C3 Communications, LLC v. Gigabit Technologies, LLC

CourtCourt of Appeals of Texas
DecidedJuly 15, 2021
Docket14-19-00730-CV
StatusPublished

This text of C3 Communications, LLC v. Gigabit Technologies, LLC (C3 Communications, LLC v. Gigabit Technologies, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C3 Communications, LLC v. Gigabit Technologies, LLC, (Tex. Ct. App. 2021).

Opinion

Reversed and Rendered and Memorandum Opinion filed July 15, 2021.

In The

Fourteenth Court of Appeals

NO. 14-19-00730-CV

C3 COMMUNICATIONS, LLC, Appellant

V. GIGABIT TECHNOLOGIES, LLC, Appellee

On Appeal from the 55th District Court Harris County, Texas Trial Court Cause No. 2017-63042

MEMORANDUM OPINION

Appellee Gigabit Technologies, LLC (“Gigabit”) sued appellant C3 Communications, LLC (“C3”) for amounts allegedly owed pursuant to three agreements. After a bench trial, the trial court rendered judgment in favor of Gigabit and awarded it $62,139.73 in damages. For the reasons below, we reverse the trial court’s final judgment and render judgment in Gigabit’s favor in the amount of $31,474.57. BACKGROUND

Procedural History

C3 entered into a subcontract with Gigabit to replace certain data cables at the Shriners Children’s Texas hospital in Galveston. During the project, Gigabit sent C3 one “Budgetary Estimate” and two “Change Orders” delineating the work required to complete the project and the price for that work. After C3 failed to remit the total amount owed under the Budgetary Estimate and Change Orders, Gigabit sued C3 and asserted claims for breach of contract and fraud.1 The parties proceeded to a bench trial in March 2019.

Evidence at Trial

Stephan Sanchez works in Gigabit’s operations logistics department and was the first witness to testify at trial. Sanchez testified that Gigabit was contacted by Jonathan Ferrell, C3’s owner and operator, with respect to the Shriners project. According to Sanchez, Shriners wanted to update their network’s data system to newer technology.

Sanchez said he and Ferrell conducted a walk-through of the Shriners facility, during which the scope of the project was discussed. Afterwards, Sanchez said Gigabit sent C3 a Budgetary Estimate. The Budgetary Estimate was admitted into evidence; it is dated April 25, 2016, and includes a description of the work to be done as well as a price for each item. The total cost included in the Budgetary Estimate is $165,897.15. Discussing the Budgetary Estimate, Sanchez said Gigabit was “not allowed to exceed the scope of this job without an additional contractual agreement by and between [Gigabit] and C3.”

1 Gigabit also asserted claims against Fibernet Engineering, Inc., the company that hired C3 to complete the Shriners Hospital project. At trial, the trial court granted Fibernet’s motion for directed verdict on Gigabit’s claims. Gigabit did not appeal this ruling and Fibernet is not a party to this appeal.

2 According to Sanchez, Gigabit received a purchase order from C3 that included a description of the project and the project’s total cost in response to the Budgetary Estimate. Sanchez testified that Gigabit began the Shriners project in October 2016. Admitted into evidence was a November 2016 check from C3 to Gigabit for $82,948.58 — approximately half of the price listed in the Budgetary Estimate.

Sanchez testified that, during the project, “some out-of-scope work” came up that was “outside of [Gigabit’s] estimate.” Specifically, Sanchez said the hospital received an influx of patients that delayed Gigabit’s completion of its work. Sanchez said he discussed the delay with Ferrell as well as its changes to Gigabit’s estimate of the project’s total cost:

Mr. Ferrell and I had a conversation saying there was additional time on the job; there was stuff that we cannot plan for, emergencies, so forth. [Ferrell] said, put it in a work order; send it over to me, the change order. And [Ferrell] would push it through to Mr. Farouk,2 and we would just keep on going. [Ferrell] was like, don’t stop. We’ve got to get the project completed.

Sanchez testified that a second incident arose that caused additional changes to the project’s estimated cost. According to Sanchez, Gigabit had to remove extra cables from the Shriners hospital that were not included in the original estimate. Sanchez said he spoke with Ferrell about this additional work and Ferrell told him “write it down, keep going forward, we have to finish the project; and then [Ferrell] would proceed on his side and get back with [Gigabit] on that.” According to Sanchez, Ferrell “wasn’t happy” about the cost of the additional work but instructed Gigabit to proceed.

2 Farouk Mohammed is the president of Fibernet Engineering, Inc., the company that contracted with C3 to complete the Shriners project.

