California-American Water Co. v. Marina Coast Water Dist.

CourtCalifornia Court of Appeal
DecidedDecember 28, 2022
DocketA160662
StatusPublished

This text of California-American Water Co. v. Marina Coast Water Dist. (California-American Water Co. v. Marina Coast Water Dist.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
California-American Water Co. v. Marina Coast Water Dist., (Cal. Ct. App. 2022).

Opinion

Filed 12/28/22 CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION TWO

CALIFORNIA-AMERICAN WATER COMPANY et al., Plaintiffs and Appellants, A160662

v. (San Francisco County MARINA COAST WATER Super. Ct. No. CGC-15- DISTRICT, 546632) Defendant and Respondent.

Here, the third and fourth appeals in this case, we address two separate appeals by two separate plaintiffs from a summary judgment emanating from two separate summary adjudications against them. The first summary adjudication was based on the two-year statute of limitations, the second on the failure to comply with the claim-filing requirement in the Government Claims Act. The summary adjudications were entered in 2019, seven years after the first lawsuit among the parties was filed—and eight years after the parties spent some six months in formal and informal efforts attempting to resolve the issues between and among them. Our de novo review leads to the conclusion that both summary adjudications were errors and, therefore, so was the judgment. We thus reverse.

1 BACKGROUND 1 The Parties and the General Setting The appeals here involve two separate appellants: Monterey County Water Resources Agency (Monterey) and California-American Water Company (Cal-Am). Both appeals have the same respondent: Marina Coast Water Company (Marina). Appellant Monterey is an independent public agency created by the Monterey Coast Water Resources Act (MCWRA ) (Water Code, Appendix, Chapter 52), responsible for analyzing water resources in Monterey County. Monterey has a dual governing board structure consisting of the elected Monterey County Board of Supervisors and a Board of Directors appointed by the Board of Supervisors. The appointed Board is responsible for the actual operation of the agency, approving and executing contracts and formulating recommendations to the Board of Supervisors on matters within the scope of the Supervisors’ duties. It also has final authority on most operational and administrative matters. Appellant Cal-Am is an investor-owned water utility regulated by the California PUC, providing water to over 100,000 residents on the Monterey Peninsula, including Carmel-by the-Sea, Monterey, Pacific Grove, Seaside,

1 Much of the background is taken from the opinion of Division One of this court in the first appeal in this case: California-American Water Co. v. Marina Coast Water District (2016) 2 Cal.App.5th 748 (Cal-Am One). Other facts are from decision No. 10-12-016 by the Public Utilities Commission (PUC) in proceeding No. 04-09-019. (See In the Matter of the Application of California-American Water Company (U210W) for a Certificate of Public Convenience and Necessity to Construct and Operate its Coastal Water Project to Resolve the Long-Term Water Supply Deficit in its Monterey District and to Recover All Present and Future Costs in Connection Therewith in Rates, 2010 Cal. PUC LEXIS 548 (Dec. 2, 2010).

2 Del Rey Oaks, and Sand City, as well as various unincorporated areas of Monterey County. Respondent Marina is a public agency formed in 1960 under the County Water District law to provide water for the City of Marina and neighboring communities on the Monterey Peninsula. A fourth entity involved, though not a party in either appeal, is RMC Water and Environment (RMC). For many years, an adequate and sustainable source of potable water was a problem on the Monterey Peninsula. And in 1995 the State Water Resources Control Board (SWRCB) issued an Order (No. WR 95-10) to Cal- Am to stop drawing water from the Carmel River and develop an alternate water supply. The Order led to years of discussions, and culminated in late 2009 when Marina, Monterey, and Cal-Am reached agreement on a plan to develop and construct a regional desalinization project designed to extract brackish water from beneath Monterey Bay, purify it, and deliver it to consumers (“RDP” or “the project”). The project was to replace the Carmel River as a water supply, and in furtherance of the project, the parties entered into five interrelated agreements that came to be referred to as the RDP Agreements, specifically: (1) A “Reimbursement Agreement,” entered into in February and March 2010, under which Cal-Am agreed to reimburse Marina and Monterey their costs in pursuing the RDP, subject to later repayments or forgiveness. (2) A “Water Purchase Agreement” (WPA), entered into on April 6, 2010, which provided for the financing and construction of the various facilities.

