C & B Construction Co. v. Nashville School District No. 1

484 S.W.2d 519, 253 Ark. 73, 1972 Ark. LEXIS 1413
CourtSupreme Court of Arkansas
DecidedSeptember 18, 1972
Docket5-5730
StatusPublished

This text of 484 S.W.2d 519 (C & B Construction Co. v. Nashville School District No. 1) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & B Construction Co. v. Nashville School District No. 1, 484 S.W.2d 519, 253 Ark. 73, 1972 Ark. LEXIS 1413 (Ark. 1972).

Opinion

J. Fred Jones, Justice.

This is an appeal by a prime contractor, C & B Construction Co. and its insurance carrier, National Surety Corporation, as well as its subcontractor, George Garrison Co., Inc. from a judgment of the Howard County Circuit Court for $37,077 in favor of the plaintiff-appellee, Nashville School District No. 1, in a suit for damage from a breach of warranty in the construction of the roof on a new school building. The original complaint filed by the school district alleged damages in the amount of $60,000 for removing and repairing the built-up roof on the school building and in the amount of $5,000 for water damage to the interior of the building. The original complaint was later amended by alleging damages in the amount of $32,077 for replacing the roof and praying judgment for $37,077 rather than $65,000.

The facts necessary to this opinion appear as follows: On May 2, 1966, the Nashville School District No. 1 entered into an agreement with an incorporated architectural firm to design a high school building with the additional duties of assisting in procuring construction contractors, conducting inspections to determine the dates of substantial and final completion, and issuing final certificate of payment to the contractors.

On June 13, 1967, the District entered into a contract with C & B Construction Co. for the construction of the building for the contract price of $566,603. C & B then entered into a subcontract with George Garrison Co. whereby Garrison undertook to install all roofing, sheet metal, skylights and aluminum siding as per plans and specifications, and as set out in the prime contract, for the sum of $28,154. C & B, as prime contractor, installed a metal roof deck as a part of the building and apparently as called for in the amended plans and specifications. Subcontractor Garrison then installed a two-ply built-up asphalt roof on the metal decking.

The work was completed on or about April 26, 1968, and a few days later a severe hailstorm occurred in the area and some damage to school property was then noted. In September, 1968, the prime contractor was notified by telephone that there were leaks in the roof of the school building and in December, 1968, the prime contractor was notified in writing by the architect that the roof had been leaking and had been damaged by the hailstorm. Subcontractor Garrison attempted to repair the roof damage caused by the hail and in doing so found that the roof had cracked at the juncture of the covered walkways and classroom areas, and over areas where the metal decking had changed directions. Mr. Garrison was directed to sweep back the gravel and apply a flood coat of asphalt on the entire roof. This was done and paid for by the insurance company. The entire building was completed and accepted by the District upon recommendation of the architect in October, 1968. In the summer of 1969 the roof began to blister over its entire surface and it continued to leak.

The District sued the prime and subcontractors on express and implied warranties in connection with the services rendered in constrúcting the roof, and also joined material manufacturers as well as the architect as parties defendant. The District alleged that the architect was negligent in that it specified an inadequately designed roofing system which was unfit for the purpose intended and that it failed to properly supervise the construction. Each of the defendants filed answers of general denial and cross-complaints against each other.

By agreement of the parties a jury was waived and the case was tried before the trial judge as a jury. The court found that the new facility was substantially complete on July 30, 1968, and final payment on the contract price was made by the District on February 26, 1969. The court further found that the roof was a total failure; that the cost of replacement would amount to $32,077 and that damage to the interior of the facility because of leakage amounted to $5,000. The court further found that the failure of the roof was caused by the presence of moisture at the time of construction and because of defective workmanship. The court found that moisture existed between the layers of felt at the time of application and, therefore, a good bond could not be obtained between the materials; that this condition caused blistering when heat was subsequently applied; that this in turn caused ply separation and by reason thereof, the roof ultimately became a total failure.

The trial court awarded judgment in favor of the District against C & B Construction Co. and its surety for $37,077 and cost on the original complaint. After finding that subcontractor Garrison carelessly and negligently installed and constructed the roof, and that such negligence was the proximate cause of the roof failure, the trial court awarded judgment over in favor of C & B Construction Co. and National Surety Corporation on their cross-complaint against the subcontractor Garrison for $37,077. The complaint and cross-complaints were dismissed as to the other parties to the lidgation.

On its appeal to this court the appellants rely on the following points for reversal:

“The court’s findings and conclusions that the roof failure and the damages allegedly sustained by the District were solely and proximately caused by the negligence and carelessness of Garrison in the application and installation of the roof is contrary to the law and the evidence in the instant case.
The trial court erred in dismissing the complaint of the Nashville School District and the respective cross-complaints of appellants as against the architects.”

The question on this appeal is not whether we would have rendered the same judgment the trial court rendered if we had been sitting in his place as the trier of facts in this case. The only real question on this appeal is the fact question of whether there is substantial evidence to support the judgment reached by the trial court in this case, and we are of the opinion there was.

It is clear from the evidence that in constructing the roof, the prime contractor built the deck upon which the roof was to be constructed by the subcontractor Garrison. In constructing the roof, in this case, rigid pieces of insulating material were first stuck to the steel roof deck with hot asphalt mopped onto the deck. Asphalt was then mopped onto the insulation and then 37 inch wide felt was rolled onto the hot asphalt. Another coat of asphalt was applied to the surface of the first layer of felt and another layer of felt was applied. This was covered with another coat of asphalt to which gravel was then applied. The prime and subcontractors blame the architect and each other for the failure of the roof, and they offered some evidence in support of their contentions. There is substantial evidence in the record, however, in support of the trial court’s view as above set out.

Mr. Gouge, the roofing superintendent for Garrison Co., testified that the steel decking was improperly designed and installed without provisions or allowances for expansion joints. He testified that he observed splits in the roof and attributed them to the lack of expansion joints in the decking. He testified that all the leaks he observed started at places where expansion joints should have been, but that in some instances the water could get on the metal decking then run 21 feet before coming through.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
484 S.W.2d 519, 253 Ark. 73, 1972 Ark. LEXIS 1413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-b-construction-co-v-nashville-school-district-no-1-ark-1972.