Cable & Connector Warehouse, Inc. v. Omnimark, Inc.

700 So. 2d 1273, 96 La.App. 4 Cir. 2831, 1997 La. App. LEXIS 2248, 1997 WL 576316
CourtLouisiana Court of Appeal
DecidedSeptember 12, 1997
DocketNo. 96-CA-2831
StatusPublished

This text of 700 So. 2d 1273 (Cable & Connector Warehouse, Inc. v. Omnimark, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cable & Connector Warehouse, Inc. v. Omnimark, Inc., 700 So. 2d 1273, 96 La.App. 4 Cir. 2831, 1997 La. App. LEXIS 2248, 1997 WL 576316 (La. Ct. App. 1997).

Opinions

I! ARMSTRONG, Judge.

This is a suit brought under the Private Works Act, La. R.S. 9:4801 et seq, and other legal theories by an unpaid supplier of materials that were ultimately used in a construction project. The defendant prime contractor on the construction project, and its co-defendant surety, moved for summary judgment on the ground that the plaintiff was a supplier to a supplier, rather than a supplier to a contractor or subcontractor, and thus had no rights under the Private Works Act and on the ground that no other legal theory was applicable so as to allow the plaintiff recovery under the facts of this case. The trial court agreed with the defendants and granted the summary judgment. The plaintiff appeals. The judgment of the trial court is correct. In light of the facts which are uncontested or as to which there is no genuine issue, the plaintiff has no rights under the Private Works Act and the other legal theories urged by the plaintiff are without merit. Therefore, we affirm.

W.S. Bellows Construction Company contracted to act as general contractor to build out (i.e. complete the interior for tenant occupancy) a number of floors hof the CNG Tower building in New Orleans. The space was to be occupied by McDermott and the project was variously described by the parties as the “CNG Tower job” and the “McDermott job.”

Bellows subcontracted with the Sandoz Group, Inc. for installation of cabling for the computer system. Under that subcontract, Sandoz was to supply all the necessary cabling material.

Sandoz purchased the necessary cabling materials for the job from Omnimark, Inc. In turn, Omnimark had purchased the cabling materials from plaintiff Cable & Connector Warehouse, Inc. Sandoz and Omnimark were owned by the same person, Louis Sandoz, but were separate corporations.

Before beginning its on-site work, Sandoz invoiced Bellows for $112,066.23. The invoice states that $100,066.23 is for “pre-pur-chased materials” and $12,000 is for “professional fees for project design work-to-date.” It is undisputed that the $100,066.23 was for all of the materials for the Sandoz subcontract with Bellows and that these were the materials which Sandoz purchased from Om-nimark and which Omnimark purchased from Cable & Connector. Bellows first inspected the cabling materials, which were located at Cable & Connector’s facility in Baton Rouge, and then paid the Sandoz invoice. However, while Sandoz was paid in full for the cabling materials by Bellows, Sandoz did not pay Omnimark and Omnimark did not pay Cable & Connector.

Cable & Connector shipped the cabling materials to the CNG Tower job site in several shipments over the course of several weeks. At or about the time of each shipment, Cable & Connector rendered an invoice for the materials shipped. Other than invoices which were solely for freight charges, there were nine Cable & Connector invoices. Each one of those nine invoices states that the materials |3are “sold to” “Om-nimark, Inc./CNG Towers.” Some of the invoices state “ship to” “The Sandoz Group/Omnimark,” one states “ship to” Bellows and several state “ship to” “will call Bill Knock.”

At some point in the project, Bellows terminated Sandoz as subcontractor because Sandoz’ license was not in order. Bellows had Hi-Tech Electric, Inc., which was an electrical subcontractor already working on the CNG Tower project, complete the work that had been subcontracted to Sandoz. However, Sandoz continued in some sort of advisory capacity to assist Hi-Tech and Bellows to finish the job.

Cable & Connector was never paid for the cabling materials and recorded a Private Works Act lien against the CNG Tower Building. Bellows obtained a surety bond from Federal Insurance Company which was deposited with the Recorder of Mortgages so as to cancel Cable & Connector’s lien. Cable & Connector sued Omnimark, Sandoz, Bellows, and Federal. The summary judgment appealed from dismissed Cable & Connector’s suit only as against Bellows and Federal.

