Butler v. Boeing Co.

175 F. Supp. 2d 1307, 51 Fed. R. Serv. 3d 872, 2001 U.S. Dist. LEXIS 20998, 2001 WL 1598036
CourtDistrict Court, D. Kansas
DecidedDecember 10, 2001
DocketCi. A. 01-2433-KHV
StatusPublished
Cited by1 cases

This text of 175 F. Supp. 2d 1307 (Butler v. Boeing Co.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler v. Boeing Co., 175 F. Supp. 2d 1307, 51 Fed. R. Serv. 3d 872, 2001 U.S. Dist. LEXIS 20998, 2001 WL 1598036 (D. Kan. 2001).

Opinion

MEMORANDUM AND ORDER

VRATIL, District Judge.

Henry F. Butler brings employment discrimination and retaliation claims against The Boeing Company (“Boeing”) under Title VII of the Civil Rights Act of 1964, 42 U.S.C. §§ 2000e et seq. as amended (“Title VII”), the Kansas Acts Against Discrimination (“KAAD”), K.S.A. § 44-1001 et seq., and the Civil Rights Act of 1871, 42 U.S.C. §§ 1981 and 1983. On October 4, 2001, the Court sustained as uncontested defendant’s motion for partial summary judgment. See Memorandum And Order (Doc. # 71). Specifically, the Court ruled that defendant was entitled to judgment on plaintiffs Title VII claims and plaintiffs KAAD claims, and that plaintiffs Section 1981 claims were limited to acts which occurred after October 21,1997. See id. at 1-2. This matter comes before the Court on plaintiffs Motion To Reconsider And Alter Or Amend Order Granting Defendant’s Motion For Partial Summary Judgment (Doc. # 75) and Motion For Relief From Judgment Or Order (Doc. # 77), both filed October 15, 2001. Pursuant to Rules 59(e) and 60(b), Fed. R. Civ. P., plaintiff urges the Court to relieve him of the partial summary judgment order For reasons stated below, the Court overrules plaintiffs motions.

Procedural Background

Defendant filed its motion for partial summary judgment on July 6, 2001, and plaintiffs response was due July 30, 2001. See Rules 59(e) and 60(b), Fed.R.Civ.P. On August 1, 2001, two days after the response time expired, the Court entered an order which allowed plaintiffs first counsel, Claudio E. Molteni and Dennis E. Egan, to withdraw from the case. See Order (Doc. # 56). About a month later, on September 5, 2001, plaintiffs second counsel, Cortland E. Berry, entered his appearance in the case. See Entry Of Appearance (Doc. # 69). 1 On October 4, 2001, nearly a month after Mr. Berry entered his appearance, the Court sustained defendant’s motion as uncontested.

Legal Standards

A motion to alter or amend judgment under Rule 59(e) is essentially a motion for reconsideration. See Schweitzer-Reschke v. Avnet, Inc., 881 F.Supp. 530, 532 (D.Kan.1995). The Court has discretion whether to grant or deny a motion to reconsider. See Hancock v. City of Okla. City, 857 F.2d 1394, 1395 (10th Cir.1988). The Court may recognize any one of three grounds justifying reconsideration: an intervening change in controlling law, availability of new evidence, or the need to correct clear error or prevent manifest injustice. See Major v. Benton, 647 F.2d *1309 110, 112 (10th Cir.1981); Burnett v. W. Res., Inc., 929 F.Supp. 1349, 1360 (D.Kan.1996). A motion to reconsider is not a second opportunity for the losing party to make its strongest case, to rehash arguments, or to dress up arguments that previously failed. See Voelkel v. Gen. Motors Corp., 846 F.Supp. 1482, 1483 (D.Kan.1994). Such motions are not appropriate if the movant only wants the Court to revisit issues already addressed or to hear new arguments or supporting facts that could have been presented originally. See Van Skiver v. United States, 952 F.2d 1241, 1243 (10th Cir.1991).

Under Rule 60(b), the Court may grant relief from a judgment or order for several reasons, including (1) mistake, inadvertence, surprise or excusable neglect; (2) newly discovered evidence; or (3) fraud, misrepresentation or other misconduct of an adverse party. Relief under Rule 60(b) is extraordinary and may only be granted in exceptional circumstances. See Yapp v. Excel Corp., 186 F.3d 1222 (10th Cir.1999); Bud Brooks Trucking, Inc. v. Bill Hodges Trucking Co., 909 F.2d 1437, 1440 (10th Cir.1990). Carelessness by a litigant does not afford a basis for relief under Rule 60(b)(1). See Pelican Prod. Corp. v. Marino, 893 F.2d 1143, 1146 (10th Cir.1990).

Analysis

Plaintiff urges the Court to overlook his failure to respond because (1) plaintiffs first counsel agreed with defendant to stay the response time until plaintiff found new counsel; (2) plaintiffs first counsel did not inform second counsel of the pending motion; (3) allowing a late response would not prejudice defendant; and (4) plaintiff can present facts and legal authority to show that the Court should overrule the motion on the merits. Although plaintiff does not clearly articulate the grounds for his motions, he essentially argues excusable neglect. Defendant responds that plaintiff and his counsel had sufficient information to know about the pending motion and that their carelessness does not justify setting aside the order.

To determine whether neglect is “excusable,” the Court must consider all relevant circumstances surrounding the delay, including (1) the danger of prejudice to defendant; (2) the length of delay and its potential impact on the case; (3) the reason for the delay, including whether it was within the reasonable control of plaintiff; and (4) whether plaintiff acted in good faith. See Pioneer Inv. Servs. Co. v. Brunswick Assocs. Ltd. P’ship, 507 U.S. 380, 395, 113 S.Ct. 1489, 123 L.Ed.2d 74 (1993). Considering these factors, the Court finds that the circumstances surrounding plaintiffs delay do not warrant a finding of excusable neglect.

The first two factors weigh against plaintiff. Plaintiff filed this case well over a year ago, on August 14, 2000. Due to multiple changes in counsel for plaintiff, the case is still in the scheduling stage. 2 The partial summary judgment order narrows the scope of plaintiffs’ claims to a two-year time frame under Section 1981. To allow additional time for plaintiff to respond to the motion-and more time for the Court to rule on the motion-would require the Court and parties to proceed with scheduling and discovery regarding a broader scope of claims. Given the substantial delays already in the case, this additional delay is not acceptable.

Regarding the third factor, the reasons which plaintiff cites for the delay-(l) that the parties agreed to stay the response time until plaintiff found new counsel, and *1310 (2) that first counsel failed to inform second counsel of the pending motion-are not convincing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
175 F. Supp. 2d 1307, 51 Fed. R. Serv. 3d 872, 2001 U.S. Dist. LEXIS 20998, 2001 WL 1598036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-v-boeing-co-ksd-2001.