Camarco Contractors, Inc. v. State

40 Misc. 2d 486, 243 N.Y.S.2d 240, 1963 N.Y. Misc. LEXIS 1757
CourtNew York Court of Claims
DecidedJuly 29, 1963
DocketClaim No. 40087
StatusPublished
Cited by2 cases

This text of 40 Misc. 2d 486 (Camarco Contractors, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camarco Contractors, Inc. v. State, 40 Misc. 2d 486, 243 N.Y.S.2d 240, 1963 N.Y. Misc. LEXIS 1757 (N.Y. Super. Ct. 1963).

Opinion

Alexander Del Gtxorno, J.

On or about September 20, 1960, claimant entered into a contract with the State of New York, acting by and through the Taconic State Park Commission, for the construction, reconstruction and improvement of certain portions of Mohansic State Park, Westchester County, affecting site preparation, recreation facilities, utilities, ground improvements, appurtenant work, excavation and grading, etc.

Said contract was to commence promptly and be completed by June 1, 1961. The contract was actually acknowledged by the commission to be completed in all details on January 17, 1962, whereas the claimant states it was completed about November 1, 1961 and accepted by the State on November 6, 1961.

The final estimate submitted by the Conservation Department on January 17, 1962 indicated that $32,381.26 was concededly due to the claimant, for which a check was sent. The claimant rejected the check forwarded on the ground that the claimant disagreed with the State as to the amount then due to it.

[487]*487On February 2,1962, the claimant filed a claim for $61,378.26 in which was included the $32,381.26 as part of its damages.

Thereafter, in a severance action, the late Judge Major, by judgment dated February 13, 1962, ordered the $32,381.26 paid to the claimant, reserving the question of interest thereon until the final determination by this court.

The trial clearly pointed out the cumbersome system under which public contracts are entered into as well as carried out, which involve too many documents to refer to (especially the Department of Public Works general specifications), which documents in turn are modified by the contract itself or plans, or additional specifications inserted in the contract. This potpourri of diverse ingredients hardly ever jells and so often leads to multifarious misunderstandings, bickerings and actual stoppages, resulting in claims which must be finally determined by this court. The parties herein frankly conceded that most of the misunderstandings of the terms of the contract and disagreements which affected the carrying out of said terms would be resolved for one side or the other, depending upon what interpretation or construction the court would come up with at the end of the trial.

Weyrauch, Richardson on Contracts (p. 269): £< To establish the nature and effect of contract obligations, modern courts apply rules of construction and interpretation to agreements brought before them for adjudication. Interpretation consists of an evaluation of words and a decision as to their meaning. Construction is broader. It embraces a determination of the thoughts and intentions of the parties as gathered from the entire course of their dealings. The judicial objective is to get a view of the contract as a whole, in the light of all of its constituent parts, and then to apply it in the terms of public policy. See Corbin, Conditions in the Law of Contracts, 28 Yale L. J. 739; cf. Restatement, Contracts, Chap. 9, Topic 1.”

The disputed issues arising from the contract were the cause of bickering and no little confusion, even at the trial. As one hears so often when faced with a complex state of affairs, £ 1 There ought to be an easier way of running this railroad. ’ ’ To arrive at a satisfactory conclusion, some analysis and references to the contract are necessary. When, as in this case, the commission embodies by reference in the contract the specifications of the Department of Public Works which consist of a printed volume of almost 500 pages, and upon which it intends to place major reliance, it should not insert upon its plans any partial excerpts of any of its provisions affecting any item of the contract but, rather, should either refer to the appropriate [488]*488subdivision of the said specifications or quote it in full on the plans or, with good grace and to avoid litigation, should accept its own modification of the contract which, being specific, evidences the positive intent of the parties and takes precedence over the general specifications. (Young Fehlhaber Pile Co. v. State of New York, 265 App. Div. 61.)

In this case it seems to the court that the commission’s representatives want to eat their cake and keep it, too. What is the claimant to do when in the contract the State incorporates by reference all the aforesaid specifications of the Department of Public Works but, in the same contract, it sets forth: “ All materials to be furnished and all work to be performed under items of .the State specifications will be covered by and shall be in conformity with Parts II, III and IV of the State specifications, except those items that are otherwise modified on the plans or in this section.”

What does the State expect of the contractor when the plans modify the Department of Public Works specifications by eliminating the important last portion of the provision regarding unsuitable materials and rely only on the first sentence thereof, which states: Unsuitable materials shall be used for flattening embankment slopes and where otherwise directed by the engineer”. This habit of preparing important public contracts can only result in uncertainty as to the precise nature of the obligations incurred thereunder.

As a result of the above and other admixtures of intent to be referred to hereafter, the representatives of both sides on the job hardly agreed on the manner of carrying out any item of the work. For example, the contract provides woke ” in the penalty clause of the contract. The defendants’ engineering consultant advised the claimant after certain delays that it would be charged engineering charges, and it was — the sum of $6,213 was arbitrarily deducted without even a discussion as to its exactness, much less its justification. The State was wrong twice, the first time when it inserted “ none ” in the contract, and the second time, when it deducted the engineering charges. (10 N. Y. Jur., Contracts, § 205.)

The contract also provides that the staking out of the utility pole lines shall be made by the New York State Electric and Glas Company, shall conform to its standards and be acceptable .to it as well as the engineer. It was staked out by the responsible engineer of the electric company but the defendants changed it, resulting in more lateral clearing and grubbing work by the claimant of some 20 to 50 feet along 2,500 feet of line, which extra item is disputed by the defendants. The reason the defend[489]*489ants give for not accepting the company’s staking of the line was esthetic and emotional. It appears that the general manager of the Taconic Parkway wanted the wires hidden among the trees, and proceeded to remove those stakes upon which the hid was based and laid out his own stakes “ by eye.”

As the court reads the contract, and as far as the claimant was concerned, that job was the utility company’s and the claimant was required to do its bidding, especially since the staking followed the lines marked on the plans. As a matter of fact, in the preparation of its bid, the claimant had consulted Mr. Brown, the engineer of the electric company, as to the proposed line the poles would follow. The direction given claimant by Mr. Brown was the basis of its bid and became later the direction first grubbed and cleared.

Then, there are many points of direct contradiction between both sides as to what was done and when and why. These witnesses seemed to me to be reputable people.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Camarco Contractors, Inc. v. State
22 A.D.2d 833 (Appellate Division of the Supreme Court of New York, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
40 Misc. 2d 486, 243 N.Y.S.2d 240, 1963 N.Y. Misc. LEXIS 1757, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camarco-contractors-inc-v-state-nyclaimsct-1963.