Calvin Paul Williams v. Vincent Alexander

CourtLouisiana Court of Appeal
DecidedDecember 6, 2017
DocketCA-0017-0436
StatusUnknown

This text of Calvin Paul Williams v. Vincent Alexander (Calvin Paul Williams v. Vincent Alexander) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calvin Paul Williams v. Vincent Alexander, (La. Ct. App. 2017).

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

CA 17-436 consolidated with CA 17-437

CALVIN PAUL WILLIAMS

VERSUS

VINCENT ALEXANDER

**********

APPEAL FROM THE BREAUX BRIDGE CITY COURT PARISH OF ST. MARTIN, NO. 16-260 C/W NO. 16-270 HONORABLE RANDY P. ANGELLE, CITY COURT JUDGE

CANDYCE G. PERRET JUDGE

Court composed of Elizabeth A. Pickett, John E. Conery, and Candyce G. Perret, Judges.

AFFIRMED. Randy M. Guidry Durio, McGoffin, Stagg & Ackermann P. O. Box 51308 Lafayette, LA 70505 (337) 233-0300 COUNSEL FOR APPELLANT: Vincent Alexander

Calvin Paul Williams 417 Martin St. Breaux Bridge, LA 70517 (404) 823-7348 APPELLEE, In Proper Person PERRET, Judge.

This appeal involves two consolidated cases regarding a construction

contract. The contractor, Calvin Paul Williams (Mr. Williams), filed a Statement

of Claims asserting he is owed money by Vincent Alexander (Mr. Alexander) for

work he performed under a construction contract. Mr. Alexander denied any

money was owed and, instead, filed suit seeking money damages for breach of

contract. The trial court rendered judgment in favor of Mr. Williams for $1,125.00

with legal interest from date of judicial demand plus all costs of the proceedings,

and dismissed the suit filed by Mr. Alexander. Mr. Alexander now appeals. Mr.

Williams did not answer the appeal. Finding no manifest error, we affirm.

ISSUE FOR REVIEW

This court must decide whether the trial court erred in finding that Mr.

Williams performed the construction contract in a good, workmanlike manner, free

from defects in either materials or workmanship and thus was entitled to payment

per the contract.

FACTUAL AND PROCEDURAL HISTORY

Appellant, Mr. Alexander, entered into a contract with appellee, Mr.

Williams on June 13, 2016, to perform certain repairs to a building located at 360

Cannery Road, Breaux Bridge, Louisiana. The construction contract included

carpentry, electrical, and plumbing work. The agreed upon price for the work was

$2,750.00. Mr. Alexander partially paid Mr. Williams in advance for the work.

Subsequently, Mr. Williams contends that he completed the work pursuant

to the agreement. However, Mr. Alexander alleges that Mr. Williams‘ work was

sub-par and incomplete. After becoming dissatisfied with the work, Mr. Alexander consulted and

hired other contractors to repair the defects. At the time, Mr. Alexander had

partially paid Mr. Williams up front for the job, but stopped payment on the final

check for the amount of $1,150.00 when he became dissatisfied with Mr.

Williams‘s work.

Mr. Williams thereafter filed a Statement of Claim and Citation alleging the

work for which he was hired was completed, yet full payment had not been made.

Mr. Williams asserts that he was hired to provide installation and electrical work

for Mr. Alexander. Mr. Williams states that, after completing the work requested,

Mr. Alexander checked the work and wrote him a check for the remainder of the

amount owed under the contract. However, a stop payment was later issued on this

check by Mr. Alexander. In support of his claim, Mr. Williams attached the

purchase order for the work.

Likewise, Mr. Alexander also filed suit seeking money damages for breach

of contract. Mr. Alexander alleges that Mr. Williams‘s workmanship was faulty,

requiring him to hire other contractors to finish and fix the work Mr. Williams was

originally hired to do. Consequently, Mr. Alexander claims he incurred additional

costs to repair the problems caused by Mr. Williams‘s faulty work.

