C. B. Keogh Manufacturing Co. v. Eisenberg

27 N.Y.S. 356, 7 Misc. 79, 57 N.Y. St. Rep. 91
CourtNew York Court of Common Pleas
DecidedFebruary 5, 1894
StatusPublished
Cited by3 cases

This text of 27 N.Y.S. 356 (C. B. Keogh Manufacturing Co. v. Eisenberg) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. B. Keogh Manufacturing Co. v. Eisenberg, 27 N.Y.S. 356, 7 Misc. 79, 57 N.Y. St. Rep. 91 (N.Y. Super. Ct. 1894).

Opinion

BOOKSTAVER, J.

The complaint alleged the sale and delivery to the defendant between ¡November 1, 1890, and May 8, 1891, of certain merchandise consisting of doors, sashes, blinds, and other building materials, at the agreed price of $4,200, and of certain. [357]*357other materials, not included in this contract, of the value of $112.95, and admits payments to the amount of $1,500, leaving a balance of $2,812.95 and interest claimed to be due plaintiff. The answer, after certain denials, set up three counterclaims, each based on a contract between the parties dated November 10, 1890, which contract was offered in evidence on the trial. The first of these counterclaims is to the effect that the plaintiff delayed for 80 days after December 30, 1890, to deliver said goods, and stipulated damages, according to the contract, at the rate of $20 per day, is demanded, amounting to $1,600. The second of the counterclaims alleges that part of the materials contracted to be delivered was not furnished at all, and that defendant purchased them elsewhere at an expense of $200. The third counterclaim is for $1,000 for alleged damages in loss of rent caused by delay in furnishing materials. To these counterclaims a reply was interposed which denied all the allegations contained in each counterclaim. After issue joined, the court ordered a bill of particulars of the various items of the counterclaims. The issues so joined were tried by a referee, who found in favor of the plaintiff the full amount of its claim; deciding, in substance, that the plaintiff was delayed by the fault of carpenters and other workmen employed by defendant, and that, as to many different items of trim, the plaintiff, prior to December 30, 1890, delivered a quantity sufficient to complete the buildings in controversy, and afterwards, at the request of defendant, made further deliveries in excess of the quantity it should have been required to deliver. From the judgment entered on the referee’s report, this appeal is taken. n

The appellant contends that inasmuch as the complaint alleges a cause of action for goods, wares, and merchandise furnished, merely, and does not expressly set forth that such claim is based on a written agreement, while the referee finds that whatever materials were furnished were delivered under a written contract at a fixed price, which provided that all the material should be delivered not later than the 30th of December, 1890, under a penalty for delay, and further found that some of the goods were furnished as late as the 6th of April, 1891, he erred in admitting evidence tending to show why the delivery was not completed within the time stipulated, the complaint not alleging any excuse for delay. This contention rests on Elting v. Dayton, (Sup.) 17 N. Y. Supp. 849. In that case, as appears from the opinion, the complaint alleged that on a certain date the plaintiff entered into a contract with the defendant to do certain work and furnish certain materials at a fixed price, and that he had fully kept and performed the contract, and had performed all the conditions thereof, on his part. The answer admitted the contract, which it alleged was in writing, and a copy was annexed thereto. The answer denied that the plaintiff had kept and performed the contract, or its conditions, upon his part, and then alleged, among other things, that the agreement provided the plaintiff would, on or before a certain date, complete his contract, under a penalty. On the trial there was no dispute but that the contract was not completed at the time fixed [358]*358in it, or for some time after. When the plaintiff offered evidence tending to excuse his failure to perform, it was objected to as incompetent, for the reason that'the plaintiff had sued upon a contract, alleging he had strictly kept and performed all the conditions thereof, and that no excuse for nonperformance and no modification or waiver had been set up in the complaint. The referee overruled the objection, to which defendant excepted, and on appeal this ruling was held error. We think that case well decided, on the pleadings and facts then before the court, but they differ materially from the pleadings and facts now before us. In this case the complaint did not set up a contract, nor aver performance of all its conditions. But it may be argued the answer did allege the written contract," and avers its breach, in that the work was not pérformed within the time therein limited, which was denied by the reply, and thus the same question is presented which was passed upon in Elting v. Dayton, supra. To this we answer the contracts in the two cases differ very materially. The appellant has laid much stress upon the provision in the contract which called for the full performance of it not later than the 30th of December, 1890, while he has studiously overlooked the further provision in the same paragraph of the contract, and separated from the one insisted on by him by a comma c-nly, to the effect that if delay was caused by the defendant the time of the plaintiff for the completion of the contract should be extended a corresponding length of time, so that the whole paragraph reads as follows:

“And the said parties of the second part hereby agree to commence furnishing trim on November 20, 1890, and to complete and fully furnish the entire contract not later than December 30, 1890, except they shall be delayed by reason of delay on the part of the party of the first part, and then only at such time later than said 30th day of December, 1890, as will be equal to the time delayed by reason thereof, and then the time extended for the completion of the said contract shall be equal to the actual delay caused by said party of the first part”

Beading the whole passage together, as we must, in order to ascertain its meaning, the intention of the parties, clearly, was that the plaintiff should have until the 30th of December, 1890, to complete the contract, plus such additional time as would lie equal to the delay caused by the defendant, if any. Viewed in this light, the testimony admitted under appellant’s objection was competent and proper, not to prove any waiver or modification of the contract on the part of the defendant, nor to excuse nonperformance on the part of the plaintiff; but to show. a performance by the plaintiff within the terms and conditions of the contract; in other words, to show how much the time limited in the contract had been extended by its own provision. This is the reverse of what was attempted in Elting v. Dayton, supra. It cannot be successfully argued that as the penalty for delay is inserted in the agreement after the provision for additional time in case the defendant-caused the delay, and the penalty clause contains nothing respecting such delay, the latter clause must control, and the defendant recover the penalty, for such a construction would put a premium upon the defendant’s own wrongdoing, and would be unconscionable.

[359]*359So far on the appellant’s own theory of the law of this case. But we do not understand that where there is a specific contract for a certain service, at a fixed price, the plaintiff must in every case set forth that contract in his complaint, and aver performance or excuse nonperformance, where the defendant has himself been guilty of a breach of the contract, as the referee has found to be the fact in this case, both in respect to delay and to payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raile v. Peerless American Products Co.
192 A.D. 506 (Appellate Division of the Supreme Court of New York, 1920)
Indianapolis Coal Traction Co. v. Dalton
87 N.E. 552 (Indiana Court of Appeals, 1909)
Stecher Lithographic Co. v. . Inman
67 N.E. 213 (New York Court of Appeals, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
27 N.Y.S. 356, 7 Misc. 79, 57 N.Y. St. Rep. 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-b-keogh-manufacturing-co-v-eisenberg-nyctcompl-1894.