The opinion of the court was delivered by

Gummere, Chief Justice.

This is an action brought upon a mechanics’ lien against the United- States Engineering Compaq, builders, and Lothridge, owner, for materials furnished in the erection of a house belonging to Lothridge. Before the commencement of the building a contract for its erection was [407]*407entered into between the company and Lothridge, and was regularly filed. The price to be paid to the engineering company, as fixed by the contract, was $4,600. The first payment was to he one-third of the total amount, and was due when the concrete walls were finished to the roof, and the door and window frames set in the wall. The second payment w*as for a like sum, and -was due when the roof was completed, and the frame work for the inside partitions, and the joists and flooring were installed. The third payment was for the remainder of the contract price, and was to be made within twenty days after the house was finished in accordance with the plans and specifications.

The contract was executed on the 1st day of June, 1908, and was filed on the 3d of that month in the Camden county clerk’s office. On the 3d of July the engineering company ■wrote Lothridge as follows: "Dear Sir: In consideration of you making payments to ns on account of onr contract with you for concrete house at Merchantville, as outlined below, we hereby agree to allow'- yon a discount of $200 on the entire contract. It is further understood that your making payments in this matter does not affect the validity of the original contract. Payments as follows: July 3, $300; July 17 or July 24, balance of first payment if walls are completed. Two weeks after first regular payment $300, and $300 each w*eek thereafter until second payment is due. Balance on contract to be paid as specified in original contract. It is further understood that this company will complete each week work to a value greater than the amount of weekly payments in the judgment of the architect and yourself. Payments made in advance must he covered by bills for labor, material and subcontracts on this house only; and the receipts for such bills must he shown before the next payment is made, or same will not have to be made. Tours truly, etc.”

There was evidence that this letter was delivered to Loth-ridge on the day of its date, at the company’s office, and also that it was then agreed between the parties that the contract should he altered in accordance with the suggestions contained in the letter*.

[408]*408It was also shown that the greater part of the materials, to recover the price of which this suit was brought by the plaintiff, were furnished after this alteration in the original contract.

When the case came on to be tried the court, at the close of the testimony on both sides, directed a verdict in favor of the defendant, Lothridge, upon the ground that the building was not liable for the plaintiff’s claim. The propriety of this direction is now challenged by the plaintiff in error.

The object of the Mechanics’ Lien law, as expressed in its title (Pamph. L. 1898, p. 538), is the securing to mechanics and others payment for their labor and materials in erecting any building. This object is sought to be accomplished (section 1) by making every building erected in the state, including the curtilage upon which it stands, liable for the payment of any debt contracted and owing to any person for labor performed, or materials furnished in its erection and construction, unless (section 2) it is erected by contract in writing, and the contract, or a duplicate thereof, together with the specifications accompanying it, is filed in the office of the county clerk. The effect of these provisions of the statute is to give to the laborer and materialman a lien apon the building,, unless the contract under which the building is erected, or a duplicate of it, is filed. The filing of a contract which falsely states the consideration to be paid to the contractor for the erection of the building, will not operate to relieve the building and curtilage from the lien of the laborer or materialman (Murphey-Hardy Lumber Co. v. Nicholas, 37 Vroom 414), nor will the filing of a contract which is afterwards superseded by a new and different agreement, protect against such liens (Buckley v. Hann, 39 Id. 624); and the reason is that, in neither of such cases, is the contract which is filed the real agreement of the parties governing the erection of the building.

An important purpose to be accomplished by requiring the filing of the very contract under which the building is erected, is to enable intending laborers and materialmen to ascertain whether its provisions are sufficiently favorable to the contractor to justify the conclusion that the job will be a fairly [409]*409profitable one to him. For this must he a potent factor in determining whether or not it will he reasonably safe to extend credit to the contractor for labor or material, particularly in those cases where his financial responsibility is questionable. Unless it was intended that such information should be afforded, the object of the statute would have been accomplished by a mere requirement that notice of the existence of a contract between the owner and the builder should be spread upon the record.

The same reason which led the Supreme Court to its decision in Murphey-Hardy Lumber Co. v. Nicholas, and this court to the conclusion which it reached in Buckley v. Hann, is conclusive that a building contract which is altered in a material particular after it is filed, will not protect the building against the claim of a laborer or materialman for work done or materials furnished after such alteration, unless the contract, as altered, is filed in the office of the county clerk.

In the present case the suggested alteration in the original contract, if it was in fact made, was, in our opinion, a material one. It consisted in a reduction in the contract price, and a change in the times of payment. The amount of the reduction it is true was small, but this, we think, is not an element to he considered, for once it is conceded that the original price may be reduced by a secret arrangement between the parties, the amount of reduction is a matter entirely within their discretion. The change in the time of payment was also material; for it affected seriously the right given by section 3 of the statute to laborers and materialmen to impound moneys due and owing by the owner to the contractor on the contract, or that might thereafter-become due thereon, as a means of obtaining payment for work done upon or materials furnished to the building.

The right of the one party or the other, therefore, to a verdict, depended upon whether or not the alteration in the contract, set up by the plaintiff, had in fact been made; and that of course was a matter which should have been left to tlie jury for determination.

[410]*410There was error in the direction of a verdict for the defendant, Lothridge, and for this reason the judgment under review must be reversed, and a venire de novo awarded.

For affirmance—None.

For reversal—The Chancellor, Chief Justice, Garrison, Swayze, Trenci-iard, Parker, Bergen, Voori-iees, Minturn, Bogért, Yredbnburgh, Congdon, JJ. 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eisenhardt v. Schmidt
98 A.2d 698 (New Jersey Superior Court App Division, 1953)
JAS. FALCONE PLUMBING & HEATING CO. INC. v. Pasquale
97 A.2d 720 (New Jersey Superior Court App Division, 1953)
Ewart v. Johnson
166 A. 716 (Supreme Court of New Jersey, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
80 A. 484, 81 N.J.L. 406, 52 Vroom 406, 1911 N.J. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-b-coles-son-co-v-lothridge-nj-1911.