C. W. Jackson & Associates, Inc. v. Brooks

415 A.2d 640, 46 Md. App. 63, 1980 Md. App. LEXIS 299
CourtCourt of Special Appeals of Maryland
DecidedJune 16, 1980
Docket1271, September Term, 1979
StatusPublished
Cited by4 cases

This text of 415 A.2d 640 (C. W. Jackson & Associates, Inc. v. Brooks) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. W. Jackson & Associates, Inc. v. Brooks, 415 A.2d 640, 46 Md. App. 63, 1980 Md. App. LEXIS 299 (Md. Ct. App. 1980).

Opinion

Wilner, J.,

delivered the opinion of the Court.

Appellant requested the Circuit Court for Baltimore County to modify certain provisions of an arbitration award, and the court did so. The modification made was not what appellant had in mind, or desired, however, and so it now claims that the court had no power to make the modification. We agree.

The controversy arises out of a construction contract dated October 6, 1972, under which appellant, the contractor, agreed to build a sales and service facility for appellee, 1 an automobile dealer. A host of complaints arose from the contract — charges and counter-charges involving appellant, one or more of its subcontractors, appellee, and appellee’s architect and engineer. Pursuant to the architect’s and construction contracts, and interim court rulings not especially relevant here, the disputes were submitted to arbitration in two stages. Stage I — that with which we are concerned in this proceeding — involved the claims and counterclaims between appellant and appellee; disputes involving the architect were reserved for Stage II.

The arbitration proceeding was protracted and lengthy. Hearings commenced in April, 1976, and, after a substantial hiatus, were concluded on October 15, 1977 — a year and a half later. The initial award was rendered on November 15, 1977, and was delivered to the parties within a day or two thereafter.

*65 The arbitrator took as a starting point the unpaid contract price of $177,292.79, against which he considered the credits claimed by appellee for various errors and deficiencies on the part of appellant, and the amounts claimed by appellant for interest and extra work done. One of the claims made by appellee — the one that forms the basis of this proceeding — was that the ductwork on or about the roof of the building was improperly installed and, as installed, did not meet specifications. The arbitrator agreed that this was so, concluding that appellant "clearly failed to fully meet the specifications in regard to this work.”

There were three complicating features with respect to this claim. First, the engineer employed by appellee’s architect — Henry Adams, Inc. — had approved the installation, notwithstanding the deficiencies; second, appellee had obtained widely varying estimates as to the cost of correcting the problem, ranging from $750 to $15,400; and, third, the corrective measures had to be coordinated with other repairs and improvements required to be made to the roof. On the other hand, the subcontractor that was generally responsible for installation of the ductwork — Mills & Sons, Inc. — conceded that the installation was improper and agreed in writing to make all -necessary repairs to the satisfaction of Adams at its own expense.

The arbitrator considered Mills’ offer as "a fair manner in which to resolve the problem” provided that the work was done expeditiously — within 120 days — and was certified by Adams, and he adopted that remedy. Taking account of the complicating features noted above, he also provided (in relevant part):

"It will be necessary for Mills to coordinate its work with that of the roofer employed by Brooks and should it fail to do so, its work shall not be deemed satisfactory. Allowance has been made to Brooks for the cost of roofing work in Item A.l.b. infra, and, in order to obtain a fully satisfactory result, Brooks will have to arrange with Adams or Mills to have whatever roofing work needs to be *66 done in conjunction with Mills’ work carried out concurrently with it.
"Brooks shall be entitled to withhold $16,000 from the amount otherwise due Jackson under this Award until either (1) Mills declines to do the work as specified herein, in which case it shall.so notify Brooks in writing within fifteen days of the date of this Award and Brooks shall be entitled to retain the $16,000 or (2) Mills performs the work within the time specified herein and Adams certifies that it is satisfactory in writing, at which time said amount shall be paid over to Jackson. Should Mills perform the work within the time allowed, but Adams fail or refuse to certify that it is satisfactory, Jackson shall have the right to apply either to the Circuit Court for Baltimore County or to this arbitrator for determination of whether Adams’ certification was unreasonably withheld. Should the court or arbitrator find that such certification was unreasonably withheld, Jackson shall be entitled to receive from Brooks not only the principal sum of $16,000 but also interest thereon at the rate of 8% per annum, from the date of this Award plus his costs and attorneys’ fees attendant upon the collection of such money.” (Emphasis supplied.)

The arbitrator also ruled, of course, on the other matters in controversy; the problems with the ductwork and the roof were not the only issues attempted to be resolved in the award.

Appellee was the first to express dissatisfaction with the award; on December 14, 1977 (60 days after rendition of the award), it filed a petition in the Circuit Court for Baltimore County claiming that the arbitrator erred in failing to award damages to appellee and in awarding an amount to appellant for extended supervision costs. Appellee made no *67 complaint about that part of the award dealing with the roof or the ductwork; its petition was silent as to those matters. On January 4,1978, appellant filed an answer to the petition in which it denied the substantive allegations and asked that the award be confirmed. It made no reference in its answer to the ductwork or roofing repairs or to those parts of the award concerning them.

Five months later, appellant reversed field. On June 14, 1978, it filed a petition, in the same proceeding, to modify the award with respect to the $16,000 withheld in order to secure the ductwork repairs. Appellant recited that (1) under the award, the subcontractor Mills was to coordinate its repair work with the work to be done by appellee’s roofer, Bollinger; (2) the ductwork was to be completed by June 15, 1978; 2 and (3) Mills and appellant had been prevented from coordinating (and thus doing) the ductwork because of appellee’s failure to advise them with respect to the roof repairs. As a result, appellant asked that the court modify the award by requiring appellee to pay the $16,000 withheld from appellant and discharging appellant and Mills from any further responsibility in connection with the ductwork.

By the time these petitions came on for hearing in May, 1979, Mills was no longer in business. It ceased operation in December, 1978. Appellee defended against appellant’s request for payment of the $16,000 on the basis that, because neither Mills nor Adams were parties to the arbitration proceeding, the arbitrator had exceeded his authority in assigning them duties with respect to the ductwork. That part of the award, therefore, was alleged to be in error. Appellee asked that it be allowed to keep the $16,000 or, in the alternative, that appellant be ordered to make the ductwork repairs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Letke Security Contractors, Inc. v. United States Surety Co.
991 A.2d 1306 (Court of Special Appeals of Maryland, 2010)
Brzowski v. Maryland Home Improvement Commission
691 A.2d 699 (Court of Special Appeals of Maryland, 1997)
State Farm Mutual Automobile Insurance Co. v. Cabs, Inc.
751 P.2d 61 (Supreme Court of Colorado, 1988)
C. W. Jackson & Associates, Inc. v. Brooks
426 A.2d 378 (Court of Appeals of Maryland, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
415 A.2d 640, 46 Md. App. 63, 1980 Md. App. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-w-jackson-associates-inc-v-brooks-mdctspecapp-1980.