Mr. Alexander requested and the court agreed to consolidate both suits.

At the trial, both parties presented their claims pro se. There is no dispute

that Mr. Williams and Mr. Alexander entered into a contract for contractor work.

The testimony evidenced an agreement between the parties for certain work to be

performed for the amount of $2,750.00. The work agreed upon was detailed in a

purchase order and included: the installation of a three compartment sink,

relocation of a washer and dryer hook up, installation of an electric hook up for a

2 stove, installation of a long neck hood for a stove, installation of a receptacle for a

stove, installation of a small sink and wash tub, relocation of the hot water tank,

closure of a door, relocation of a door, and closure of the previous door opening.

Mr. Williams testified all the appliances were provided by Mr. Alexander,

including the stove hood. Mr. Williams agreed to install a long neck hood,

however, Mr. Alexander provided him with a hood that is installed under a cabinet.

Mr. Williams testified the long neck hood was necessary because cabinet doors

would not open due to a beam that was in the way. Mr. Williams also testified he

did not place the receptacle box for the hot water heater up top where Mr.

Alexander wanted it because he could not do so safely. Instead, he put the

receptacle box lower, where it would not be near a sink, causing a safety hazard.

Mr. Williams testified he completed all the tasks required of him in the contract.

Mr. Williams introduced the purchase orders he and Mr. Alexander agreed on, as

well as blueprints showing the location of the washer and dryer, the sink, and the

type of stove hood to be installed.

Mr. Alexander presented testimony from Larry Carmouche, a contractor he

hired after Mr. Williams. Mr. Carmouche testified he refinished sheetrock work,

screwed a three compartment sink into the wall so it would be sturdier, and closed

a hole or window opening with vinyl sheeting for Mr. Alexander. Although Mr.

Alexander alleges Mr. Williams failed to install the three compartment sink, Mr.

Carmouche testified the three compartment sink was already installed when he

arrived. Mr. Carmouche further testified he did not see any leakage from the sink.

Mr. Carmouche did testify that the cabinets above the stove hood would not open

because of a beam. Therefore, Mr. Carmouche lowered the cabinets so the doors

would open. Mr. Carmouche also testified the door installed by Mr. Williams was

3 operable, it would open and close, but it appeared to be leaning slightly. Mr.

Carmouche was not asked to fix the door.

Mr. Alexander also presented Ozer Alexander, an electrician who worked on

the property after Mr. Williams. Mr. Ozer testified the water heater plug was too

low and, with the tank was against the wall, the receptacle box could not be

reached where it was currently located. Mr. Ozer also testified the stove required a

four-wire plug but only a three-wire plug was installed. The four prong receptacle

for the stove was acceptable, but the wire, a three prong wire, was not acceptable.

Mr. Ozer also testified the dryer could not be plugged in because the vent dryer

duct was in the way. The hole for that duct was also larger than the duct.

Mr. Alexander next presented Francis Alexander, a plumber. Mr. Francis

testified the work Mr. Williams completed would have worked, but that there were

leaks from the sink faucet. Mr. Francis also testified the drain was not properly

connected; therefore, the water would drain on the floor. Mr. Francis estimated the

fix would be twenty-five dollars ($25.00).

On October 10, 2016, the trial court ultimately ruled in favor of Mr.

Williams in open court, finding Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. AAA Brick Co., Inc.
386 So. 2d 987 (Louisiana Court of Appeal, 1980)
McCorvey v. McCorvey
922 So. 2d 694 (Louisiana Court of Appeal, 2006)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Neel v. O'QUINN
313 So. 2d 286 (Louisiana Court of Appeal, 1975)
Maxwell v. Cayse
54 So. 3d 118 (Louisiana Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Calvin Paul Williams v. Vincent Alexander, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calvin-paul-williams-v-vincent-alexander-lactapp-2017.