3 Sanchez testified that Gigabit issued two Change Orders with respect to these additional charges. Both Change Orders were issued after the work was completed and are dated January 26, 2017. Change Order #1 lists $9,880.72 in charges and includes the following summary of the work performed:

Down Time/Patch Cords/6th Floor Ladder Tray This Change Order is for all Downtime that was [sic] occurred on the job that wasn’t expected or included on the bid. Waiting on Keys, Permission to enter restricted areas, Permits, Dock Access, Skin Rank, Patient’s [sic] from Mexico. Tech Support, Fabricating Patch cords Elevators were shut down do [sic] to a fire across the street at UTMB. Their Patience [sic] were transferred to Shriners. Change Order #2 lists $20,784.44 in charges and includes the following summary of the work performed:

Demo extra Cables that where [sic] not included in the original scope of work. Demo all existing station cables that are in place from the floor to the IDF closet. Cables were not removed from the 110 Blocks. All work is performed after hours. And some work will be done with a containment Unit.

Both Change Orders include a line stating “Acceptance & Notice to Proceed” followed by a space labeled “Signature”. Neither Change Order is signed.

Also admitted into evidence was a January 30, 2017 email exchange between Sanchez and Ferrell. In the first email, Sanchez sends Ferrell both Change Orders and states: “Change Order [#2] is for the Demo of the existing cables. Change order [#1] is for Down Time . . . (i.e. explosion in Mexico delaying our work progress .. plus), Patch Cords, 6th floor Ladder Tray and More.” In response, Ferrell said:

4 You’re telling me that Shriners will be expecting a change order for down time etc for almost $10K and be ok with that? And I sent you the pic of my original prints/notes where it showed the ladder in MDF was discussed and to be included. If you missed [the] 5th floor, that’s not my issue. 6th floor, MDF floor, clearly states 2 sets of materials which acknowledges it was to be done. I think it was simply forgotten. And your requested change order for the demo is almost unrealistic. In your proposal to me, it states Gigabit will demo all existing cabling. This is why Shriners does not find it to be a change order. I’m willing to help out, out of my own pocket, but $20K is unrealistic.

In response, Sanchez replied:

Sir the demo was never in G.T. estimate for the Phone side and you know that only the DATA .. You told me that it was between you and Farouk. That you didn’t agree with him on the demo but you told me that you were going to have to pay for it out of your pocket . . . . Do you remember that conversation? You shouldn’t be surprised with the amount of the change order. You told me on the phone that it was going to be a big change order. Yes Shriners should be expecting a change order.

Finally, Ferrell replied in part: I’m not disagreeing with you that it wasn’t very clear, but like I told you during our conversation, I see both sides. Unfortunately, Shriners goes by what’s written in the proposals. Which yours and mine said demo of all existing cabling. Read it again. I’m willing to pay a reasonable amount to go back and demo because of the unclarity of the situation. It’s simply out of the goodness of my heart. Brass tax, I don’t have to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Service Corp. International v. Guerra
348 S.W.3d 221 (Texas Supreme Court, 2011)
Fort Worth Independent School District v. City of Fort Worth
22 S.W.3d 831 (Texas Supreme Court, 2000)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Mabon Ltd. v. Afri-Carib Enterprises, Inc.
29 S.W.3d 291 (Court of Appeals of Texas, 2000)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Pace Corporation v. Jackson
284 S.W.2d 340 (Texas Supreme Court, 1955)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Parker Drilling Co. v. Romfor Supply Co.
316 S.W.3d 68 (Court of Appeals of Texas, 2010)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
T.O. Stanley Boot Co. v. Bank of El Paso
847 S.W.2d 218 (Texas Supreme Court, 1993)
Donwerth v. Preston II Chrysler-Dodge, Inc.
775 S.W.2d 634 (Texas Supreme Court, 1989)
2001 Trinity Fund, LLC v. Carrizo Oil & Gas, Inc.
393 S.W.3d 442 (Court of Appeals of Texas, 2012)
New York Party Shuttle, LLC v. John Bilello
414 S.W.3d 206 (Court of Appeals of Texas, 2013)
Michael S. Land v. Stephanie Anne Land
561 S.W.3d 624 (Court of Appeals of Texas, 2018)
Frontier Logistics, L.P. v. National Property Holdings, L.P.
417 S.W.3d 656 (Court of Appeals of Texas, 2013)
MKM Engineers, Inc. v. Guzder
476 S.W.3d 770 (Court of Appeals of Texas, 2015)
Fischer v. CTMI, L.L.C.
479 S.W.3d 231 (Texas Supreme Court, 2016)
In the Interest of S.M.H.
523 S.W.3d 783 (Court of Appeals of Texas, 2017)
Yazdani-Beioky v. Sharifan
550 S.W.3d 808 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
C3 Communications, LLC v. Gigabit Technologies, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c3-communications-llc-v-gigabit-technologies-llc-texapp-2021.