Business Cabling, Inc. v. Yokeley

643 S.E.2d 63, 182 N.C. App. 657, 2007 N.C. App. LEXIS 786
CourtCourt of Appeals of North Carolina
DecidedApril 17, 2007
DocketCOA06-1255
StatusPublished
Cited by8 cases

This text of 643 S.E.2d 63 (Business Cabling, Inc. v. Yokeley) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Business Cabling, Inc. v. Yokeley, 643 S.E.2d 63, 182 N.C. App. 657, 2007 N.C. App. LEXIS 786 (N.C. Ct. App. 2007).

Opinion

TYSON, Judge.

Vitafoam, Incorporated (“defendant”) appeals from judgment and order entered following a bench trial in which the court concluded defendant had engaged in unfair and deceptive practices (“UDP”) with Business Cabling, Inc. (“plaintiff’). Plaintiff cross-appeals only the portion of the judgment allowing credit to defendant for any amount it recovers from Barry W. Yokeley (“Yokeley”). We reverse.

I. Background

Plaintiff is a North Carolina corporation with its principal place of business located in Davidson County, North Carolina. Plaintiff installs industrial grade computer cables. In 2004, Bud and Shira Hedgepeth owned ninety percent of plaintiff’s outstanding stock.

Yokeley was employed by plaintiff from 26 November 2001 to 6 February 2004. During this time, Yokeley was an officer and director of the corporation and owned ten percent of plaintiff’s stock. Yokeley was plaintiff’s sole representative in sales and marketing. His duties included: (1) soliciting new customers; (2) making business proposals to new and existing customers; (3) entering into contracts on plaintiff’s behalf with customers; and (4) supervising, performing, and carrying out these contracts with plaintiff’s customers. Yokeley’s employment was not subject to any covenant not to compete or a non-solicitation agreement with plaintiff.

*659 Defendant is a North Carolina corporation with its principal place of business located in Guilford County, North Carolina. Defendant manufactures foam used in various applications.

Richard Loftin (“Loftin”), Yokeley’s father-in-law, was defendant’s chief operating officer until April 2004. In 2003, Loftin informed Yokeley that defendant was considering an update of its computer network and might require new computer cable of the type installed by plaintiff. Loftin was not involved in any contract negotiations between plaintiff and defendant.

Between May and July 2003, Yokeley submitted a bid on behalf of plaintiff for a small cable installation at defendant’s High Point facility. Jim Bridges (“Bridges”) was defendant’s information technology director at that time and possessed authority to accept such small bids. Bridges accepted Yokeley’s bid, the work was completed, and defendant paid plaintiff in full.

In July 2003, defendant was considering a major upgrade of its computer network at its locations in: (1) High Point; (2) Greensboro; (3) Thomasville, North Carolina; (4) Tupelo, Mississippi; and (5) Chattanooga, Tennessee. On 28 July 2003, plaintiff through Yokeley submitted bids to perform the cable installation at these locations.

Bridges informed Yokeley that no contract would exist between plaintiff and defendant until: (1) each separate agreement was approved by defendant’s senior management; (2) a capital expense budget proposal was approved; (3) defendant was assigned a purchase order number; and (4) the purchase order number was given to plaintiff.

Between 19 September 2003 and 30 September 2003, Bridges accepted plaintiff’s proposals on defendant’s behalf for the High Point and Greensboro facilities. Plaintiff completed the work at both facilities, invoiced defendant, and was paid in full in December 2003.

In late 2003 or early 2004, defendant hired David Kame (“Kame”) as its new chief financial officer. Kame was instructed to carefully review all proposed projects. Defendant’s Thomasville and Chattanooga projects were placed on indefinite hold. The Tupelo project remained under consideration.

Defendant never accepted plaintiff’s bids to install cable at defendant’s Thomasville and Chattanooga locations. No contract *660 was entered into between plaintiff and defendant to perform any work at these locations. The Thomasville and Chattanooga projects were never performed by any vendor. Defendant ultimately sold these plants.

