C. W. Stark Lumber Co. v. Sether

257 N.W.2d 556, 1977 Minn. LEXIS 1443
CourtSupreme Court of Minnesota
DecidedAugust 5, 1977
Docket47170
StatusPublished
Cited by8 cases

This text of 257 N.W.2d 556 (C. W. Stark Lumber Co. v. Sether) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. W. Stark Lumber Co. v. Sether, 257 N.W.2d 556, 1977 Minn. LEXIS 1443 (Mich. 1977).

Opinion

YETKA, Justice.

This is an action to foreclose a mechanics lien by a materialman who supplied lumber to a construction company, which at the time of the first delivery of materials was the vendor in an unrecorded executory contract for the sale of real property. The construction company used the lumber to construct a house on land which it then sold to the vendees. The construction company failed to pay the materialman, who thereafter sought to foreclose a mechanics lien. The trial court granted the vendees’ motion for partial summary judgment on the grounds that the materialman had failed to give the vendees notice pursuant to “owners” notice provision of Minn.St. 514.011, subd. 2. The materialman appeals from the judgment subsequently entered. We affirm.

The issue on appeal is whether the “owners” notice provision of the mechanics lien statute applies to a vendee of an unrecorded executory contract for the sale of real property when the materialman contracts directly with the contractor-vendor.

In November 1971, Alene J. and Arthur A. Heaton sold a parcel of land to Amber Construction, Inc. (Amber), by an unrecorded contract for deed. On May 5, 1974, Amber entered into a building contract with Wayne K. and Patricia J. Sether to build a two-story, three-bedroom house and garage on the property. Appellant supplied *558 lumber for the construction valued at $7,616.78 to Amber from August 1, 1974, to February 6, 1975. On November 27, 1974, Aleñe Heaton, then an unmarried woman, conveyed the land to Amber by warranty deed. Two days later, Amber in turn conveyed the land by warranty deed to the Sethers, the present fee owners. On December 6, 1974, Amber and the Sethers closed the sale of the property. Amber presented a forged lien waiver purportedly executed by appellant to the Sethers and received the mortgage proceeds. The two deeds transferring title were recorded on December 23, 1974. Amber failed to pay appellant and subsequently became insolvent. Appellant filed a mechanics lien on the property on April 22, 1975. When appellant brought an action to foreclose the lien, the Sethers brought a motion for a partial summary judgment dismissing the mechanics lien foreclosure. The trial court granted the motion on the grounds that the Sethers were equitable owners of the property at the time appellant first supplied his materials on August 1,1974, and that appellant’s failure to notify the Sethers pursuant to § 514.011, subd. 2, prevented him from perfecting his lien.

At the time appellant first supplied lumber to Amber on August 1, 1974, the record title was in the name of Aleñe Heaton. Further, Amber had entered into an unrecorded contract for deed with Heaton and had entered into a building contract with the Sethers. The threshold question is whether this gave the Sethers an equitable interest in the land. Appellant argues that it did not and that the Sethers thus did not qualify as “owners” under § 514.011, subd. 2. Instead, appellant contends the building contract merely constituted an option to purchase and thus conveyed no interest in the land. See, Shaughnessy v. Eidsmo, 222 Minn. 141, 145, 23 N.W.2d 362, 365 (1946).

The trial court found that an equitable interest in the property existed. Under the mechanics lien statute the principal concern is whether there is an estate in land upon which a mechanics lien could attach. Equitable as well as legal interest may be included. See, e. g., Atkins v. Little, 17 Minn. 342 (Gil. 320) (1871); Carey-Lombard Lumber Co. v. Bierbauer, 76 Minn. 434, 79 N.W. 541 (1899). Because the equitable interest the Sethers had in the land could be the subject of an action for specific performance, they qualify as holders of an interest in the land for purposes of the mechanics lien statute.

The more troublesome question presented is whether the “owners” notice provision of § 514.011, subd. 2, applies to a vendee of an unrecorded executory contract for the sale of property when the material-man contracts directly with the contractor-vendor. The statutory requirements of § 514.011, subd. 2, do not apply to a party “under direct contract with the owner.” Thus, appellant argues that it had a direct contract with Amber, which was acting as an owner and not as a general contractor, and that it therefore was not required to give notice to the Sethers. Whether a mechanics lien may affect the interest of a vendee under an executory contract depends on whether the materialman is a subcontractor or a principal contractor; that is, whether Amber by agreeing to construct a building on its land and then to convey the land and the building to the vendees changed its status from an owner (in which case appellant would be a principal contractor) to a general contractor (in which case appellant would be a subcontractor). There are no Minnesota cases on this point, and the cases from other jurisdictions are mixed. See, Annotation, 50 A.L.R.3d 944; 53 Am.Jur.2d, Mechanics’ Liens, § 123; 57 C.J.S., Mechanics’ Liens, § 71.

To understand the issue, § 514.011 must be considered. The statute provides:

“Subdivision 1. Every person who enters into a contract with the owner for the improvement of real property and who has contracted or will contract with any subcontractors or materialmen to provide labor, skill or materials for the improvement shall give the owner the notice required in this subdivision. The notice shall be delivered personally or by certified mail to the owner or his autho *559 rized agent within ten days after the contract for the work of improvement is agreed upon. The notice shall be in at least 10-point bold type, if printed, or in capital letters, if typewritten and shall state as follows:
“(a) Persons or companies furnishing labor or materials for the improvement of real property may enforce a lien upon the improved land if they are not paid for their contributions, even if such parties have no direct contractual relationship with the owner;
“(b) Minnesota law permits the owner to withhold from his contractor so much of the contract price as may be necessary to meet the demands of all other lien claimants, pay directly such liens and deduct the cost thereof from the contract price, or withhold amounts from his contractor until the expiration of 90 days from the completion of such improvement unless the contractor furnishes to the owner waivers of claims for mechanics’ liens signed by persons who furnished any labor or material for the improvement and who provided the owner with timely notice.
“A person who fails to provide the notice shall not have the lien and remedy provided by this chapter.
“The notice required by this subdivision is not required of any person who is himself an owner of the improved real estate, to any corporate contractor of which the owner of the improved real estate is an officer or controlling shareholder, to any contractor who is an officer or controlling shareholder of a corporation which is the owner of the improved real estate, or to any corporate contractor managed or controlled by substantially the same persons who manage or control a corporation which is the owner of the improved real estate.
“Subd. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Automated Building Components, Inc. v. New Horizon Homes, Inc.
514 N.W.2d 826 (Court of Appeals of Minnesota, 1994)
Marque Plumbing, Inc. v. Barris
380 N.W.2d 174 (Court of Appeals of Minnesota, 1986)
Louie's Floor Covering, Inc. v. DePhillips Interests, Ltd.
378 N.W.2d 923 (Supreme Court of Iowa, 1985)
Mill City Heating & Air Conditioning Co. v. Nelson
351 N.W.2d 362 (Supreme Court of Minnesota, 1984)
MILL CITY HEATING & AIR CONDITION. v. Nelson
351 N.W.2d 362 (Supreme Court of Minnesota, 1984)
Dolder v. Griffin
323 N.W.2d 773 (Supreme Court of Minnesota, 1982)
Minnesota Wood Specialties, Inc. v. Mattson
274 N.W.2d 116 (Supreme Court of Minnesota, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
257 N.W.2d 556, 1977 Minn. LEXIS 1443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-w-stark-lumber-co-v-sether-minn-1977.