Cajun Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission, Louisiana Public Service Commission, Intervenors

66 F.3d 364, 314 U.S. App. D.C. 235, 1995 U.S. App. LEXIS 27944
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 6, 1995
Docket94-1556
StatusPublished

This text of 66 F.3d 364 (Cajun Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission, Louisiana Public Service Commission, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cajun Electric Power Cooperative, Inc. v. Federal Energy Regulatory Commission, Louisiana Public Service Commission, Intervenors, 66 F.3d 364, 314 U.S. App. D.C. 235, 1995 U.S. App. LEXIS 27944 (D.C. Cir. 1995).

Opinion

SILBERMAN, Circuit Judge:

This case returns after remand. Cajun Electric Power Cooperative, Inc., a cooperative composed of electric utilities, again petitions challenging the Federal Energy Regulatory Commission’s interpretation of a contract between Cajun and a competing utility which was filed as a rate schedule with the FERC. This time we deny the petition.

I.

The background of this dispute is described in our prior opinion. Cajun Elec. Power Coop., Inc. v. FERC, 924 F.2d 1132 (D.C.Cir.1991). Cajun and Gulf States Utilities Company disagree as to the meaning of a 1980 amendment to a power integration agreement (PIA). Cajun argues that this clause obliges Gulf States to deliver electricity to Cajun’s members at any point reached by Gulf States’ transmission system whether or not it is off a Cajun member’s integrated system (traditional area of service). 1 One of Cajun’s members sought to provide electricity to customers (presumably at a lower price) who are located off that member’s integrated system. Gulf States, owning the transmis *366 sion system and objecting to what it perceived as an attempted sortie into its service area, refused.

Before the amendment, Gulf States’ obligation to provide transmission services to Cajun was limited by the following provision:

To assure the applicability of all the standards and conditions for transmission hereunder, ... it is agreed that for purposes of this Service Schedule, all delivery points initially included in Exhibit “A” of Rate Schedule CSTS and added by mutual agreement of the parties shall be limited to delivery points on an integrated part of the system of a rural electric cooperative ... which is an active member of [Cajun],

Section 5.1 (emphasis added). The amendment, which was added to the PIA without any change in Section 5.1, provides that:

If the parties fail to reach mutual agreement for [Gulf States] to furnish additional points of delivery or increases in capacity for whatever reasons, then [Cajun] shall have the option of providing the necessary distribution and transmission facilities to interconnect with [Gulf States’] existing transmission system at mutually agreeable points, subject to appropriate approvals and certifications by any regulatory authorities having jurisdiction. [Gulf States] shall have the right to contest such interconnection in any regulatory proceeding and otherwise.

Section 3.3(d) (emphasis added).

FERC originally concluded that these clauses unambiguously supported Gulf States’ interpretation. We easily rejected that conclusion as unsupportable; whatever one’s view of this agreement, unambiguous it is not. The confusion is, of course, created by the second reference to mutual agreement in Section 3.3(d) (“mutually agreeable points”). Cajun claims that this phrase enables Gulf States to refuse to provide delivery points off a member’s integrated system only based on engineering considerations. Gulf States contends, on the other hand, that Section 3.3(d) does not compel it to provide service off a Cajun member’s integrated system. That can occur only if Gulf States subsequently agrees. In that respect, Section 5.1 still governs. Section 3.3(d) did expand Gulf States’ obligation to provide a delivery point to Cajun members by requiring Gulf States to provide, or allowing Cajun to construct, new delivery points to accommodate more than a normal load increase on a member’s integrated system.

Neither interpretation flows naturally out of the language of the agreement. Cajun’s limitation on the phrase “mutually agreeable points” in Section 3.3(d) is not apparent, and Gulf States’ limitation on the phrase “for whatever reasons” to exclude a Cajun member’s desire to force Gulf States to deliver electricity beyond the member’s integrated system is, similarly, not apparent.

II.

We previously rejected FERC’s rather incredible determination that the contract was unambiguous and therefore remanded so that Cajun could show the parties’ intent through evidence of the bargaining history. We stated that “[i]f after these proceedings it still can be said that the parties never meant squarely to address the issue raised by this dispute, then the Commission is entitled to place its own construction on the resultant ambiguity — so long as it is reasonable.” 924 F.2d at 1137; see also National Fuel Gas Supply Corp. v. FERC, 811 F.2d 1563, 1568-70 (D.C.Cir.), cert. denied, 484 U.S. 869, 108 S.Ct. 200, 98 L.Ed.2d 151 (1987) (holding that FERC’s interpretation of a settlement agreement between the Commission’s staff and a private party was entitled to Chevron deference). Although petitioner now claims that the Commission’s interpretation should not be afforded deference because the language clearly supports its interpretation, we do not take that argument any more seriously than we did the original FERC position. Nor do we think much of petitioner’s claim that FERC must assert a specific public policy supporting its interpretation before it is entitled to deference. National Fuel Gas Supply was not so limited. So long as FERC adequately explains why it interprets the contract as it does, we assume that its explanation is drawn from its statutory responsibility and experience.

*367 The Commission, on remand, sent the case to an ALJ for an evidentiary hearing. After extensive testimony, the ALJ concluded that Cajun failed to meet its burden that the parties had intended Cajun’s interpretation— and the Commission affirmed his findings. It is not necessary to review those findings in detail. Essentially, the ALJ determined that even if Cajun (supported by the Rural Electrification Administration) 2 had affirmatively wished to gain the right it now claims it obtained — in return for helping Gulf States to finance a nuclear power plant that would provide electricity to both Gulf States and Cajun — Gulf States never agreed to it. The ALJ concluded the negotiating parties used euphemisms to dance around this issue, which, if it had been forthrightly addressed, might have broken the deal.

As the ALJ (and the Commission) noted, the negotiations took place against a backdrop in which the disputed issue had been highlighted. Once, before the negotiations which led to the amendment, in July 1973, Cajun had requested a delivery point to serve a customer, Cortina Mall, which was four miles away from the integrated system of Cajun member Dixie. Gulf States had rejected that request, stating that “the point is not geographically located on the system of Dixie.” Cajun was told that Gulf States would never give Cajun’s members the right to tap into its transmission system at will. Cajun informed Gulf States that this was not its intent. 59 F.E.R.C. at 65, 177. That position is certainly understandable. The ALJ and the Commission thus concluded that if Cajun had actually gained such a major concession in the subsequent negotiations, it would have been clearly spelled out. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
66 F.3d 364, 314 U.S. App. D.C. 235, 1995 U.S. App. LEXIS 27944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cajun-electric-power-cooperative-inc-v-federal-energy-regulatory-cadc-1995.