Butler Cnty. Landfill, Inc. v. Butler Cnty. Bd. of Supervisors

299 Neb. 422, 908 N.W.2d 661
CourtNebraska Supreme Court
DecidedMarch 23, 2018
DocketS-17-276
StatusPublished
Cited by68 cases

This text of 299 Neb. 422 (Butler Cnty. Landfill, Inc. v. Butler Cnty. Bd. of Supervisors) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler Cnty. Landfill, Inc. v. Butler Cnty. Bd. of Supervisors, 299 Neb. 422, 908 N.W.2d 661 (Neb. 2018).

Opinion

Miller-Lerman, J.

NATURE OF CASE

The Butler County Board of Supervisors (the Board) appeals from the order of the district court for Butler County which reversed the Board's decision to deny an application by Butler County Landfill, Inc. (BCL), to expand its solid waste disposal landfill area located in Butler County, Nebraska. We conclude that the district court lacked jurisdiction to enter the February 7, 2017, order from which this appeal is taken and that, consequently, we lack jurisdiction over this appeal. We therefore vacate the district court's order and dismiss this appeal.

STATEMENT OF FACTS

BCL, a wholly owned subsidiary of Waste Connections of Nebraska, Inc., operates a solid waste landfill located in Butler County near David City, Nebraska. The landfill has been in existence since 1986, and an expansion of the landfill was approved in 1992 which allowed it to accept solid waste from other counties. The record indicates that by 2015, BCL was accepting solid waste from 15 to 20 counties in eastern Nebraska and some additional counties outside Nebraska.

BCL determined that it needed to expand the solid waste landfill area in Butler County. Neb. Rev. Stat. §§ 13-1701 to 13-1714 (Reissue 2012) are the statutes that govern siting approval procedures for solid waste disposal areas and solid waste processing facilities. These statutes indicate that if denied, an applicant for siting approval can reapply after the passage of 2 years. See § 13-1711.

As required by § 13-1702, BCL filed a request for siting approval with the Board on July 6, 2015. In its request, BCL asserted, inter alia, that as the scope of the *664 area it served has expanded, the amount of solid waste it accepted had increased. BCL asserted that in the mid-1990's, it had accepted approximately 100,000 tons of solid waste per year; that by 2015, it accepted approximately 550,000 tons of solid waste per year; and that it projected that by 2020, it would receive 800,000 tons of solid waste per year. The size of the expanded landfill approved in 1992 was 144.79 acres. In the July 6 request, BCL sought approval to further expand into a 160-acre parcel of land it had purchased that was contiguous to the south side of its existing landfill.

As required by § 13-1706, the Board, on October 28, 2015, held a public hearing on BCL's request. Part of the purpose of a public hearing under § 13-1706 is to "develop a record sufficient to form the basis of an appeal of the decision." At the public hearing, the Board heard testimony by representatives of BCL and by members of the public, including those who favored and those who opposed BCL's request.

Following the public hearing and a written comment period which served to supplement the record of the public hearing, the Board met on December 14, 2015, to deliberate BCL's request. At that meeting, the Board considered, inter alia, the statutory criteria for siting approval set forth in § 13-1703, which provides that "[s]iting approval shall be granted only if the proposed area or facility meets all of" six specified criteria. The record of the deliberations shows that the Board considered in turn whether each criterion had been shown. At the end of the Board's discussion of each criterion, a poll was taken of the seven supervisors as to whether each supervisor thought that specific criterion had been met. Based on the polling of supervisors during the meeting, all supervisors agreed that three of the six criteria had been met, and all supervisors agreed that one criterion had not been met. With respect to the two remaining criteria, the votes were split, with a majority voting in each case that the criteria had not been met.

At the end of the discussion, based on the polling as to each criterion, a supervisor moved to deny the application, another supervisor seconded the motion, and the Board unanimously voted to deny the application. The supervisors thereafter signed a document titled "Decision Regarding Siting Approval," which set forth the procedures that had been followed with regard to BCL's application and which concluded that "[b]ased upon the finding that [BCL] has failed to meet all criteria required to be met under [§] 13-1703 it was moved ... and seconded ... that the [BCL application] be denied. Upon roll call vote, the motion was unanimously passed." This December 14, 2015, written decision did not specify which criteria were not met and did not further set forth reasons for the decision.

On February 10, 2016, BCL filed a petition in the district court for Butler County seeking judicial review, pursuant to § 13-1712, of the Board's denial of its siting application. At a hearing on the petition held on March 21, the district court received into evidence a transcript of the public hearing held October 28, 2015; the exhibits received at the public hearing; a transcript of the Board's December 14, 2015, meeting; and the Board's decision dated December 14, 2015.

After an additional hearing, the district court on June 17, 2016, filed a journal entry in which it referred to § 13-1712, which requires that "the district court shall consider the written decision and reasons for the decision of the ... county board and the transcribed record of the hearing held pursuant to [§] 13-1706." The court concluded that in addition to a written decision and a transcript of the *665 public hearing, the statute required the Board to "make a written statement of the reasons for its decision." The court stated that in this case, the

Board "simply found that [BCL] had failed to demonstrate the statutory requirements but did not specify any of its reasons for reaching that conclusion." Although the district court's jurisdiction was conferred under § 13-1712, rather than under the Administrative Procedure Act, the court cited cases under the Administrative Procedure Act regarding a failure "to make findings of fact and conclusions of law." The court concluded its June 17 journal entry with the following paragraph, which was titled "Remand":

The failure of the [B]oard to make specific fact findings as required by statute, necessitates that the order entered December 14, 2015 be set aside and the matter remanded to the ... Board ... with directions to make findings of fact supporting the order which they shall issue within thirty days of this remand.

For completeness, we note that because we lack jurisdiction over this appeal, we make no comment regarding the correctness of the district court's reading of the requirements of § 13-1712.

On July 14, 2016, the Board filed in the district court a "Notice of Compliance" stating that it had complied with the court's order. The Board attached to the filing a certified copy of a resolution passed by the Board on July 13 in which it stated that it had denied BCL's application by a unanimous vote and that it was adopting findings of fact "in further support of its denial" of BCL's application.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heist v. Nebraska Dept. of Corr. Servs.
979 N.W.2d 772 (Nebraska Supreme Court, 2022)
Preserve the Sandhills v. Cherry County
310 Neb. 184 (Nebraska Supreme Court, 2021)
McEwen v. Nebraska State College Sys.
303 Neb. 552 (Nebraska Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
299 Neb. 422, 908 N.W.2d 661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-cnty-landfill-inc-v-butler-cnty-bd-of-supervisors-neb-2018.