Moore, J.

This suit was brought to recover damages for the breach of a contract made between the B. & O. Sand & Gravel Company and the defendant, which contract was assigned by the B. & O. Sand & Gravel Company to the plaintiff. . It was agreed in open court that if plaintiff was entitled to recover anything it was the sum of $2,800.

The record bears out the following statement of facts which is taken from the brief of counsel :

“The contract was entered into April 3, 1912, between the defendant and C. S. Owen and J. T. Belanger, doing business as the B. & O. Sand & Gravel Company. It was to continue during the navigation season of 1912. The Cadwell Company was the owner of the vessel C. W. Cadwell. The Cadwell Company was to ‘carry sand and gravel in such quantities of approximately 500 cubic yards per week’ up to the capacity of the vessel, as might be required by the B. & O. Company. The deliveries were to be made ‘to the dock of the parties of the second part at De[483]*483troit or other points as are herein provided for, having in view the Solvay Process Company dock or such other dock as is. accessible and convenient to navigable waters, and for the delivery of sand and gravel on the Detroit river in the said city of Detroit, or in the River Rouge as hereinafter set out.’ The price for carrying was 37 cents per yard for sand and 48, 50, and 52 cents per yard, for gravel, depending upon the distance, whether within 40, 50, .or 60 miles from Detroit. Payments were to be made ‘for the quantities delivered during the previous month, on the twelfth day of the following month for all previous months’ deliveries.’ As. security for payment the B. & O. Company was, ‘on the request’ of the Cadwell Company, to assign any contract made by the B. & O. Company for the sale of the sand and gravel being carried by the Cadwell Company. Upon the opening of navigation in 1912 the parties entered upon the performance of this contract, and so continued until October 21, 1912, at which date the B. & O. Company assigned the contract to the C. H. Little Company, of which assignment the Cadwell Company was at once given notice in writing. While the parties were engaged in the performance of the contract, the B. & O. Company made a contract wth the Superior Sand & Gravel Company under date of May 8, 1912, whereby the Superior Company was to take from the B. & O. Company 1,400 yards of gravel and 2,100 yards of sand per week during the navigation seasons of 1912, 1913, and 1914. The price for the gravel was 65 cents per yard and for the sand 43 cents. This contract was made with express reference to the Cad-well contract. It was a sale by the B. & O. Company to the Superior Company of all the sand and gravel which the Cadwell Company was to deliver to the B. & O. Company. This contract was also assigned by the B. & O. Company to the Little Company on the same day as the contract with the Cadwell Company was assigned, and the Superior Company was at once given notice in writing of such assignment.
“The Cadwell Company replied to the notice of assignment October 25, 1912, sending its reply to both the assignor (the B. & O. Company) and the assignee (the Little Company). The reply was as follows:
[484]*484“ ‘We hereby notify you that the said assignment is in breach of the said contract, as you have no right to assign the same. We hereby declare said contract forfeited. We have further notice that the contract made between the Superior Sand & Gravel Company and yourselves has been assigned to the C. H. Little Company. We therefore further notify you that the said assignment is in breach of clause 6 of our said contract, whereby you undertake to assign to us all such contracts, as security for the payment of the sums of money due us, from time to time. We now declare the said contract made between us forfeited and of no force and effect.’
“The Superior Company at the same time replied to the notice of assignment of its contract with the B. & O. Company, stating:
' “ ‘We hereby declare the same canceled and at an end, for the reasons: First, that said contract is not assignable, and second, because the action was taken in violation of the statutes of the State of Michigan respecting the creation of monopolies.’ * * *
“During the navigation season of 1912, after October 21st, the steamer Cadwell was seen unloading sand on the Superior Company’s dock. The Little Company, at the time of the taking over of these contracts, was ready to have them carried out according to their terms. If the Cadwell Company had gone on with the contract, instead of canceling it, it would have been required to deliver 3,500 yards per week for the remainder of that season in quantities of substantially 1,400 yards of gravel and 2,100 yards of sand.
“The plaintiff offered to show that if the defendant had notified the plaintiff that the defendant would not deal with the plaintiff on credit, the plaintiff Would have paid cash. This was excluded. The plaintiff also offered to show that it was its intention that the Cadwell Company should go on delivering sand to the Superior Company under the contract. This likewise was excluded. With reference to the taking over of the contracts by the Little Company it appeared that the B. & O. Company approached the general manager of the Little Company, and that after consultation with the board of directors it was decided to purchase the contracts. A number of leases for sand and gravel beds were taken over at the same time. If the Little Company could not have furnished the Solvay dock [485]*485for the unloading of the gravel for any reason, the Little Company had other docks which would have answered the description in paragraph 1 of the Cad-well contract, and had railroad facilities and docks upon whch the sand and gravel could have been delivered just as conveniently as at the Solvay dock.
“The defendant, under the third paragraph of its plea, sought to introduce testimony _ which _ it was claimed would tend to show that the plaintiff did not in fact intend to carry out the contract with the Cadwell Company. This was excluded over the objection and exception of the defendant, on the ground that, it was not within the averments of the plea. The defendant likewise sought to show that the plaintiff had breached the contract of the Superior Company, in that the plaintiff had refused to deliver any more gravel under the terms of the contract, or to deliver any gravel except at a higher price than in the Superior contract. This was excluded because not stated as a reason for the rescission by the Superior Company at the time it received notice of the assignment and rescinded the contract.
“Defendant further sought to show that it would not have entered into such a contract as the contract in question with the plaintiff either at the time the contract was entered into with the B. & O. Company or at the time it was assigned, and would not have made a contract extending credit to the plaintiff.”

There are two questions presented for consideration: (1) The assignability of the contract; (2) The application of the laws relating to monopolies.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
163 N.W. 952, 197 Mich. 481, 1917 Mich. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-h-little-co-v-cadwell-transit-co-mich-1917.