C. H. Sternberg & Sons v. Nodaway Drainage District No. 2

218 S.W. 960, 203 Mo. App. 131, 1920 Mo. App. LEXIS 166
CourtMissouri Court of Appeals
DecidedJanuary 5, 1920
StatusPublished

This text of 218 S.W. 960 (C. H. Sternberg & Sons v. Nodaway Drainage District No. 2) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. H. Sternberg & Sons v. Nodaway Drainage District No. 2, 218 S.W. 960, 203 Mo. App. 131, 1920 Mo. App. LEXIS 166 (Mo. Ct. App. 1920).

Opinion

BLAND, J.

Plaintiffs, C. H. Sternberg & Sons et al., hereinafter called the contractors, on December 11, 1913, filed a petition in the circuit court of Nodaway County, Missouri, praying judgment in the first count in the sum of $5101.93, the claimed balance due on a contract for the grading of a drainage ditch, entered into by plaintiffs with Nodaway Drainage District No. 2, hereinafter called the drainage district. The drainage district on December 13, 1913, filed suit against C. H. Sternberg & Sons, the surety on their bond, et al, in said court alleging the failure on the part of the contractors to properly complete the drainage ditch, and asking judgment for damages for such failure in the sum of $6898.07. The suits on changes of venue were sent, to the circuit court of Andrew County where they were consolidated and a referee appointed. The court set aside the findings of the referee and rendered judgment against plaintiffs on their first count and found in favor of the drainage district in the sum of $4079.92. This latter sum being less than the amount the contractors would have been entitled to, to-wit, the sum of $5101.93, had they properly completed their contract, which the court found they had not done, the court found that the drainage district was not entitled to a judgment for said sum of $4079.92. The contractors have appealed.

The facts show that on Oct. 27, 1910, the contractors entered into a written contract with the drainage district for the construction of a drainage ditch according *133 to certain plans and specifications. The object and purpose of the contract was the excavation of a drainage ditch, approximately 16 miles in length from nortn to south, in the valley of the Nodaway river. The dimensions of the ditch were to be 18 ft. in width at the bottom with a side slope of 1/4 ft. horizontal to 1 ft. vertical. The ditch was to be excavated in depth according to the grade line shown in the profile prepared by the engineer of the Drainage Board. The ditch ran through a comparatively level river bottom. It had a fall of 2 or 3 feet to the mile and had an average depth of 16 feet with extremes of from 10 to 25 feet. The average width at the top was to be from 16 to 28 feet. The ditch intersected or returned to the Nodaway river twelve times. The river thus divided the ditch into sections which were numbered consecutively 1 to 13, beginning with the north end. This appeal is concerned with the facts concerning sections 1, 2, 3, 5 and 12 only. The wasted earth to be excavated was to be piled on the bank of the ditch 8 feet from the edge thereof. This wasted earth is called the spoil bank. The Board’s engineer was to set stakes and levels indicating the excavating to be done. The contractors were to receive $.0645 per cubic yard for the excavating, and the specifications provided that the excavation should be measured in position before the work was done or subsequently measured as the cubic contents of the excavation made. The excavation was to be done by a dredge boat where possible.

There was a railroad bridge across the Nodaway river where section 3 of the drainage ditch began. Owing to the difficulty of getting a dredge boat under this bridge, sections 1 and 2 of the ditch, which were north of the bridge, were dug with a drag line dredge. A drag line dredge is a steam shovel machine rolling on rollers or wheels and working on top of the bank and placed on the side of the ditch it is excavating. This machine began at the lower end of the ditch and worked up grade, the ditch remaining dry and free from water *134 until the machine should emerge into the stream at the upper end of the section.

When the drag line dredge reached the north end of section 1 there was some dirt left at the entrance of the section, and • about 150 feet at the extreme north end of section 2 was left unexcavated to a depth of six or seven feet. The remaining 11 sections of the ditch were excavated with a dredge boat that started south of the railroad bridge at the north end, or the beginning, of section 3. The dredge boat worked down grade and the waters of the Nodaway rivers were supposed to follow after it and keep it afloat. It was necessary to build a dam across the head, or beginning, of the section the boat was excavating and to pump water into it to a high enough level to float the boat and to enable it to do the work. The work of excavating was done during the years of 1911, 1912, and the first half of 1913.

The contract entered into for the construction of the ditch provided that the contractors should excavate and construct the drainage ditch in accordance with the plan for drainage adopted by the Board; that it should be constructed and the excavation completed in all respects and in every particular as provided by said plan for said drainage; and that the contractors should fully complete the drainage ditch between the points specified. The plan for the drainage recited that the ditch was being constructed to drain and reclaim lands in the district and to protect them from overflow and damage by flood and water. It described the dimensions of the ditch to he constructed. The specifications provided that its object was the doing of all excavation and removal of all obstructions and the performance of all work required to furnish a completely graded ditch; that the ditch should he completed iñ a first-eiass workmanlike manner according to the “plan for the drainage’ and the plans and specifications.

The evidence shows that the character of the earth through which the ditch was excavated was a sandy loam which had a tendency to cave. The evidence further *135 shows that to prevent the sides of the ditch from caving its banks should have had a slope of 1. ft to 1 ft. instead of a slope of 1/4 tft. to 1 ft. as provided in the plan. The Board’s engineer advised the Board that the slope of 1/4 ft. to 1 ft. was not a proper one and that the banks of thé ditch would cave. The contractors advised the Board to the same effect. The members of the Board testified that they knew the banks would cave; that it was their purpose to have the banks cave and the ditch thus made wider, and that it was their idea that when the Nodaway river should rise to the proper stage water would flow into the ditch when finished and erode or wash out any caved-in material that might be present. There is only one inference from the evidence and that is that the drainage board was actuated by a motive of economy in constructing the ditch. The board desired a much wider ditch than it contracted with .the contractors to build, believing that it would acquire such wider ditch by means of erosi'on rather than by paying the contractors the additional amount of money necessary to have the ditch constructed to the width actually desired.

The court found that it was the desire of the drainage district Board that the banks should cave and that the banks did cave badly and at times immediately behind the dredge boat, and that cave-in material filled the ditch to a depth of from six to eight feet in some places. The evidence shows that instead of the ditch being of the width of 29 ft. at the top, the width the contractors attempted to make it, it caved in at some places enough to make the width at the top as much as from 80 to 100 feet, and at places even a portion of the spoil bank caved into the ditch.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
218 S.W. 960, 203 Mo. App. 131, 1920 Mo. App. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-h-sternberg-sons-v-nodaway-drainage-district-no-2-moctapp-1920.