Because this case comes before us on an appeal from a summary judgment, we must determine whether there was any genuine issue of material fact and whether the mover [1275]*1275was entitled to judgment as a matter of law. See La.Code Civ. Proe. art. 966(B); see also 1997 La. Acts 483 (amending Article 966); Hayes v. Autin, No. 96-287 (La.App. 3rd Cir. 12/26/96), 685 So.2d 691, 694-95 (cited in Act 483), writ denied, No. 97-C-0281 (La.3/14/97), 690 So.2d 41.

A key legal point which impacts the issues and arguments in this case is that, while a supplier to a subcontractor or a contractor has certain rights under the Private Works Act, a supplier to a supplier does not have such rights under that [4statute. Put another way, in order to have rights under the Private Works Act, a supplier must sell directly to a subcontractor or a contractor. This arises from the statute’s language granting rights to “Sellers, for the price of movables sold to a contractor or a subcontractor.” La. R.S. 9:4802(A)(3). See generally Leonard B. Hebert, Jr. & Co. v. Kinler, 336 So.2d 922, 924 (La.App. 4th Cir.1976) in which the court stated: “Under the settled law of this State, a materialman who furnishes material to a materialman has no right to a lien.” Because .Cable & Connector sold cabling to another supplier (Omnimark), rather than to a subcontractor (Sandoz) or to a contractor (Bellows), Cable & Connector has no rights under the Private Works Act. Cable & Connector recognizes this legal rule but in an attempt to avoid its application advances a number of arguments, each of which will be discussed below.

Another legal rule that is of importance to some of the issues in this case is that, in a sale transaction, ownership of the things sold is transferred even if there has not yet been payment or delivery. A sale is perfected as soon as there is agreement between the buyer and seller as to the thing sold and the price. La. Civ.Code art. 2439. “Ownership is transferred between the parties as soon as there is agreement on the thing and the price is fixed, even though the thing sold is not yet delivered nor the price paid.” La. Civ.Code art. 2456. In the present case, the purchase of the cabling materials from Cable & Connector was made by Omnimark using a purchase order on an Omnimark letterhead. Thus, the sale of the cabling materials by Cable & Connector to Omnimark, and the transfer of ownership of the cabling materials from Cable & Connector to Omnimark, was accomplished before the materials were shipped by Cable & Connector and before Cable & Connector rendered invoices for the cabling materials. This is of some | gimportance because some of Cable & Connector’s arguments are either explicitly or implicitly premised on the notion that the cabling materials were not sold until they were shipped and invoices were rendered by Cable & Connector.

Cable & Connector’s first argument is that Bellows and Hi-Tech (the subcontractor who completed the cabling work after Sandoz was terminated) actually purchased most of the cabling material and, because that would constitute a sale to a contractor or subcontractor, Cable & Connector has rights under the Private Works Act as well as a contract claim against Bellows (Hi-Tech is not a party to this case).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Royal Const. Co., Inc. v. Sias
496 So. 2d 1301 (Louisiana Court of Appeal, 1986)
Meunier v. Pizzo
696 So. 2d 610 (Louisiana Court of Appeal, 1997)
LEONARD B. HERBERT, JR. & CO., INC. v. Kinler
336 So. 2d 922 (Louisiana Court of Appeal, 1976)
Daniel v. Blaine Kern Artists, Inc.
681 So. 2d 19 (Louisiana Court of Appeal, 1996)
Hayes v. Autin
685 So. 2d 691 (Louisiana Court of Appeal, 1996)
Walker v. Kroop
678 So. 2d 580 (Louisiana Court of Appeal, 1996)
Fruge v. Muffoletto
137 So. 2d 336 (Supreme Court of Louisiana, 1962)
Oakley v. Thebault
684 So. 2d 488 (Louisiana Court of Appeal, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
700 So. 2d 1273, 96 La.App. 4 Cir. 2831, 1997 La. App. LEXIS 2248, 1997 WL 576316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cable-connector-warehouse-inc-v-omnimark-inc-lactapp-1997.