Calabrian Chemicals Corp. v. Bailey-Buchanan Masonry, Inc.

44 S.W.3d 276, 46 U.C.C. Rep. Serv. 2d (West) 778, 2001 Tex. App. LEXIS 3102, 2001 WL 497399
CourtCourt of Appeals of Texas
DecidedMay 10, 2001
Docket09-00-373 CV
StatusPublished
Cited by3 cases

This text of 44 S.W.3d 276 (Calabrian Chemicals Corp. v. Bailey-Buchanan Masonry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calabrian Chemicals Corp. v. Bailey-Buchanan Masonry, Inc., 44 S.W.3d 276, 46 U.C.C. Rep. Serv. 2d (West) 778, 2001 Tex. App. LEXIS 3102, 2001 WL 497399 (Tex. Ct. App. 2001).

Opinion

OPINION

GAULTNEY, Justice.

Appellee Bailey-Buchanan Masonry, Inc. (“Bailey”) sued appellant Calabrian Chemicals Corporation (“Calabrian”) to recover damages under a building contract and to foreclose on a mechanic’s lien. The jury found that Calabrian did not comply with its agreement with Bailey, but nonetheless returned a verdict of zero damages. After both Bailey and Calabrian filed post-verdict motions, the trial court granted Bailey’s motion to disregard the jury findings of $0 for both damages and attorney’s *278 fees and, in effect, denied Calabrian’s motion to enter judgment on the jury verdict. The trial court then made its own affirmative findings on damages and attorney’s fees and entered judgment in favor of Bailey. On appeal we are asked by Calabrian to reinstate the jury findings in its favor or, in the alternative, to grant a new trial. We reverse the trial court’s judgment and order a new trial.

The Dispute

Bailey worked on the construction of a concrete block building in 1998-99 for Cal-abrian. The terms of the agreement between the parties are the subject of this dispute. Bailey claims it agreed to do the work on a time and material basis. Calab-rian agrees with that characterization of the agreement, but also maintains there was an additional term agreed to by the parties — namely a $68,000 cap. The record reveals that Bailey’s invoices exceeded the $68,000 cap. The record also reveals that Bailey cashed a Calabrian check on which was typed the notation “final payment.” With the $68,000 having been paid to Bailey and no additional payments forthcoming, Bailey sued Calabrian for breach of contract, fraud, and DTPA violations, and sought foreclosure of a mechanic’s lien.

The BACKGROUND Facts

The dispute is clear-cut, as presented through the testimony of the two people who negotiated the agreement: Robert Bailey, the president of Bailey-Buchanan Masonry, Inc., swore the agreement he negotiated with Kate Block was time and material only — with no cap; Kate Block, Calabrian’s purchasing agent, swore the agreement was time and material — with a $68,000 cap. Both Bailey and Block agreed they had at least four conversations in 1998 about the project — one in August 1998, and the others on September 30, October 23, and October 28,1998.

The August Conversation: During the August conversation, Block asked Bailey to begin work on the building and to construct the first three rows of brick. After the three rows of brick were laid, and while other work on the project was being done by other contractors, Bailey left the job. Both Block and Bailey agreed that this phase of the work was on a time and material basis only. That work, from August 18 — 26, 1998, was completed and Bailey was paid for the work.

The September BO Conversation: On September 30, 1998, Kate Block again called Bailey. According to Robert Bailey, Kate Block asked him to fax her his original bid ($112,700) on the project; the bid had been rejected and she had lost her copy. Bailey claimed he and Kate Block did not talk about any percentage breakdown on the job or any change in the agreement concerning payment.

Kate Block’s account of the September 30 conversation is different. She testified she called Bailey and asked him for “a quote, another bid ... [a] not to exceed [bid], to do the second part of the building.” According to Kate Block, Robert Bailey told her during their September 30 conversation to subtract the $9,285.64 that Calabrian already had paid him for the first completed phase of the project from the original bid, and then use a 65/35 split to obtain the remaining bid. This division would permit Bailey to receive 65 percent for his labor; Calabrian would be responsible for the material, about 35 percent.

The October 23 Conversation: As with the accounts of their September 30 conversation, the parties’ descriptions of the October 23 conversation differ markedly. According to Bailey, Kate Block called and told him to return to work on the project. He indicated she never mentioned any *279 change in the way he would be paid. When Block brought up a 65/35 breakdown, he told her it would take him a few days to figure it out. Bailey indicated Block did not actually want a specific breakdown on the job. Bailey testified there was no change of terms; he understood they were still working under the same purchase order number. He further indicated there was no discussion about a “cost not to exceed” basis for the job. In response to Block’s call, Bailey resumed work on the project.

According to Kate Block, Benny Deters (Calabrian’s plant manager) instructed her to call Bailey on October 23 and firm up the deal. During the October 23 conversation, she went over the terms with Bailey again: (a) the 65/35 split (that she says Bailey suggested in their September 30 conversation) and (b) the time and material basis of the job with a cap of $68,000. She testified she wrote up that same day a purchase order (number 10356) reflecting their conversation. On its face, the purchase order states as follows:

“This project is done on time basis, but not to exceed $68,000.00. Calabrian to furnish materials, Bailey to furnish rental equipment & concrete.... ”

Block stated she gave Bailey the purchase order number by phone on October 23. According to both Bailey and Block, Bailey resumed work on Monday, October 26, 1998.

The October 28 Conversation: Both Kate Block and Robert Bailey testified that Block faxed the purchase order to Bailey on Wednesday, October 28. Upon receipt of the purchase order, Bailey immediately telephoned Block because he was surprised at the “not to exceed number” language on the purchase order. He claims she told him that the purchase order was an “in-house need on [Calabrian’s] part,” and that they needed to put a limit on the purchase order amount. According to Bailey, Block also told him that the actual amount of the project would be different, and that Calabrian would later make out a second and then third purchase order. He indicated this procedure had been followed on an earlier job. Bailey emphasized that he did not agree to provide labor other than on a time and material basis, and that there was never any suggestion that the internal cap of $68,000 would be binding upon him. Nevertheless, after their conversation ended Bailey instructed his secretary, Belinda Faulk, to make note of when the project reached the $51,000 level so that he could inform Cal-abrian he was reaching the limit on the purchase order.

Like Bailey, Kate Block testified she faxed purchase order 10356 to Bailey on Wednesday, October 28,1998. She agreed that Bailey telephoned her that same day and told her he was not going to guarantee the cost of $68,000 on the job. However, Block testified Bailey did not tell her there was no way he would do the work for $68,000. She indicated that if Bailey had told her there was no way he was going to do the work for $68,000, she would have gone to Deters about it and Bailey probably would have left the job.

Kate Block testified that Valerie Randall, a Calabrian employee in accounts payable, informed her in early January 1999 that Bailey’s invoices exceeded the $68,000 cap.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
44 S.W.3d 276, 46 U.C.C. Rep. Serv. 2d (West) 778, 2001 Tex. App. LEXIS 3102, 2001 WL 497399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calabrian-chemicals-corp-v-bailey-buchanan-masonry-inc-texapp-2001.