C. R. Meyer & Sons Co. v. Industrial Commission

217 N.W. 408, 194 Wis. 615, 1928 Wisc. LEXIS 38
CourtWisconsin Supreme Court
DecidedJanuary 10, 1928
StatusPublished
Cited by16 cases

This text of 217 N.W. 408 (C. R. Meyer & Sons Co. v. Industrial Commission) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. R. Meyer & Sons Co. v. Industrial Commission, 217 N.W. 408, 194 Wis. 615, 1928 Wisc. LEXIS 38 (Wis. 1928).

Opinion

Doerfler, J.

The question to be determined in this case is whether under the provisions of the written contract and of all the other facts and circumstances in the case Grady was an employee of the plaintiff and therefore entitled to compensation, or whether he was an independent contractor. The circuit court based its judgment exclusively upon the terms of the written contract and held that Grady was an independent contractor; that under the terms of the contract McAbee & Grady, for a certain consideration, were to furnish not only the crusher, but also two men to- operate the machine; and that the amount paid per day per man for these two men was a part of the consideration of the contract between the plaintiff and McAbee & Grady, in addition to the fixed price to be paid for the amount of stone crushed.

Viewing the contract alone, there is considerable plausibility in the logic contained in the opinion of the learned circuit judge. However, we cannot agree that even from the written contract alone it must necessarily follow that Grady was an independent contractor. The contract, among other things, provides that McAbee & Grady were to furnish a certain crusher to C. R. Meyer & Sons Company, the plaintiff. After this crusher was furnished and' set up according to the terms of the contract, it is clear that the same was in the possession and under the control of the plaintiff exclusively. We agree with the position taken by the learned counsel for the appellant that the contract itself was a mere renting contract. The consideration to be paid to McAbee & Grady is termed in the contract itself as rent. Furthermore, it is provided in the contract that McAbee & Grady were to furnish two men to operate the crusher and engine, and that they were to be paid by the [619]*619plaintiff at the rate of $5 per day for each man. The contract does not specify who the two men to be furnished shall be. There is nothing on the face of the contract which indicates in the' slightest degree that any of the members of the firm of McAbee & Grady were to be furnished or employed to operate this machine. When the machine is furnished in accordance with the terms of the contract and the two men are supplied, McAbee & Grady have fully complied with their terms of the contract, excepting for the obligation assumed by them under and pursuant to which they agreed to keep the crusher and the engine in first-class running condition; and the men so furnished are as much under the control of the plaintiff as are the engine and the crusher.

The two men furnished were Edward Grady, a member of the firm of McAbee & Grady, and one Galloway, not connected with the firm. If, instead of furnishing these two men, entire strangers to McAbee & Grady had been furnished, under whose control, may we ask, would these men have operated the machine? Clearly, under the plaintiff’s herein. Furthermore, a careful reading of the contract itself demonstrates that the two men were to be furnished by McAbee & Grady as a part of the obligation assumed -by the firm, and that the provision for the furnishing of such men was inserted solely for the benefit of the plaintiff; and that being so, the plaintiff at any time could have dispensed with this provision and supplied its own men. This view can readily be taken and is well founded if we consider solely the terms of the contract.

This is not an action brought by either of the parties against the other for the purpose of obtaining a construction of the contract. Grady, as a member of the firm of McAbee & Grady, is a distinct entity from Grady as an employee (if he may be considered, as such) of the plaintiff herein. The written contract, as evidence, may be deemed to have considerable weight in determining the question at issue, but it is not necessarily conclusive. What must be [620]*620borne in mind in the instant case is the actual relationship that existed at the time of the injury between Grady and the plaintiff herein; also the surrounding facts and circumstances existing at or about the time of the execution of the contract; the purpose for which the contract was executed; the construction given to the contract by the parties themselves during the period of its execution; and the acts of the parties which indicate their relationship to- each other.

