cost of equity. We find the Commission’s decision inadequate in two areas and therefore remand the case to the Commission.

The Company supplies water to Camden, Rockland, Thomaston, Rockport, Owl’s *1286 Head, and Warren and is ninety-two percent owned by the Consumers Water Company. On November 11,1979, the Company applied for a 26.2 percent rate increase, for a revenue increase of $462,052, to be effective December 8,1979. Following the Commission’s suspension of the proposed rates, the towns of Camden, Rockland, and Thom-aston intervened. The Commission granted a revenue increase of $197,895 on August 8, 1980. On August 19, the Commission approved the Company’s revised rate schedule. The Company then petitioned for a rehearing on August 25 to modify the Commission’s order, requesting an increase of $236,-000. The Commission denied the petition. The Company appealed the Commission’s decision under 35 M.R.S.A. § 303 and filed a complaint for review under 35 M.R.S.A. § 305. The section 303 appeal and section 305 complaint were ordered consolidated for hearing by this Court.

The goal of ratemaking is to provide “just and reasonable” rates, 35 M.R.S.A. § 51. Meeting this goal entails the Commission’s balancing two public interests. One is the public interest in low utility costs. The second is the interest in the utility’s continued operations. Therefore, the Commission must set rates that will provide the utility with the opportunity to earn a return sufficient to meet its operating expenses and, by allowing a fair return to its investors, to attract necessary capital at reasonable rates. Id.; see New England Telephone & Telegraph Co. v. Public Utilities Commission, Me., 390 A.2d 8, 14 (1978). The allowed return to the utility is calculated as the product of the utility’s rate base times the rate of return. Here, the Company contends that the Commission made errors in its calculation of both of these components, resulting in too low a return.

I. Rate Base

Rate base is defined as the value of the utility’s investment on which it is allowed to earn a return. Title 35 M.R.S.A. § 52 limits the allowed rate base to “all property . . . used or required to be used in its service to the public within the State.” The Company proposed a rate base of $4,186,828. The Commission eliminated certain proposed items and reduced others, resulting in a rate base of $3,892,155. The Company contends that the low return resulting from the Commission’s calculation of rate base, as well as specific errors in the Commission’s methodology, made the rate base unreasonable.

A. The Actual Investment Comparison

The Company argues that the Commission set its rate base so far below its actual investment that the Company cannot earn the authorized rate of return on its capital, which, it concludes, is confiscatory. According to the Company, the Commission had a statutory obligation under 35 M.R. S.A. § 51 to provide the utility with the opportunity to earn a reasonable rate on its investment. This result is necessary, the Company reasons, because the utility must earn the authorized return on substantially all of its capital investment in order to attract further capital on reasonable terms. Therefore, rate base must approximate total capitalization, making the rate of return on each comparable.

The Company makes several comparisons between its authorized return on equity and its actual return on investment and between rate base and total capitalization to show that the return derived from the Commission’s calculated rate base was too low. For example, although the authorized cost of equity was 13.75 percent, the Company could earn a maximum of only 11.19 percent on its actual equity investment with the allowed rate base. According to the Company, the Commission acted unreasonably because it refused to reevaluate its rate base calculations in light of the resulting low return, instead treating rate base solely as the sum of several components whose inclusion or exclusion is determined independently of the overall result. Rather, the Company argues, the Commission should approach rate base as a flexible concept requiring it to include items as necessary to provide an adequate return. The Company concludes that the Commission therefore *1287 erred by excluding from rate base many of the Company’s proposed entries. 1

We find two problems with the proposed comparisons. First, the Commission is not statutorily authorized to consider return on total investment in determining rate base. Title 35 M.R.S.A. § 52 expressly limits the Commission’s consideration to property in service. Although the Company correctly points out that the Commission is obligated to ensure that the utility has the opportunity to earn sufficient revenues to provide an adequate return to its investors, the legislature has provided the return on rate base, not the return on total capitalization, as the measure of that amount. Therefore, we do not consider comparisons between allowed return on rate base and actual return on total investment as indicating an inadequate rate base.

Second, we have developed a carefully circumscribed standard of review over the Commission’s decisions that reflects in part the Legislature’s placing the Commission in a position of expertise with authority to use its discretion in setting utility rates. New England Telephone & Telegraph Co. v. Public Utilities Commission, Me., 390 A.2d 8, 48 (1978). We do not possess the same degree of expertise, nor is it our function to override essentially legislative decisions. Id.

In earlier cases we have stated that our scope of review includes reviewing the reasonableness of the results of the Commission’s decision. Generally, we discussed this standard where the issue concerned the methodology used by the Commission in computing rate of return, New England Telephone & Telegraph Co. v. Public Utilities Commission, Me., 390 A.2d 8, 48-49 (1978), or a specific component of the rate calculation, e. g., Mars Hill & Blaine Water Co. v. Public Utilities Commission, Me., 397 A.2d 570, 576 (1979) (effective federal income tax rate); Casco Bay Lines v. Public Utilities Commission, Me., 390 A.2d 483, 494 (1978) (reduction in liability insurance expense). In Mars Hill

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D'Amato v. S.D. Warren Co.
2003 ME 116 (Supreme Judicial Court of Maine, 2003)
Public Advocate v. Public Utilities Commission
1998 ME 218 (Supreme Judicial Court of Maine, 1998)
American Ass'n of Retired Persons v. Public Utilities Commission
678 A.2d 1025 (Supreme Judicial Court of Maine, 1996)
Texaco Puerto Rico, Inc. v. Ocasio Rodriguez
749 F. Supp. 348 (D. Puerto Rico, 1990)
Maine Public Advocate v. Public Utilities Commission
476 A.2d 178 (Supreme Judicial Court of Maine, 1984)
New England Telephone & Telegraph Co. v. Public Utilities Commission
470 A.2d 772 (Supreme Judicial Court of Maine, 1984)
Central Maine Power Co. v. Public Utilities Commission
455 A.2d 34 (Supreme Judicial Court of Maine, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
432 A.2d 1284, 1981 Me. LEXIS 924, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camden-rockland-water-co-v-maine-public-utilities-commission-me-1981.