California Paving & Grading Co. v. Lincoln General Insurance

206 Cal. App. 4th 36, 141 Cal. Rptr. 3d 405, 2012 WL 1820921, 2012 Cal. App. LEXIS 595
CourtCalifornia Court of Appeal
DecidedMay 21, 2012
DocketNo. B228930
StatusPublished
Cited by3 cases

This text of 206 Cal. App. 4th 36 (California Paving & Grading Co. v. Lincoln General Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
California Paving & Grading Co. v. Lincoln General Insurance, 206 Cal. App. 4th 36, 141 Cal. Rptr. 3d 405, 2012 WL 1820921, 2012 Cal. App. LEXIS 595 (Cal. Ct. App. 2012).

Opinion

Opinion

KLEIN, P. J.

Plaintiff and appellant California Paving & Grading Co., Inc. (hereafter, Paving or plaintiff), a subcontractor, appeals a judgment of dismissal following the sustaining without leave of a demurrer interposed by [38]*38defendant and respondent Lincoln General Insurance Company (Lincoln) to Paving’s second amended complaint seeking recovery on a payment bond.

The essential issue presented is whether the instant contract was for public work or for private work. The proper characterization of the nature of the contract determines whether this action is governed by Civil Code section 3097 (preliminary 20-day notice for private work)1 or by section 3098 (preliminary 20-day notice for public work). The nature of the contract also determines whether Paving’s lawsuit is governed by the limitations period applicable to an action on a public works payment bond (§ 3249), or by a longer limitations period.

We conclude the instant subdivision improvement work constituted a “work of improvement contracted for by a public entity” and therefore amounted to a public work within the meaning of section 3100.

Paving failed to allege it served a preliminary notice in compliance with the statutory scheme applicable to payment bonds on public works. (§§ 3098, 3252.) Therefore, its action against Lincoln, the surety on the bond, is barred. Accordingly, the judgment of dismissal is affirmed.

FACTUAL AND PROCEDURAL BACKGROUND

1. Facts.2

This matter arises out of a subdivision improvement agreement and contract (the Agreement) between a private developer, 26 Moorpark LLC (Moorpark), and the City of Los Angeles (the City). As a condition for approval of the final map for Tract No. 65651, the Agreement required the subdivider, Moorpark, at its “own cost and expense, to construct and install all public improvements required in and adjoining and covered by the final map.” The Agreement estimated the cost of the improvements at $195,000, and required Moorpark to file or deposit “a good and sufficient PAYMENT SECURITY for labor and materials in an amount not less than fifty (50) percent” of the estimated cost of the improvements.

In accordance with the Agreement, Moorpark obtained a “subdivision labor and material payment bond” in the amount of $97,500 from Lincoln, the surety.

Moorpark entered into a prime contract with Masada Development, Inc. (Masada), a licensed general contractor, for the construction of the public improvements.

[39]*39Masada then entered into a subcontract with Paving, in the sum of $51,535, under which Paving agreed to perform street paving and asphalt work in connection with the public improvements, at the intersection of Wortser Street and Moorpark Street in Studio City.

On January 20, 2009, Paving completed its work but was not paid.

In June 2009, Paving filed suit against Moorpark and Masada to recover for the work it performed under the subcontract.

On October 29, 2009, Moorpark filed for bankruptcy. Masada likewise has filed for bankruptcy.

2. Proceedings.

a. Pleadings.

On March 12, 2010, Paving filed suit against Lincoln, the surety, to recover on the labor and material payment bond which Moorpark had filed with the City.

The operative second amended complaint pled a single cause of action. It alleged, inter alia, Paving was an intended beneficiary of the bond and was entitled to recover against Lincoln the sum of $55,958 plus interest thereon, from the completion date of January 20, 2009.

b. Lincoln’s demurrer.

Lincoln demurred to the second amended complaint on the ground it was barred by the applicable statute of limitations and therefore failed to state facts sufficient to state a cause of action. Lincoln’s arguments were twofold:

First, Paving failed to make a timely claim on the bond in accordance with section 3252. Lincoln asserted that to make a claim on a payment bond, a claim must give written notice to the principal and surety on the bond within 15 days after recordation of a notice of completion, or if no notice of completion has been recorded, within 75 days after completion of the work of improvement. Here, there was no allegation as to whether a notice of completion had been filed. However, Paving pled it completed the work on January 20, 2009. Thus, Paving had 75 days, until April 6, 2009, to make a claim to the surety on the bond. However, Paving did not make a written claim to Lincoln until it filed the instant lawsuit nearly one year later, on March 12, 2010.

[40]*40Lincoln further contended that more importantly, Paving failed to file its lawsuit within the prescribed statutory period. Lincoln asserted that pursuant to the statutory scheme, Paving had 90 days after completion of its work on January 20, 2009, to serve a stop notice. (§ 3184, subd. (b).) The deadline for filing a stop notice was April 20, 2009. Paving then had six months after the expiration of the period in which a stop notice may be filed, i.e., until October 20, 2009, to file suit against Lincoln. (§ 3249.) Therefore, Paving’s lawsuit against Lincoln, which was not filed until March 12, 2010, was time-barred.

c. Paving’s opposition to the demurrer.

In opposition, Paving contended the improvements for which the bond was issued are subdivision improvements, not a public work within the meaning of the Civil Code sections. Therefore, the payment bond is not a public works payment bond and the statute of limitations set forth in section 3249 does not apply to this action.

Paving reasoned that in the instant matter, the City entered into an agreement with Moorpark, a private developer, requiring Moorpark at its own expense to install improvements on publicly owned property; the City was not a party to the construction contract and the obligation to pay for the construction was that of Moorpark; and the construction work was not financed by public funds. Therefore, the subdivision improvement work was not a public works project within the meaning of section 3100, making section 3249’s limitations period inapplicable.

Paving took the position the applicable statute of limitations for filing suit on the bond is the four-year statute of limitations for a contract action under Code of Civil Procedure section 337, and therefore its action was clearly timely.

d. Hearing and ruling.

On October 8, 2010, the matter came on for hearing. After hearing argument of counsel, the trial court adopted its tentative ruling as the final ruling in the matter and sustained Lincoln’s demurrer to the second amended complaint without leave to amend. The trial court’s written ruling states in pertinent part:

“It appears from the face of the complaint that the action is barred by the limitations periods for filing claims and suits against sureties on payment bonds with respect to public works.
[41]*41“Plaintiffs written notice of the claim on the bond was untimely. At the very latest, plaintiff had 75 days from completion of the work of improvement to give the principal and surety on the bond written notice of a claim against the payment bond. [(§ 3252.)] . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Granite Construction v. Bond Safeguard Ins. CA3
California Court of Appeal, 2014
R&R Pipeline, Inc. v. Bond Safeguard Insurance
223 Cal. App. 4th 438 (California Court of Appeal, 2014)
Nissho of California, Inc. v. Bond Safeguard Insurance
220 Cal. App. 4th 974 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
206 Cal. App. 4th 36, 141 Cal. Rptr. 3d 405, 2012 WL 1820921, 2012 Cal. App. LEXIS 595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/california-paving-grading-co-v-lincoln-general-insurance-calctapp-2012.