Busset v. California Builders Co.

12 P.2d 36, 123 Cal. App. 657, 1932 Cal. App. LEXIS 968
CourtCalifornia Court of Appeal
DecidedMay 25, 1932
DocketDocket No. 7084.
StatusPublished
Cited by9 cases

This text of 12 P.2d 36 (Busset v. California Builders Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Busset v. California Builders Co., 12 P.2d 36, 123 Cal. App. 657, 1932 Cal. App. LEXIS 968 (Cal. Ct. App. 1932).

Opinion

JOHNSON, J., pro tem.

This action was instituted by plaintiff to foreclose a lien claimed for work done by him under a subcontract made March 2, 1928, with M. G. Kendall, operating under the name of the California Builders Co., as the general contractor for the erection of a building for the defendant J. W. Helm, to be used in part for stores and offices, in part for a public garage.

Plaintiff’s contract was for the construction of interior walls; and in connection with their answer the defendants filed a cross-complaint against the plaintiff and Frank M. Clausen, who did the plastering under a subcontract made also with the general contractor and dated October 27, 1927.

After hearing the evidence, the trial court decided that the plaintiff Busset was entitled to a decree of foreclosure of the lien claimed, and that the defendants were not entitled to judgment under their cross-complaint against either Busset or Clausen. In due time a motion for a new trial was made by defendants and cross-complainants, which was denied so far as the motion related to Busset, but was granted as to the cross-defendant Clausen. Thereupon a motion was made immediately on behalf of Clausen to dismiss the action as to him, upon the ground that he was not a proper party defendant, and that no cause of action was stated against him in .the cross-complaint. That motion was forthwith granted. From the judgment in favor of plaintiff and from the order dismissing the action as to Clausen, the defendants and cross-complainants took this appeal.

The building in question is a four-story concrete office building with a public garage, situated in Oakland. The building was constructed for the owner, Helm, under a contract made by him with M. G. Kendall doing business under the name of California Builders Co., but the contract was not filed with the county recorder. The plans and specifications accompanying that contract called for use of hollow tiles for the interior walls. Instead of using tiles, how *660 ever, a contract was made through Kendall with Busset to construct a wall according to a process used by Busset, making what he called a Pacific wall, consisting of a composition of gypsum and rice hulls with water added to give fluidity in pouring. In soliciting the contract, Busset sub- ' mi tied a written offer dated February 3, 1928, in which the so-called Pacific wall is described as composed of one part of aerated stucco, two parts of rice hulls, with sufficient water to allow pouring into forms. Detailed specifications for the construction were embodied in the offer, and a price of $5,000, payable in progressive installments, was named. The offer having been accepted, a written contract was entered into on March 2, 1928, in which Busset agreed to install “Pacific wall partitions and fireproofing as per tender of Feb. 3, 1928” for the sum of $5,000, of which $3,400 was to be paid in specified installment payments up to the time of completion of the contract, and a further sum of $1,000 forty days after completion, together with a note for $600, payable in two years with interest at eight per cent and secured by deed of trust executed by the owner of the property. The contract provided that the work was to be done “in a first class manner, and in accordance with the plans and specifications for the building, complete in every respect, so as to insure a satisfactory job”. Since Busset’s work was to conform to the specifications in his tender of February 3d, the reference in the contract to plans and specifications of the building must be deemed to include Busset’s specifications as a substitute for those relating to the use of tiles.

The walls were installed by Busset, and the payments falling due up to the time of completion of his contract, and aggregating $3,400, were paid as the work progressed. The residue of the agreed price has not been paid; and a claim of lien having been duly recorded, Busset in this action seeks recovery of the balance of $1600 with interest and costs, and sale of the property in satisfaction of the lien asserted. Judgment in the amount claimed went in Busset’s favor, together with decree for foreclosure of the lien.

The defendants alleged in their pleadings that Busset knew that the walls were to be plastered in the usual way, and, when finished by the plasterer, were to be white and clean and free from defects. It is further averred that Bus- *661 set represented that walls built by his process were better than walls of tile and, when finished, produced a smooth surface capable of receiving plaster applied in the regular way. It is pleaded in addition that after Busset finished his work and the plastering had been done, blotches and discoloration appeared, so that painting became necessary in order to make the walls white and clean and free from defects, the cost of painting being $2,000; and claiming also damages in the sum of $1,000 by reason of delay charged in completion of the building; the defendants by their answer and their cross-complaint against Busset prayed that he take nothing by his complaint and that damages be awarded in favor of defendants and cross-complainants.

As has been stated, the cross-complaint brought in the plasterer, Clausen, as a cross-defendant; but attention will be given first to the controversy over the construction of the wall itself by Busset.

The trial court found, among other things, that the blotches and discolorations complained of were caused by plastering the walls before they had become sufficiently dry; that the plastering was thus done prematurely at the instance and under the direction of the general contractor, Kendall, with knowledge on his part of the moist condition of the walls; and that any damage suffered was caused by such premature plastering done under Kendall’s direction. The court further found that there was no negligence on the part of the plasterer; that no delay in completion had been caused by either Busset or Clausen, and that Busset was entitled to the amount of his lien claim. Nothing was allowed to the cross-complainants under the cross-complaint.

The issue as to the construction of the walls and the cause of the blotches and discolorations is one of fact; and since the court found that the defects complained of were due to the circumstance that, under orders of the general contractor or his agents, the walls were plastered while wet, our function is confined to ascertaining whether the record contains evidence sufficient to support such findings. The evidence is not free from conflict; but attention must be centered upon that which, as interpreted by the trial court, sufficed to create a preponderance in favor of Busset.

Complaint about blotches and discolorations appears to be directed mainly to the walls in the stores located on the *662 ground floor. There was testimony of M. L. Garrison, the superintendent, and Harold A. Probst, the foreman, employed by Kendall, and also testimony of Clausen, the plasterer, that the walls of the building appeared to be dry when the plastering began. On the other hand, Busset’s superintendent, George Smith, testified that the work on the walls started early in March and was completed about May 2d; and that about three weeks after the work began, there came rainy weather before the roof was on, in consequence of which the building became wet and the drying of the walls was retarded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petersen v. Bank of America Corp.
232 Cal. App. 4th 238 (California Court of Appeal, 2014)
Landau v. Salam
484 P.2d 1390 (California Supreme Court, 1971)
Dicker v. Bisno
318 P.2d 159 (California Court of Appeal, 1957)
Dallman Supply Co. v. Sweet
195 P.2d 864 (California Court of Appeal, 1948)
Kraft v. Smith
148 P.2d 23 (California Supreme Court, 1944)
Morris v. Duncan
58 P.2d 669 (California Court of Appeal, 1936)
San Francisco M. Co. Ltd. v. Mordecai
26 P.2d 669 (California Court of Appeal, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
12 P.2d 36, 123 Cal. App. 657, 1932 Cal. App. LEXIS 968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/busset-v-california-builders-co-calctapp-1932.