C. J. Langenfelder & Son, Inc. v. State

8 Ct. Cl. 193
CourtWest Virginia Court of Claims
DecidedJanuary 25, 1971
DocketNo. D-120
StatusPublished
Cited by2 cases

This text of 8 Ct. Cl. 193 (C. J. Langenfelder & Son, Inc. v. State) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. J. Langenfelder & Son, Inc. v. State, 8 Ct. Cl. 193 (W. Va. Super. Ct. 1971).

Opinion

PETROPLUS, JUDGE:

This is a claim filed in this Court on October 21, 1968, in the amount of $224,768.11, and later amended by Petition seeking an additional amount of $366,829.56, or a total sum of $591,-[194]*194597.67, in which the petitioner, C. J. Langenfelder & Son, Inc., a corporation, seeks damages from the State Road Commission, now the West Virginia Department of Highways, in connection with a construction contract between the parties to construct a roadway and two bridges in the City of Wheeling, Ohio County, West Virginia.

The contractor claimant, C. J. Langenfelder & Son, Inc., a Maryland corporation, brought this action against the State Road Commission of West Virginia, respondent, to recover damages for alleged delays caused by the Commission in the construction of a highway and bridges near the east portal of Wheeling Tunnel on a section of Interstate Route No. 70, within the corporate limits of the City of Wheeling. The claimant-petitioner is a Company engaged in heavy highway and industrial construction work and has been so engaged for the past fifty years in the construction of dams, airports, power houses, highways, bridges and tunnels. Some of its projects have included the Andrews Air Force Base, the Dulles International Airport, the New York State Thruway, the Connecticut Turnpike, the New Jersey Turnpike and the Pennsylvania Turnpike and tunnels. There can be no doubt that the claimant was well qualified to undertake a complicated and expensive multi-million dollar project in a congested and highly urbanized area of the City of Wheeling, involving many variables, such as traffic flow, Acts of God, floods, slides, relocation of streets and utilities, and unforeseen conditions which required many change orders, extras, supplemental agreements and forced account agreements during the progress of the work.

In order to bring the project to completion in accordance with the voluminous plans and specifications prepared and furnished by the Commission, the contractor was required to coordinate his work with other projects in the area, maintain a traffic flow, and subcontract portions of the work to other contractors. The contract was awarded pursuant to bids on December 29, 1964, to the petitioner, on specified unit prices rather than on a lump sum agreement and the project was designated therein as “East Portal of Tunnel to DeChantal Road, 1-70-1 (13) 2, Contract No. 2”, covering an area of approximately 1657 feet in length. The project was to be completed in 550 working days. The work was satisfactorily performed and was accepted by the State Road Commission as [195]*195being in accordance with the plans and specifications. However, the work was not completed until the month of August, 1966, 110 working days beyond the planned and scheduled completion date.

Because of the complexity of the project, and the activity in other separate projects in the same area, which encompassed a winding creek, a heavily traveled City Street, railroad rights of way, sewer lines, water lines, gas and telephone lines, the contractor prepared a sequence of coordinated operations, which it intended to follow and which sequence was made a part of the specifications.

The contractor claims that many unreasonable delays, not contemplated by the parties and attributable to the inefficiency and incompetence of State Road Commission personnel, disrupted a critical and planned sequence of operations for the work, resulting in damages of great magnitude to the contractor. Two other contracts had been awarded to the petitioner in adjoining areas of operation which involved the construction of two tunnels through a hillside and the portals and approaches thereto.

According to the allegations of the Petition, the Company started to work soon after the contract was executed, when a defect in the plans and specifications was discovered which caused an enforced suspension of the work to provide time for the consulting engineers of the State to make subsurface explorations and studies. This delayed the progress of the work from June 3, 1965, to September 20, 1965, a period of approximately 110 days. The suspension of operations was ordered by the Chief Engineer of the respondent when pile driving for the construction of a pier designated as EB-2 revealed a hazard which required the consideration of the consulting engineers for the project, who had been independently employed by the Commission. The apprehension of the consulting engineers was evidenced by a long delay in studying the problem and eventually redesigning the bridge structure. The suspension of operations naturally delayed the planned relocation of the utilities, which delay in turn prevented the construction of other bridge piers in the area, and the erection of the structural steel which was on order and planned for delivery on specific dates, as well as the paving of a relocated. [196]*196City Street. The bridge piers which were planned for construction in the summer and early fall of 1965 were not constructed and completed until the late winter of 1966. The maintenance of a detour was prolonged and piers constructed adjacent to the detour required sheeting protection. The relocation of McColloch Street was constructed under adverse winter weather rather than in the summer of 1965, as originally planned when the weather would be dry and the area would be workable. Muddy excavated material had to be replaced by suitable stockpiled materials. None of these factors were taken into consideration by the contractor in his bid proposal as they were not anticipated and within the contemplation of the parties.

The steel for the bridges which was planned for erection in September, 1965, under a schedule and sequence of shipments from the Fort Pitt Bridge Works was not erected until January, 1966, resulting in heavy costs for storing, rehandling and reconditioning the steel. Lighting facilities which were to be provided for the highway and bridges which required adjustments to the superstructure were not planned and specified by the Commission until one and one-half years after the work started on the project, thereby delaying the construction of the concrete superstructures on the bridges from November, 1965, until April, 1966.

When the contractor made his proposal, the bids were prepared on a plan to complete the project within 550 working days. The additional expenses incurred by the contractor in idle equipment and maintaining its plant, paying supervisory personnel and overhead items for the extra 110 days, not contemplated by the contract, is the basis for this action. The contractor claims a sustained loss in the aggregate of $591,-597.67, supported by numerous exhibits and cost calculations.

All of the above contentions were supported by evidence from reliable and trustworthy witnesses.

The Answer of the respondent sets forth that the expense in relocating the office trailer was the responsibility of the contractor, who should have known that the location thereof was detrimental to operations under other contracts awarded to . the petitioner. The evidence clearly indicated that the trailer [197]*197was located on a site approved by the engineers of the respondent, who apparently have the last word on where the field offices should be located for the convenience of all parties concerned. Since the trailer had to be removed as an obstruction to other projects, we conclude that the cost of its removal must be borne by the State.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kenhill Construction Co. v. West Virginia Regional Jail & Facility Authority
22 Ct. Cl. 46 (West Virginia Court of Claims, 1998)
McAnallen Bros. v. Board of Regents
14 Ct. Cl. 240 (West Virginia Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
8 Ct. Cl. 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-j-langenfelder-son-inc-v-state-wvctcl-1971.