C. E. Sparrow Co. v. W. H. Hartman Co.

121 N.W.2d 98, 254 Iowa 1370, 1963 Iowa Sup. LEXIS 743
Supreme Court of Iowa·Decided April 9, 1963·No. No. 50911·Published

Opinion

Stuart, J.

— The defendant, W. H. Hartman Company, hereinafter referred to as the owner, owned the Waterloo Courier Building in Waterloo, Iowa. It entered into a contract for extensive remodeling of this building with the John G. Miller Construction Company, hereinafter referred to- as the contractor. The contractor subcontracted the plumbing and heating portion of the contract to Sid Smith and Company, hereinafter referred to as the subcontractor. The subcontractor purchased materials to- be used on this job from the plaintiff, C. E. Sparrow Co-., Inc., hereinafter referred to- as the supplier. The subcontractor did not pay the account of the supplier. Supplier filed a mechanic’s lien against the property of the owner and brought this action to- foreclose. The -trial court held the payment in full by the contractor to the subcontractor terminated supplier’s lien rights, if any, against the owner. Supplier has appealed from the judgment. The case was tried upon a stipulation of fact.

In January 1959 supplier furnished the materials to subcontractor which were used in owner’s building. Subcontractor [1372] billed the contractor for the materials January 31, 1959, and the contractor paid the subcontractor February 4, 1959. The contractor billed the owner February 28, 1959, and was paid March 7, 1959. By April 16, 1959, subcontractor had been paid in full for all items of labor and material furnished by it under its subcontract. The supplier had not been paid by subcontractor and on July 30, 1959, its mechanic’s lien was filed and the owner was served legally with notice as provided in section 572.10, Code of Iowa. More than 60 days had elapsed since the furnishing of the material but at that time the owner owed the contractor an amount in excess of the claim of the supplier. The amount still due the contractor was for work and materials furnished by contractor during July 1959.

The owner concedes the supplier is a materialman within the provisions of section 572.1(2), 1958 Code of Iowa, and is a person entitled to a lien within the provisions of section 572.2. It is also conceded the mechanic’s lien was filed after the 60-day period in accordance with the provisions of section 572.10 and that the notice was duly and legally served on the owner.

The narrow question in controversy here is the legal effect of full payment of the amount due the subcontractor upon the lien of a supplier of the subcontractor which supplier did not file its mechanic’s lien until after the 60-day period has expired. This involves an interpretation of section 572.11 of the 1958 Code of Iowa, which reads as follows:

“Extent of lien filed after sixty days. Liens perfected under section 572.10 shall be enforced against the property or upon the bond, if given, by the owner, as hereinafter provided, only to the extent of the balance due from the owner to the contractor at the time of the service of such notice; but if the bond was given by the contractor, or person contracting with the subcontractor filing the claim for a lien, such bond shall be enforced to the full extent of the amount found due the subcontractor.”

The supplier claims that it perfected its lien by filing the claim as provided in section 572.10 and that under section 572.11 it is entitled to enforce it against the property of the owner “to the extent of the balance due from the owner to the contractor at the time of the service of the notice”, which in the instant ease [1373] is more than enough to cover supplier’s account. It claims the fact that the subcontractor with which the supplier contracted has been paid in full in no way affects its right to enforce the lien against the owner.

The owner contends the mechanic’s lien statutes only contemplate three parties, the owner, contractor and subcontractor and that the term “contractor” as used in section 572.11 means the party with which the supplier contracts which would not necessarily be the principal contractor. Thus, where four parties are involved, as in the instant case, the rights of the supplier are to be determined on the basis of the contractor being in the shoes of the owner, the subcontractor in the shoes of the contractor and the supplier in the shoes of the subcontractor. In other words, the owner argues supplier’s lien must be enforced through the party with whom supplier contracted and if that party has been paid in full, supplier’s lien cannot be enforced against the owner if filed after the 60-day period has expired. Owner contends that if a lien is not filed within 60 days it has the right to assume the supplier will look elsewhere for payment and can feel at liberty to pay the contractor. Under these same circumstances the contractor could feel at liberty to pay a subcontractor without risk of a lien being filed and enforced against the unpaid balance due contractor from the owner.

In view of the amount of construction that has taken place in Iowa over the past 100 years, there is a surprising lack of authorities on this particular question. The only case found by either party or the court which is directly in point is the case of Utter v. Crane (1873), 37 Iowa 631, 633, 634, upon which the owner has based its case and from which many of the arguments advanced by the owner were taken. In this case a laborer employed by a subcontractor attempted to enforce a mechanic’s lien against the owner railroad. The court said:

Free access — add to your briefcase to read the full text and ask questions with AI

C. E. Sparrow Co. v. W. H. Hartman Co., 121 N.W.2d 98, 254 Iowa 1370, 1963 Iowa Sup. LEXIS 743 (iowa 1963).

121 N.W.2d 98 (C. E. Sparrow Co. v. W. H. Hartman Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Adams v. Grand Island & W. C. R.
72 N.W. 577 (South Dakota Supreme Court, 1897)
Congdon & Henry Hardware Co. v. Grand Island & W. C. R.
86 N.W. 633 (South Dakota Supreme Court, 1901)
Utter v. Crane
37 Iowa 631 (Supreme Court of Iowa, 1873)
Nash & Phelps v. Chicago, Milwaukee & St. Paul R'y Co.
62 Iowa 49 (Supreme Court of Iowa, 1883)
Beach v. Wakefield
107 Iowa 567 (Supreme Court of Iowa, 1898)
Illinois Steel Warehouse Co. v. Hennepin Lumber Co.
182 N.W. 994 (Supreme Court of Minnesota, 1921)