At or about the time when the contract was executed a discussion ensued between the contracting parties, and the statement was made that the machinery was liable at times to become broken down and that the operations of the crusher would during such times be suspended. The parties then considered that during these periods the two men furnished by McAbee & Grady would be without employment. Thereupon it was agreed that these men could be used in the performance of other labor than that involved in the operation of the crusher, and such other labor consisted of that which the plaintiff herein would furnish; and it -is beyond question that while performing such other labor the men were under the exclusive direction, supervision, and control of the plaintiff. That such breakdowns frequently occurred is undisputed in the evidence, and that Grady and Galloway were frequently actually engaged in work other than that connected with the operation of the crusher is conceded in the evidence. But these men were not only under the direction of the plaintiff when the machinery was broken down, but they were at all times under its direction.

The plaintiff had in its employ on its contract a superintendent by the name of Johnson and a foreman by the name of Driesen, and these men from time to time supervised and inspected the work performed by the crusher. They admit that they supervised the work in so far as quality and quantity is concerned. They deny that they ever gave any specific instructions as to the details of operation. However, it is clear that Grady, outside of operating the crusher, [621]*621from time to time performed other work in and about the premises while the crusher was in operation. He assisted in removing stone from the hopper into the crusher. He also aided the men in removing the dust under the screen, and he performed other acts in aiding and assisting the other employees engaged in doing the work in and about the crusher; in fact, instead of attending to the mere operation of the machine, the greater portion of his time was occupied in performing other work, such as that herein indicated.

It must here be remembered that Grady was an expert in operating the crusher; that to perform the work about the crusher required from three to four men in addition to the two men employed in operating the engine and the crusher; that he was not only familiar with his own work, but was also competent to direct the other employees. In fact,- Johnson, the superintendent, testified that Grady also acted in the capacity of a foreman. Under these circumstances the reason why Johnson and Driesen did not give specific directions to Grady becomes apparent. Directions' were unnecessary, because Grady was an expert in his field. A person may be an employer and liable as such for injuries to an employee, under the workmen’s compensation act, even though he does not direct the work of the employees, as long as he possesses the power to direct. Madix v. Hochgreve B. Co. 154 Wis. 448, 143 N. W. 189.

When the contract was first executed the crusher was operated during the daytime for a period of about ten hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masri v. State of Labor & Industry Review
2013 WI App 62 (Court of Appeals of Wisconsin, 2013)
Klusendorf Chevrolet-Buick, Inc. v. Labor & Industry Review Commission
328 N.W.2d 890 (Court of Appeals of Wisconsin, 1982)
Myers v. Workmen's Compensation Commissioner
148 S.E.2d 664 (West Virginia Supreme Court, 1966)
Burkhardt v. State
53 N.W.2d 394 (North Dakota Supreme Court, 1952)
Burt Bros. v. Industrial Commission
39 N.W.2d 388 (Wisconsin Supreme Court, 1949)
Bituminous Casualty Corp. v. Wilkes
49 S.E.2d 916 (Court of Appeals of Georgia, 1948)
Green Valley Co-Operative Dairy Co. v. Industrial Commission
27 N.W.2d 454 (Wisconsin Supreme Court, 1947)
Smith v. Southern Waste Paper Co.
226 N.C. 47 (Supreme Court of North Carolina, 1946)
Smith v. . Paper Co.
36 S.E.2d 730 (Supreme Court of North Carolina, 1946)
Employers Mutual Liability Insurance v. Industrial Commission
284 N.W. 548 (Wisconsin Supreme Court, 1939)
Dahl v. Wunderlich
259 N.W. 399 (Supreme Court of Minnesota, 1935)
Campbell v. Connolly Contracting Co.
229 N.W. 561 (Supreme Court of Minnesota, 1930)
Badger Furniture Co. v. Industrial Commission
227 N.W. 288 (Wisconsin Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
217 N.W. 408, 194 Wis. 615, 1928 Wisc. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-r-meyer-sons-co-v-industrial-commission-wis-1928.