Cain v. Whiston

137 P.2d 479, 58 Cal. App. 2d 738, 1943 Cal. App. LEXIS 105
CourtCalifornia Court of Appeal
DecidedMay 24, 1943
DocketCiv. 3085
StatusPublished
Cited by4 cases

This text of 137 P.2d 479 (Cain v. Whiston) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cain v. Whiston, 137 P.2d 479, 58 Cal. App. 2d 738, 1943 Cal. App. LEXIS 105 (Cal. Ct. App. 1943).

Opinion

BARNARD, P. J.

This is an appeal from a judgment decreeing foreclosure of a mechanic’s lien.

On August 8, 1940, the West Coast Improvement Company leased five acres of land which it owned to E. L. Cord for the purpose of drilling for oil. On the same day, Cord entered into a written agreement with H. L. Whiston which provided that Whiston was to install a derrick and drilling rig, with the necessary material and equipment, and drill an oil well on this land. A day or two later Whiston entered into an oral agreement with the plaintiffs under which the plaintiffs agreed to move a certain derrick and drilling rig onto this property and install it for the sum of $1,741 and to furnish certain labor and materials necessary in constructing the cement foundation work and certain pipe racks. The court found that this labor and materials were furnished and were of the reasonable value of $419.48. The derrick and drilling rig belonged to Whiston and was then situated on other premises some twenty miles away. The removal of the same to the land in question and its installation there involved its dismantling at the place where it was situated, moving it to this land and reconstructing it there.

On August 12, 1940, West Coast Improvement Company and Cord first learned that the plaintiffs were furnishing this labor and materials. On August 14, 1940, each of them posted on the property a notice of nonresponsihility in proper form, and copies of these were recorded on August 15, 1940. On November 13, 1940, the plaintiffs recorded a notice of lien covering the labor and materials above referred to and on December 14, 1940, they recorded an amended notice of lien correcting an error in the legal description of the five acres on which the drilling rig was installed. This action followed and the defendants West Coast Improvement Company and *741 E. L. Cord have appealed from the judgment entered in favor of the plaintiffs and decreeing, as against these defendants, that the plaintiffs have a lien upon the oil well rig and equipment and upon the oil well drilled therewith, and that the improvement be sold for the purpose of satisfying said lien.

It is first contended that the complaint fails to state a cause of action because it seeks a general lien under the first paragraph of section 1183 of the Code of Civil Procedure. It is argued that there can be no general lien on improvements placed upon oil property and that the mining lien provided for in the second paragraph of section 1183 covers only labor and materials furnished in the subtractive process of actually working the mine. The complaint alleged that this derrick and rig constituted an improvement upon this real property and that the described real property is necessary for the convenient occupation and use of this improvement. The prayer was for a lien upon said improvement and upon the land or such portion thereof as was reasonably required for the convenient use and occupation of the improvement. There is no evidence that the property was acquired under the mining laws, and the prayer was for a general lien. In the absence of supporting evidence we cannot assume as against the judgment that the property was a mining claim as such property is technically known under the mining laws. At the time the labor and materials in question were furnished there was no oil well upon this property and the drilling of such a well had not been commenced. Although this improvement was later used in drilling an oil well the labor and materials were not furnished while any mining operations were being carried on. We are unable to agree with the proposition that the respondents are entitled to no relief under section 1183. The cases cited by the appellant in support of their contention, that the only way a lien can be established upon an oil well itself is through a mining lien under the provisions of the second paragraph of section 1183, are not controlling here. While the court decreed a lien also on the oil well itself there is no evidence to support that part of the judgment and it may be eliminated without affecting the other part of the judgment. In our opinion, the complaint states a cause of action and the general lien provisions of the first paragraph of section 1183 are applicable.

It is contended that the first notice of lien filed on *742 November 13, 1940, was filed more than ninety days after the completion of the work in question and was, therefore, ineffective for any purpose. In support of this contention the appellants argue that it appears from the testimony of certain witnesses that the work in question was started on or before August 1, 1940, that certain “man days” were required for the work, and that by a mathematical computation it appears that the work must have been completed on or before August 14, 1940. The most that can be said is that there is a conflict in the evidence in this regard. The court found that the work and materials furnished by the respondents were not completed and furnished prior to August 15, 1940, and that the same were furnished and completed on or about August 26, 1940. These findings are supported by the evidence. One of the respondents testified that the agreement with Whiston for furnishing this labor and material was entered into between August 8 and August 10, that the work was started on August 10 or shortly thereafter, and that it was completed on August 31. The last invoice for materials, which is dated August 26, 1940, bears upon it a notation signed by the foreman “Received in good order.”

The appellants urge that the evidence does not support the amount found to be due to the respondents and that the respondents forfeited all right to a lien by falsely stating the work and services performed and the amount due. It seems to be argued that everything done by the respondents was under their agreement with Whiston to be done and furnished for the flat price of $1,741, that the actual hauling of the equipment from a location twenty miles away to the land in question was done by Whiston, that the respondents are claiming a lien for this service which they did not perform, and that they are also claiming the value of materials furnished when these were included in the contract price. Assuming, but not holding, that a part of the evidence would justify this contention the evidence, in its entirety, supports the finding made in this regard. It is further argued in this connection that the amount for which the lien was allowed included the cost of dismantling this derrick and rig on the property on which it was situated some twenty miles away, and that this is a nonlienable item since the statute only allows a lien for labor and materials furnished in connection with an improvement on the land where the improve- *743 merit is erected. No cases are cited on this point and we know of no reason or principle supporting this contention. It was desired to remove a drilling rig owned by Whiston to the land in question. This involved dismantling the rig at one point and reconstructing it after it had been moved. The reconstructed rig constituted the improvement with which we are concerned. Apparently the dismantling of the rig in the former location was either a necessary or convenient prerequisite to its reconstruction in a new location. It appears from the evidence that it was cheaper to do this than to purchase a new drilling rig. The work of dismantling was a proper part of, and contributed to, the construction of the improvement on the premises in question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halbert's Lumber, Inc. v. Lucky Stores, Inc.
6 Cal. App. 4th 1233 (California Court of Appeal, 1992)
Coates v. Shell Western E & P, Inc.
5 Cal. App. 4th 904 (California Court of Appeal, 1992)
Borello v. Eichler Homes, Inc.
221 Cal. App. 2d 487 (California Court of Appeal, 1963)
Ott Hardware Co. v. Yost
69 Cal. App. 2d 593 (California Court of Appeal, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
137 P.2d 479, 58 Cal. App. 2d 738, 1943 Cal. App. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cain-v-whiston-calctapp-1943.