In late 2003, disputes arose between Bud and Shira Hedgepeth and Yokeley. In December 2003, Yokeley was asked to seek other employment. In January 2004, Yokeley began negotiations for employment with one of plaintiff’s competitors, Fleet Communications (“Fleet”). During Yokeley’s negotiations with Fleet, he presented a list of potential customers he felt he could bring to Fleet. This list included cable installations at several of defendant’s facilities, including Tupelo. Yokeley resigned from plaintiff on 6 February 2004 and became employed by Fleet on 9 February 2004.

On 5 January 2004, Yokeley prepared a bid proposal in his own name for defendant’s Tupelo project, prior to resigning from plaintiff. In mid-January 2004, Yokeley presented the bid to Bridges. On 18 February 2004, Bridges accepted Yokeley’s bid for defendant’s Tupelo project. Defendant’s cable installation in Tupelo was performed by Yokeley’s new employer, Fleet. Fleet invoiced defendant for the work and was paid in full.

After Yokeley became employed by Fleet on -9 February 2004, Fleet, through Yokeley, bid on and performed several other projects for defendant. None of these projects had been previously bid upon by plaintiff. Plaintiff presented no evidence it was even aware of these projects. Among the projects Fleet bid on was a new project at defendant’s Greensboro location (“new Greensboro project”). The new Greensboro project was completely separate and apart from any work plaintiff had previously bid on. On 11 February 2004, defendant accepted Fleet’s bid on the new Greensboro project. Fleet completed the work, submitted invoices, and was paid in full.

On 11 March 2004, Shira Hedgepeth contacted Bridges on plaintiff’s behalf and inquired for updates on any of defendant’s cable projects. Bridges responded he had no idea what the status of the projects were at that point and that until Bridges heard from defendant’s chief executive officers, and Bud Hedgepeth heard from him, “all bets [were] off.” On 12 March 2004, Bridges informed Shira Hedgepeth, “I think at this point you need to plan as though [defendant’s acceptance of plaintiff’s bids] is not going to happen, which is a real possibility.”

*661 At the time this electronic mail correspondence occurred between Shira Hedgepeth and Bridges, Bridges was aware that defendant had contracted with Fleet through Yokeley to perform cable installation work at defendant’s Tupelo and new Greensboro facilities. Bridges neither advised Shira Hedgepeth, nor any other person at plaintiff, that Fleet had performed the cable installation at defendant’s Tupelo and new Greensboro locations. Bridges’s employment with defendant was terminated on 31 March 2004.

On 15 September 2004, plaintiff filed suit against defendant and Yokeley. Plaintiff asserted claims against defendant for: (1) breach of contract; (2) breach of implied warranty of good faith and fair dealing; and (3) UDP. Plaintiff asserted claims against Yokeley for: (1) wrongful interference with contract; (2) UDP; and (3) punitive damages. Plaintiff’s claims against defendant were tried separately from its claims against Yokeley.

On 22 June 2006, the trial court concluded defendant had participated in UDP and entered judgment against defendant. The trial court awarded plaintiff treble damages in the amount of $96,272.88, $95,000.00 in attorneys fees and various other costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heron Bay Acquisition, LLC v. United Metal Finishing, Inc.
781 S.E.2d 889 (Court of Appeals of North Carolina, 2016)
McKinnon v. CV INDUSTRIES, INC.
713 S.E.2d 495 (Court of Appeals of North Carolina, 2011)
Carcano v. JBSS, LLC
684 S.E.2d 41 (Court of Appeals of North Carolina, 2009)
Meijer, Inc. v. Abbott Laboratories
544 F. Supp. 2d 995 (N.D. California, 2008)
TSC RESEARCH, LLC v. Bayer Chemicals Corp.
552 F. Supp. 2d 534 (M.D. North Carolina, 2008)
Anderson v. Dobson
627 F. Supp. 2d 619 (W.D. North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
643 S.E.2d 63, 182 N.C. App. 657, 2007 N.C. App. LEXIS 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/business-cabling-inc-v-yokeley-ncctapp-2007.