3 (3) A “Settlement Agreement,” also entered into on April 6, which established a process for proposing the desalination project to the PUC for approval. (4) A “Project Management Agreement,” entered into on January 11, 2011, under which RMC was selected as the project manager; and (5) A “Credit-Line Agreement,” also entered into on January 11, which established a line of credit to Monterey and Marina to minimize their project-related finances. Meanwhile, while some of the above agreements were still being negotiated and executed, in December 2010, the PUC approved the project, (Cal-Am One, supra, 2 Cal.App.5th at p. 753), approval that was a condition precedent to it. 2 Meanwhile, in January 2010, Marina hired Stephen Collins who sought to facilitate approval of the project by the PUC, including by working on the draft WPA. Our colleagues described Collins’s involvement in more detail: “Stephen Collins was a member of Monterey’s appointed board of directors when the RDP agreements were being negotiated and, in some cases, entered into. Starting in January 2010, he also was a paid consultant for RMC to advocate for the agreements through a contract he had with Marina. RMC ultimately paid Collins $160,000 for his work. At a February 2011 meeting of Monterey’s board of directors, Collins exposed his potential conflict of interest by recusing himself from a vote on the selection of RMC as the manager of the desalination project. Local media began reporting on the possible conflict of interest, and an investigation followed. Collins resigned

2The project was never built, and to this day a replacement water supply has not been completed.

4 from Monterey’s board of directors on April 1, 2011.” (Cal-Am One, supra, 2 Cal.App.5th at p. 753.) 3 On July 7, 2011, Monterey’s outside counsel, Kevin O’Brien, sent a letter to Marina and Cal-Am expressing the opinion the RDP Agreements were void as a consequence of Collins’s financial interest in the Project. Cal- Am then gave notice the RDP Agreements were terminated. Marina, Monterey, and Cal-Am thereafter engaged in months of negotiation and mediation in an attempt to resolve the future of the project, efforts that included several mediation sessions at JAMS and with an Administrative Law Judge at the PUC, and various private sessions. These efforts continued, off and on, for several months, finally ending on January 16, 2012 without resolution. On January 25, Mark Fogelman, Marina’s outside counsel, e-mailed the parties noting “[t]he mediation is over” and declaring “the parties should be free to pursue their legal remedies.” And in a later e-mail, Mr. Fogelman further represented that Marina had “no objection” to the parties being able to raise in court any and all “issues and legal claims” referred to in the parties’ pre-mediation correspondence or other issues “reasonably related” to such issues and claims. Despite that, uncertainty surrounded the parties’ pre-lawsuit discussions: Marina insisted the parties were obligated to comply with the dispute resolution procedure in the WPA; Monterey disagreed, but

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiCampli-Mintz v. County of Santa Clara
289 P.3d 884 (California Supreme Court, 2012)
Waller v. Truck Insurance Exchange, Inc.
900 P.2d 619 (California Supreme Court, 1995)
Norgart v. Upjohn Co.
981 P.2d 79 (California Supreme Court, 1999)
City of Ukiah v. Fones
410 P.2d 369 (California Supreme Court, 1966)
Blanton v. Womancare, Inc.
696 P.2d 645 (California Supreme Court, 1985)
McDanels v. General Insurance Co. of America
36 P.2d 829 (California Court of Appeal, 1934)
DeBerard Properties, Ltd. v. Lim
976 P.2d 843 (California Supreme Court, 1999)
City of San Jose v. Superior Court
525 P.2d 701 (California Supreme Court, 1974)
Davies v. Krasna
535 P.2d 1161 (California Supreme Court, 1975)
Jolly v. Eli Lilly & Co.
751 P.2d 923 (California Supreme Court, 1988)
Redsted v. Weiss
163 P.2d 105 (California Court of Appeal, 1945)
Adams v. Paul
904 P.2d 1205 (California Supreme Court, 1995)
Neel v. Magana, Olney, Levy, Cathcart & Gelfand
491 P.2d 421 (California Supreme Court, 1971)
Budd v. Nixen
491 P.2d 433 (California Supreme Court, 1971)
United Community Church v. Garcin
231 Cal. App. 3d 327 (California Court of Appeal, 1991)
People Ex Rel. Department of Parks & Recreation v. West-A-Rama, Inc.
35 Cal. App. 3d 786 (California Court of Appeal, 1973)
Leaf v. City of San Mateo
104 Cal. App. 3d 398 (California Court of Appeal, 1980)
Enfield v. Hunt
91 Cal. App. 3d 417 (California Court of Appeal, 1979)
Turner v. State of California
232 Cal. App. 3d 883 (California Court of Appeal, 1991)
White v. Superior Court
225 Cal. App. 3d 1505 (California Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
California-American Water Co. v. Marina Coast Water Dist., Counsel Stack Legal Research, https://law.counselstack.com/opinion/california-american-water-co-v-marina-coast-water-dist-calctapp-2022.