Busing v. Electronic Power Design, Inc.

986 F. Supp. 593, 1997 U.S. Dist. LEXIS 18583, 1997 WL 726263
CourtDistrict Court, D. Nebraska
DecidedNovember 19, 1997
Docket4:96CV3295
StatusPublished

This text of 986 F. Supp. 593 (Busing v. Electronic Power Design, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Busing v. Electronic Power Design, Inc., 986 F. Supp. 593, 1997 U.S. Dist. LEXIS 18583, 1997 WL 726263 (D. Neb. 1997).

Opinion

MEMORANDUM AND ORDER

KOPF, District Judge.

At the end of the plaintiffs’ 1 case-in-chief, and after viewing the evidence in the light most favorable to Dean Busing (Busing), I granted Steven G. Smith’s (Smith) motion for judgment as a matter of law under Federal Rule of Civil Procedure 50(a). Busing sued Smith, together with an equipment supplier, contending that Smith had a duty under Nebraska law to warn him of the instability of a truck load.

Although I orally explained my reasons for dismissing the case against Smith, explaining my reasoning in greater detail is appropriate. I proceed to that task now.

I.

Western Sand & Gravel Company employed Busing as the manager of that company. Busing is a large man. He weighed about 230 pounds when he was injured.

At a trade show in New Orleans Busing talked to a sales representative from Electronic Power Design, Inc. (EPD) about the purchase of heavy electrical equipment. After that conversation and through another company, Busing ordered three pieces of equipment from EPD. One piece of equipment was an “SCR.” This piece of equipment was 90 inches tall and weighed more than one thousand pounds. Protruding from one side of the SCR was an “appendage” that housed a transformer. The other two pieces of equipment were large and heavy also. The equipment was intended to be welded to a barge and was designed to run a dredge motor.

Smith is an independent truck driver whom EPD engaged to haul the equipment from Texas to Nebraska. There is no evidence that Smith had ever dealt with EPD before the incident in question. There is also no evidence that Smith had ever dealt with Busing or Western Sand & Gravel before. There is no claim that Smith had any specialized experience with large pieces of electrical equipment, although Smith was an experienced truck driver.

Viewing the evidence in the light most favorable to Busing, I assume that when Smith went to pick up the equipment at the EPD plant an EPD employee told him that the SCR was unstable. As a result, Smith, with the help of the EPD employee, built a wooden brace for the SCR so that the SCR would not shift during the trip from Texas to Nebraska.

After that, in the presence of Smith, the electrical equipment, including the SCR, was loaded on Smith’s flat-bed truck by EPD workers. The three pieces of equipment were placed on the truck so that each piece was very close to the other pieces. Smith lodged the brace he had built under the *595 appendage of the SCR. The three pieces of equipment were then tied down using straps. The load was then covered with tarps, and they tied down the tarps also.

After loading was complete, Smith left Texas and drove to Nebraska. Smith arrived at Western Sand & Gravel at 9:00 p.m. Sunday, April 17, 1994. About an hour before arriving Smith called Busing and told Busing when the load would be arriving.

Busing was anxious to get the equipment unloaded because the dredging season was starting. Despite the late hour, Busing and two other employees of Western Sand & Gravel met Smith at Western’s plant. Busing told Smith to park under some spot lights, and Busing and his men prepared to unload the truck.

Busing, Western Sand & Gravel, EPD and Smith anticipated that Western Sand & Gravel employees would unload the truck. Specifically, Busing did not expect Smith to play any part in the unloading, and, as Busing expected, Smith did not participate in that effort. As Busing was unloading the truck, Smith was looking after his equipment, including the tarps and straps. According to Busing, Smith’s activity in looking after his own equipment was “what you would expect.”

Because the equipment was heavy, it had to be unloaded by a crane. Western Sand & Gravel had its own crane. Busing told one of his men to get the crane, and the crane was moved to the place where they would unload the equipment. After that, in the glow of the lights, the three Western Sand & Gravel employees began the unloading process.

One of the Western Sand & Gravel employees operated the crane. Another served as an observer on the ground. Busing decided that he would hook the crane to the electrical equipment. To do this, Busing climbed on the flat-bed truck.

As Busing climbed on the truck, he could see how the three pieces of equipment were placed on the truck in relation to one another. At this time, the SCR was standing upright as it had been when it was loaded. Busing could observe the SCR. Busing also observed the brace that Smith had built. Viewing the evidence in the light most favorable to Busing, I assume that the brace was no longer lodged under the appendage of the SCR. Although Busing saw the brace on the floor of the truck, I further assume that he did not know its purpose. Busing removed the brace from the floor of the truck, and threw it toward the rear of the vehicle.

Busing decided to unload another piece of equipment before unloading the SCR. To do this, Busing was required to hook the crane to the piece that was to be unloaded first. The electrical equipment had “eye bolts” on the top of the equipment so that a crane could be hooked to the equipment for unloading.

Using the rear deck of the truck, Busing climbed on the SCR. He then leaned from the SCR to the other equipment and attached the crane to the first item to be unloaded. A ladder was available to Busing for this purpose, but he elected not to use it. Busing used the step deck of the truck and then the SCR as his “ladder.”

While standing on the SCR, Busing directed the crane operator to remove the first piece of equipment. As the crane was removing the first piece of equipment, the SCR began to tip. With Busing still standing on it, the SCR fell from the truck. Busing also fell. The SCR landed on Busing’s foot crushing his toes. Busing’s toes were later amputated.

A drawing of the SCR as it stood on the truck when Busing climbed on it is attached. 2 The drawing shows Busing standing on the SCR appendage. Busing admitted standing on the SCR appendage, but claimed that when the SCR fell he was standing on the top of the SCR rather than on the appendage. I have assumed that Busing’s testimony is true for purposes of the Rule 50 motion.

Busing presented testimony from Frank Searcella, an executive of Ranger Truck Lines. Ranger hauled the SCR to the EPD plant before Smith took the SCR to Nebraska. Searcella testified about the custom and practice in “the trucking industry as to the *596 type of warning ... [that] should be communicated to the people at the other end.”

Scarcella stated that it was the shipper’s responsibility, and not the driver’s responsibility, to provide unloading warnings. According to Scarcella, the shipper customarily lists such instructions on the bill of lading or packing slips. The truck driver’s sole responsibility, according to Scarcella, is to give the bill of lading or packing slips to the consignee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hopkins v. Fox & Lazo Realtors
625 A.2d 1110 (Supreme Court of New Jersey, 1993)
Schmidt v. Omaha Public Power District
515 N.W.2d 756 (Nebraska Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
986 F. Supp. 593, 1997 U.S. Dist. LEXIS 18583, 1997 WL 726263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/busing-v-electronic-power-design-inc-ned-1997.