Butt v. Bovis Lend Lease LMB, Inc.
Opinion
OPINION OF THE COURT
Plaintiff sues to recover for injuries allegedly sustained on January 2, 2003, when he fell from a ladder while plastering a beam in the ceiling of an interior stairwell in the gymnasium at Public School 24 in the Bronx. He asserts claims based upon common-law negligence and Labor Law violations. The premises were owned by the City of New York, and operated and maintained by the Board of Education. The project was funded by the New York City School Construction Authority (SCA), and Bovis Lend Lease was the general contractor and construction manager. After discovery, defendants moved for summary judgment, arguing that the work engaged in by plaintiff at the time of the accident was outside the scope of the contract between Bovis and plaintiffs employer, Nortom Construction, and thus did not fall within the embrace of the Labor Law. Supreme Court denied the motion, made seven months after the note of issue was filed, without addressing the merits, finding that the motion was untimely and that defendants had failed to show good cause for the delay.
Defendants satisfied their obligation to show good cause for the delay in moving for summary judgment (see CPLR 3212 [a]), and the merits of the motion should have been reached. On April 1, 2005, approximately 2½ weeks after plaintiff filed a note of issue and certificate of readiness, plaintiff s counsel advised defendants’ counsel of the death of the stenographer who [340] had recorded the deposition of a party witness, Alex Rollaros, Bovis’s project manager, on November 17, 2004, and indicated that a new deposition would have to be undertaken since the stenographer’s notes could not be found. Subsequently, on June 16, 2005, at a court conference attended by all parties, the court directed a second deposition of Rollaros. This deposition was conducted on July 26, and the transcript thereof was forwarded to defendants on September 27. Defendants moved for summary judgment on October 18, acknowledging the late filing, but arguing that there was good cause therefor because the Rollaros deposition, which was essential to the motion, had to be conducted a second time.
The fact that the deposition of a key witness, Rollaros, was not taken until over four months after the note of issue had been filed demonstrated good cause (see Gonzalez v 98 Mag Leasing Corp., 95 NY2d 124 [2000]; Fainterg v Dalton Kent Sec. Group, 268 AD2d 247 [2000]). That an earlier deposition of the same witness had been taken before the filing of the note of issue, a circumstance relied upon by plaintiff, is of no moment. Significantly, it was plaintiff who had requested a second deposition in light of the lack of a transcript of the earlier deposition, a fact conspicuously missing from plaintiffs opposition to defendants’ motion. It is also significant that the court was aware of the discovery being conducted after the filing of the note of issue (see Quizhpi v Lochinvar Corp., 12 AD3d 252 [2004]). It is no answer to argue, as plaintiff does, that defendants could have gotten an affidavit from the witness since they already knew the nature of his testimony as a result of the first deposition. Defendants were entitled to await the taking of Rollaros’s second deposition to have the benefit of his entire testimony. Upon receipt of the transcript of that testimony, they moved expeditiously for summary judgment. Thus, defendants met their burden. The standard for a good cause showing should not be an unreasonable one. Nor should untimeliness ever be used as a facile excuse to avoid reaching the merits.
As to the merits, the motion should be denied. Defendants seek summary judgment on the ground that the work plaintiff was performing at the time of his accident was outside the scope of the contract and that therefore he was not entitled to protection under the Labor Law. While Labor Law § 240 (1) and § 241 (6) claims have been dismissed on the ground that a “plaintiffs work at the time of the accident was outside the scope of the general contractor’s contract” (Balthazar v Full Circle Constr. [341] Corp., 268 AD2d 96, 98 [2000]; see also Root v County of Onondaga, 174 AD2d 1014 [1991], Iv denied 78 NY2d 858 [1991]), this defense inures only to the benefit of the parties who lacked the authority to supervise or control the work. The rule has its genesis in the concept that Labor Law liability under section 240 (1) and section 241 (6) is premised on an owner’s or general contractor’s right to control the work, irrespective of whether such control is exercised, and that if the work leading to the accident is outside the scope of what is contracted for, there is no right of control on the part of the contractor and thus no liability under those statutes (see Balthazar, 268 AD2d 96 [2000]; Root, 174 AD2d 1014 [1991]).
Footnotes
47 A.D.3d 338 (Butt v. Bovis Lend Lease LMB, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.