Calabro Const. Co., Inc. v. Hamilton Twp.

25 A.2d 515, 131 N.J. Eq. 1, 1941 N.J. Ch. LEXIS 31, 30 Backes 1
CourtNew Jersey Court of Chancery
DecidedJuly 25, 1941
DocketDocket 129/500
StatusPublished
Cited by1 cases

This text of 25 A.2d 515 (Calabro Const. Co., Inc. v. Hamilton Twp.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calabro Const. Co., Inc. v. Hamilton Twp., 25 A.2d 515, 131 N.J. Eq. 1, 1941 N.J. Ch. LEXIS 31, 30 Backes 1 (N.J. Ct. App. 1941).

Opinion

This is a suit under the Municipal Mechanics Lien Act, — R.S.2:60-180 et seq., brought by complainant, as subcontractor under Spiniello Construction Co. on a contract between that company as contractor and the Township of Hamilton, for the construction of a certain sewer. Defendant Standard Accident Insurance Co. is the surety on the performance bond of the contractor, Spiniello Co.

The suit involved, inter alia, a determination of the amount actually due and unpaid from the Township to the contractor, — the Township admitting that $71,378.40 was due and denying liability for any greater sum, whereas the Spiniello Co. claimed an additional amount of about $133,000 over and above the $71,378.40 admitted by the Township.

During the course of the proceedings it developed that there was no issue between the Spiniello Co. (nor its surety) and any of the lien claimants, and by agreement, and without prejudice as to the issues between the contractor and the Township, the latter paid over to the surety company the said sum of $71,378.40, and the surety paid all the lien claimants in full.

There is a counter-claim by the surety against the contractor for some $73,000 or more expended by the surety for the account of the contractor — based on the duty of the contractor to indemnify or reimburse the surety and on certain assignments made by the contractor to the surety of the moneys due or to grow due from the Township to the contractor.

There presently remains for determination, first, the amount due from the Township to the contractor; second, the amount due from the contractor to the surety; third, the amount of allowance to be made to the original complainant for costs and counsel fee; and fourth, the question of costs and counsel fees as between or among the Township, the contractor and *Page 4 the surety. Of these, the second and fourth have not been argued, — and indeed the proofs are not complete in regard to the second.

The main issue is therefore the amount due to the contractor. The lump sum contract price was $478,900. It was contended by the contractor and the surety (see the answers to interrogatories) that the contractor became entitled to additional compensation for extra work and materials in the following items and amounts:

1. Vitrified Pipe Risers .........................     $1,166.00
2. Stone or gravel ...............................        208.00
3. Relaying 15 inch pipe on Right of Way .........      1,237.37
4. House Connections .............................      2,977.24
5. "Extra Work Items Allowed"
      a. Lumber .....................   $14,547.60
      b. Other items ................    25,943.88
                                        __________     40,491.48
6. Additional lumber .............................    114.174.90
7. Six inch under-drain ..........................      5,457.50
                                                     ___________
                                                     $165,712.49
Of these the Township conceded that item 5-b $25,943.88, but contested all the others; and also counter-claimed against the contractor for $5,350 for liquidated damages under the contract for delay in completing the contract.

Toward the conclusion of the testimony a compromise was agreed upon by the parties as to items 1, 2, 3 and 4, whereby the Township admitted liability for one-half the amount of these items, or $2,794.30, and the contractor and surety waived claim for the other half.

The Township therefore admits that a total of $507,638.18 became due to the contractor. Concededly $510,069.01 has been paid to or for the account of the contractor, (which includes the $71,378.40 paid without prejudice after bill filed, as aforesaid). The Township claims therefore that there has been an overpayment of $2,430.83, and that this sum, together with the $5,350 damages claimed for delay, (or a total of $7,780.83) should be repaid by the contractor and/or the surety.

The contractor and surety on the other hand deny liability for the $5,350; and they claim that there became due to the *Page 5 contractor, in addition to the $507,638.18, admitted by the Township as above set forth, the sum of $134,180 (being items 5a, 6 and 7 in the list hereinbefore set forth), or a total of $641,818.18, and that there is still due after deducting the payments of $510,069.01 already made, the sum of $131,749.17.

We have then the claims of the contractor (a) for lumber, $14,547.60; (b) for additional lumber, $114,174.90; (c) for under-drain, $5,457.50; and (d) the claim of the Township for $5,350 for delay.

Taking these up in inverse order; — it is deemed that the Township is not entitled to its claim for the $5,350. This is based on clauses in the contract documents providing for the assessment of liquidated damages at $50 per day for each day of delay in completion of the work. While contracts as to liquidated damages are enforceable where such damages are not a penalty but are really agreed on as being a fair and reasonable figure for actual damages not readily susceptible of exact ascertainment or proof, and while the contractor did not complete within the time specified by the contract and subsequent extensions, nevertheless it does not appear that there was any actual damage whatever from this delay, — indeed it is tacitly conceded that there was no such damage. This contract was one of several interrelated contracts involving a sewer system, and it would not have been possible for this sewer to be used prior to the completion of other contracts, even if this one had been completed earlier. Moreover the letter sent to Spiniello Co. by the architects and engineers on May 13th, 1940, was from an equitable point of view, tantamount to a statement that this sewer would be regarded as completed within time, if completed by May 31st, 1940; and it was completed on May 30th, 1940.

Next as to the contractor's claim for under-drains. Testimony on behalf of the contractor is that 4,366 lineal feet of six-inch tile underdrain was furnished and installed by the contractor at certain specified portions of the sewer. This testimony is not contradicted. The contractor's contention is that this material and labor was extra, — not comprised in the general contract, and that compensation should be paid *Page 6 therefor by the Township, at the rate of $1.25 per foot (which concededly is the rate specified in the contract for extra work of this particular kind, when duly authorized.

The contract, Exhibit DS-1, on page 46 under the heading of "Equalizing Beds," contains the following provision:

"When running water, hard clay, sandstone, shale or other unyielding or unstable trench bottom is encountered, the pipe shall be laid on an equalizing bed of gravel, broken stone, or sand as ordered by the Engineer, but not less than eight (8") inch depth, measured directly under the outside center of the pipe, and extended to a height of one-third (1/3) of the internal diameter of the pipe, measured from the invert bottom. TheEngineer may direct that four (4") or six (6") inch Vitrified Farm Drain Tile or Porous Concrete Drain Pipe be placed in a gravel or broken stone equalizing bed if in his opinion he deemsit necessary. These items and quantities shall be furnished at the unit prices bid as an addition to the lump sum bid." (Italics supplied.)

The evidence shows that at the several places where the contractor claims this six-inch tile drain was put in, there was running water and unstable trench bottom, and written orders for the placing of equalizing beds of gravel were given by the engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westmount Country Club v. Kameny
197 A.2d 379 (New Jersey Superior Court App Division, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
25 A.2d 515, 131 N.J. Eq. 1, 1941 N.J. Ch. LEXIS 31, 30 Backes 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calabro-const-co-inc-v-hamilton-twp-njch-1941.