Camden Iron & Metal v. Krafsur

CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 10, 2003
Docket02-50530
StatusPublished

This text of Camden Iron & Metal v. Krafsur (Camden Iron & Metal v. Krafsur) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camden Iron & Metal v. Krafsur, (5th Cir. 2003).

Opinion

United States Court of Appeals Fifth Circuit F I L E D July 10, 2003 IN THE UNITED STATES COURT OF APPEALS Charles R. Fulbruge III Clerk FOR THE FIFTH CIRCUIT

_______________________

No. 02-50530 _______________________

In the Matter of: NEWELL INDUSTRIES, INC., Debtor

_______________________________

CAMDEN IRON & METAL, INC., Appellant versus

ANDREW B. KRAFSUR, Trustee Appellee

Appeal from the United States District Court For the Western District of Texas

Before GARWOOD and HIGGINBOTHAM, Circuit Judges, and FELDMAN,* District Judge.

FELDMAN, District Judge:

I.

* District Judge of the Eastern District of Louisiana, sitting by designation.

1 Camden Iron & Metal, Inc. is a metal recycling and salvaging

company engaged in shredding and processing old automobiles and

appliances. The scrap that is left is sold to steel mills and

aluminum foundries and processed into new products.

In April 1998, Camden agreed with Newell Industries, Inc. to

buy a MegaShredder. The MegaShredder is a specialized, complex

machine that is designed to shred large metal objects into fist-

sized scrap metal. Newell agreed to design, manufacture and

deliver an unassembled MegaShredder within 180 days for a price

of $2.53 million. The deal became plagued with performance

problems.

After Newell failed to meet some of its early deadlines,

Camden representatives discovered that Newell had somehow

arranged to sell the MegaShredder to a company in Denmark.

Camden then stopped making payments. Predictably, a flurry of

lawsuits followed. Newell sued Camden in Texas state court for

breach of contract and interference with delivery of equipment,

and Camden sued Newell for breach of contract and fraud.1

The parties subsequently reached an agreement which provided

that Newell would complete the manufacture of the MegaShredder

and Camden would monitor its progress. Three months later,

however, substantial components of the MegaShredder remained

unfinished.

1 The two cases were later consolidated.

2 In November 1999, Newell filed for bankruptcy protection

under Chapter 11 of the Bankruptcy Code. Camden in turn sued

Newell in bankruptcy court to prevent it from selling,

transporting or disassembling the unfinished MegaShredder or any

of its parts.

Thereafter, Newell and Camden reached still another

agreement under Bankruptcy Rule 9019. They set a delivery date

of May 20, 2000, increased the purchase price by $200,000,2 and

agreed that a Camden engineer could observe the manufacturing

process and review design plans.

After Newell again failed to meet its obligations, Camden

and the trustee entered one more final agreement. The terms of

the last agreement were recited in open court:

1) The Newell estate will deliver the manufactured MegaShredder by July 15, 2000;

2) Camden will provide the estate a $200,000 line of credit, to be drawn on only when it spends such amount in manufacturing or when the MegaShredder is completed; and

3) Camden can oversee and direct the order in which the components are manufactured, have access to all assembly plans, specifications and drawings,3 and will be provided an engineer to oversee assembly at its facilities.

After the last agreement, Newell’s estate spent an

2 The $200,000 was to be paid under a letter of credit in installments. 3 Newell agreed to file a complete set of plans under seal with the court.

3 additional $209,000 making the MegaShredder’s components.

Camden, however, refused to pay the $200,000 fee because it

claimed the trustee failed to provide it with both a supervising

engineer and sufficient design plans. The trustee then moved the

bankruptcy court to determine and compel compliance with the

agreement.

The bankruptcy court held, among other things, that the

trustee was not required to pay for Camden’s supervising engineer

during assembly, that Camden was entitled to all the design

plans, specifications and drawings that the trustee had filed

with the court, and that Camden could claim a $50,000 offset for

the expenses it incurred as a result of the incomplete design

plans. The district court affirmed. We affirm in part and

reverse in part.

II.

The bankruptcy court's findings of fact “will not be set

aside unless clearly erroneous.” Matter of Faden, 96 F.3d 792,

795 (5th Cir. 1996). Conclusions of law, on the other hand, are

subject to plenary review on appeal. See id. (“[W]hen a finding

of fact is premised on an improper legal standard, that finding

loses the insulation of the clearly erroneous rule.”).

The interpretation of a contract is a matter of law, as is

the determination that a contract is ambiguous, and both are

reviewed de novo. See In re Liljeberg Enterprises, Inc., 304

4 F.3d 410, 439 (5th Cir. 2002). A contract is not ambiguous if it

can be given a definite or certain meaning as a matter of law.

See Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd., 940

S.W.2d 587, 589 (Tex. 1996).

A. Engineer During Assembly

The appellant first contends that the bankruptcy and

district courts erred by holding that the trustee was not

required to provide Camden with an engineer to oversee the

installation and assembly of the MegaShredder.4 The final

agreement clearly instructs:

The bankrupt estate will furnish at its own expense an engineer to oversee the installation and assembly of Job 559 on Camden’s facilities.

Although the plain language of the agreement clearly and

definitely states that the trustee was required to provide Camden

with an engineer during assembly, the court nonetheless found the

provision to be ambiguous because it is subject to various

reasonable interpretations.5 In particular, the district court

4 The bankruptcy court denied Camden’s request for an engineer because it was not claimed in the original pleadings. While appellant contests this finding, we need not review the bankruptcy court’s rationale because neither the district court nor the appellee’s brief relied on such reasoning. 5 Camden asserts that neither the parties nor the bankruptcy court raised the issue of ambiguity below, and therefore the district court exceeded its scope of review by sua sponte raising the issue. The interpretation of the contract and determination of ambiguity, however, is a matter of law, and the court “may conclude that a contract is ambiguous even in the absence of such a pleading

5 found it reasonable to interpret the agreement as capping the

trustee’s total expenditures at $200,000. The district court

thus concluded that, after the trustee spent $200,000, all

further manufacturing, installation and assembly costs, including

engineers, were to be paid by Camden. We disagree with the

court’s reading of the agreement. The simple text requires no

added complexity.

The language and intent of the agreement make clear that the

$200,000 line of credit limits only the trustee’s manufacturing

expenditures. For example, the agreement states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Camden Iron & Metal v. Krafsur, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camden-iron-metal-v-krafsur-ca5-2003.