C. F. W. Construction Co. v. McNutt

179 So. 2d 806, 253 Miss. 783, 1965 Miss. LEXIS 1050
CourtMississippi Supreme Court
DecidedNovember 8, 1965
DocketNo. 43643
StatusPublished

This text of 179 So. 2d 806 (C. F. W. Construction Co. v. McNutt) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. F. W. Construction Co. v. McNutt, 179 So. 2d 806, 253 Miss. 783, 1965 Miss. LEXIS 1050 (Mich. 1965).

Opinion

Lee, C. J.

Robert Norwood McNutt and wife filed their bill of complaint, being an attachment in chancery, against C. P. W. Construction Company, Inc., to recover damages to their property and for the recovery of the statutory penalty for cutting trees thereon in violation of the statute. Prom a decree for the complainants, the defendant appealed.

The litigation arose in this manner: The City of Tupelo advertised for contractors to build a trunk sewer line in the city. C. P. W. Construction Company, Inc., was the successful bidder therefor.

The proposed improvement was to cross the lands of Robert Norwood McNutt and wife. They owned, a home in the city, with approximately 4.11 acres of land. The city attorney, Prank Riley, contacted McNutt with reference to obtaining an easement of 20 feet across this property. McNutt wanted the line to be laid out on the ground, showing where it would run. An assistant to the city engineer, Ackin, and the engineer himself, Bob Cook, went over this property with McNutt and staked out the easement as it was to run. There was the grant of a permanent easement covering 2 feet, and additionally 8 feet on each side of the line as a temporary construction easement, involving a total of 20 feet. The easement also showed the trees that would be cut or damaged. The McNutts executed the easement for which they received no monetary consideration.

The work was begun over the McNutt land on December 3, 1963. McNutt testified that he observed the approach of the construction, before it reached his place, [787]*787and saw that they were cutting a wider path than was called for in his easement. He had a conference with the foreman on the job and called attention to the center line stakes and that he was to go only 10 feet on either side. Several days later, when the company’s crew was digging a manhole, they piled some of the dirt off the easement and damaged some small trees. McNutt conferred with the foreman again and made known to him specifically that the work was not following the easement. Not being satisfied from his conference with the foreman, McNutt got in touch with the superintendent of the job, a Mr. Cushman, took this man over the property, and showed him the bounds of the easement. Cushman replied that they would have to get off the easement. McNutt informed him that they could not. Thereupon Cushman said that they were going to build the sewer line. When McNutt stated that they would be trespassing and be liable for statutory penalty in addition to actual damages, Cushman replied that he supposed the company could pay the damage, if McNutt wanted to make a claim.

After this conversation with these representatives, and after obsei'ving the dirt which was placed outside the easement, McNutt counted the trees on the area, subject, as he thought, to the statutory penalty. Later he made a list, detailing the number of trees, the character and kind of each, and those which were either destroyed or damaged; and he testified that there were approximately 400, 251 of which were completely destroyed while the others were damaged in different degrees.

It was shown that the company had never requested the city to obtain an additional easement for this construction. It was also repeatedly called to their attention that they were trespassing. Ackin, the assistant to the city engineer, testified that he told the representatives of the company to stay on the 20 foot easement, [788]*788and, when they got off the 20 foot easement, they were violating his instructions.

During the progress of the work, McNutt again protested to Cushman, but he was given another answer of the same tenor, namely, that they were going to build the sewer line, and if he wished to do so, he could file his claim for damages.

About the time of the completion of the work, McNutt made another protest to Farrar, who had replaced Cushman as superintendent; but again no satisfaction was obtained.

Some time after this suit had been filed, it was necessary for the company to return to the work in order to make repairs. McNutt testified that, at that time, he asked them not to damage the trees, but they did damage one, and McNutt talked to Farrar about the matter. He, however, replied that they were going to build the line and that they did not care what they did, and that the next time, if McNutt came out and tried to tell them what to do, he would not be dealt with in as friendly manner as they had treated him in the past. For that reason, the complainants filed a supplemental bill to recover for further trespasses on their property.

McNutt testified as to the number of trees of the type subject to the statutory penalty. He said that there were 198 of a market value of $5 each; that it would cost over $2,700 to restore the trees, as they formerly stood; that he had paid $379.50 for the repair of damaged trees; and that he had entered into a contract for the removal of the dirt out of the lake and other places for the sum of $781.50. He further testified that both the amount spent and that to be expended were reasonable values for that work. James Brown, a landscape architect, was fully cognizant of the nature of the work to be done, and he testified that those prices were reasonable.

For the defendant, J. L. Minor, an appraiser, was of the opinion that the damage to the property was [789]*789$1,400. He had not seen the property before the construction work was done, and his estimate was based on the damage which remained after the work, for which McNutt had paid $1,161, had been completed. The witness did not allow anything for the trees which were cut on Lot 7 of the land. Another witness, Jack Mann of Jackson, Mississippi, was of the opinion that the actual damage was $1,000. However he did not allow any damages for the actual value of trees which were destroyed.

At the instance of the defendant, the chancellor viewed the property. In his decision, the learned chancellor held that 251 trees, which fell into the category entitling the owner to the statutory penalty, had been destroyed; besides, he was of the opinion that the actual value of the trees cut was $1,500. He also concluded that the repair of the damaged trees in the sum of $1,161 was not excessive. Consequently he awarded actual damages in the sum of $2,660 and the statutory penalty in the amount of $3,765, being $15 per tree for 251 trees.

Substantially, the contention of the appellant is that the City of Tupelo was exercising a governmental function; that, under the contract, the city was obligated to furnish the right of way for the sewer line; that the work was supervised, approved and accepted by the city’s engineers and the city in accordance with the contract; that it was not charged with negligence; that such damage as was sustained by the complainants was a mere incident to the performance of its obligation and constituted a taking of such private property for a public use; and that it was not liable, but was entitled to be protected by the city’s immunity.

On the contrary, the substantial contention of the appellees is that (1) the construction of a sewer line is not a governmental function; but that (2) a contractor is liable for a trespass on adjoining property while engaged in performing a contract with a governmental [790]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chevron Oil Co. v. Snellgrove
175 So. 2d 471 (Mississippi Supreme Court, 1965)
Wood v. Foster & Creighton Co.
235 S.W.2d 1 (Tennessee Supreme Court, 1950)
Tishomingo County v. McConville
104 So. 452 (Mississippi Supreme Court, 1925)
Newberry v. Hamblen County
9 S.W.2d 700 (Tennessee Supreme Court, 1928)
Valley Forge Gardens, Inc. v. James D. Morrissey, Inc.
123 A.2d 888 (Supreme Court of Pennsylvania, 1956)
Louisville & Nashville Railroad v. Stewart
78 Miss. 600 (Mississippi Supreme Court, 1900)
Austin v. Millspaugh
43 So. 305 (Mississippi Supreme Court, 1907)
Covington County v. Watts
82 So. 309 (Mississippi Supreme Court, 1919)
L & A Contracting Co. v. Hube
133 So. 2d 394 (Mississippi Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
179 So. 2d 806, 253 Miss. 783, 1965 Miss. LEXIS 1050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-f-w-construction-co-v-mcnutt-miss-1965.