Bushra Company

CourtArmed Services Board of Contract Appeals
DecidedApril 22, 2016
DocketASBCA No. 59918
StatusPublished

This text of Bushra Company (Bushra Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bushra Company, (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Bushra Company ) ASBCA No. 59918 ) Under Contract No. M68450-06-M-7233 )

APPEARANCE FOR THE APPELLANT: Mrs. Bushra Mohammed Owner

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney ChristinaLynn E. McCoy, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PROUTY ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

Before the Board is the government's motion to dismiss for lack of jurisdiction, which has two bases: first, the government contends, appellant Bushra Company (Bushra) failed to file its appeal with the Board within 90 days of receipt of the contracting officer's final decision (COFD) terminating the subject contract for default; second, the government argues, Bushra's later claim to the contracting officer (CO) was (if timely) jurisdictionally defective because it did not include a sum certain. Bushra's response is confined to a defense on the merits of this action, arguing that it should not have had its contract terminated because of problems with the contracting officer's email. Bushra makes no effort, whatsoever, to address the government's challenges to our jurisdiction. The government's arguments prevail.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 25 September 2006, the government's Joint Contracting Command for Iraq and Afghanistan (JCC-1/A) awarded Contract No. M68450-06-M-7233 (the contract) to appellant Bushra in the amount of $328,440.00 for the delivery of limestone at various sites within Iraq (R4, tab 1 at 2-3). The contract's statement of work anticipated that performance would begin within 7 days of the contract award and take no longer than 30 days to complete (id. at 3). The contract also included a clause from the Department of Defense Federal Acquisition Regulation Supplement (DFARS) that provided that all correspondence with the government would be conducted in English (id. at DFARS 252.225-7041, CORRESPONDENCE IN ENGLISH (JUN 1997)).

2. Bushra never made the deliveries required by the contract (R4, tab 14 at 11 (Bushra's 2015 "Claim for settlement for limestone contract")). Whether this was the fault ofBushra, the government, or neither party is not relevant for resolution of the pending motion.

3. The government terminated Bushra's contract for cause 1 on 18 February 2007 (R4, tab 4). The termination was received the same day (R4, tab 14 at 15). The letter informed Bushra of its "right to appeal [the] determination under the Disputes clause cited in [Federal Acquisition Regulation (FAR)] Part 33.211" (R4, tab 4 at 1). The letter did not include language required by the FAR explaining the right to appeal to the agency board of contract appeals within 90 days (see id., FAR 33.21 l(a)(3)(v)). In addition to a letter to Bushra stating so, the government also issued a contract modification effecting the termination on the same date (R4, tab 5 at 1).

4. On 25 June 2012, Bushra sent an email to the Army stating that it had been out of Iraq "because of the security situation" and now wished to close out its contracts with the United States military (R4, tab 5 at 2). The email requested that the Army inform Bushra of the payments made on the contract (id.). The Army apparently responded to Bushra by forwarding it a copy of the contract modification terminating it for cause (id. at 1).

5. Bushra made no attempt to challenge the termination for cause in any manner until 5 August 2013, when it sent an email to Army contract closeout personnel inquiring about the status of the contract (R4, tab 6). After some back and forth with Army personnel, Ms. Joan Wysoske, Chief ofReachback Closeouts for the Army Contracting Command, wrote to Bushra that the contract had been terminated for Bushra's "failure to perform" and that a copy of the modification was sent to Bushra on 29 June 2012 2 (R4, tab 10 at 4). Ms. Wysoske also wrote that, "no compensation is coming to you" (id. at 3). Bushra responded that its failure to perform was the Army's fault (id.).

6. More email traffic followed, including a statement from Bushra on 2 September 2013 that it "want[ ed] compensation equals to our lost money" (R4, tab 10 at 2). On 3 September 2013, the Army told Bushra that it needed to submit a claim telling the Army, "the exact amount of the money you wish the government to pay you and why the government should pay you any compensation" (id.). On 10 September 2013, Bushra sent to the Army an email with an attachment that it characterized as its "claim for settlement" (see id. at 1-2; R4, tab 13 (the apparent attachment)).

1 As in the referenced clause in the Federal Acquisition Regulation (FAR), FAR 52.212-4(m), the government could use the terms "termination for cause" and "termination for default" interchangeably. 2 The 29 June 2012 correspondence, itself, is not in any of the files produced in this case, though the statement that there was such correspondence is consistent with the documents in tab 5 of the Rule 4 file. 2 7. The 17-page attachment (Bushra's claim) consisted largely of "screen shots" of email between Bushra and various Army personnel discussing performance of the contract with a narrative interspersed between the screenshots (see R4, tab 13). We construe it to be solely a challenge to the Army's termination for cause, and to constitute an effort to recoup money that Bushra lost as a consequence of that termination (R4, tab 13 at 15). In general, Bushra argued that its designated point of contact with the Army, lLT Todd Lohstreter, was not receiving his emails as a result of a problem on lLT Lohstreter's end and that this prevented Bushra from performing (R4, tab 13 at 4). On page 15 ofBushra's claim, it stated that it needed to make a settlement for "all the cost we spent under this contract" and then referred the reader to its agreement with the Boad Almada company for limestone, which it purportedly paid (id. at 15). The remaining two pages ofBushra's claim appear to be in Arabic and include some tables with numbers in them, but it is not clear what the numbers represent or in what denomination they would be if the figures actually are costs (see id. at 16-17).

8. Ms. Wysoske informed Bushra, on 26 September 2013, that the document referred to as Bushra' s claim did not, in fact, constitute a claim because it did not include the amount of money requested from the government and, ifthat amount were greater than $100,000, it needed to be certified (R4, tab 10 at 1). She also attached a sheet of instructions about how to file a claim (id.). On 17 October 2013, Ms. Wysoske, in response to a follow-up email from Bushra, informed it that she "reject[ed]" its claim as "untimely and unsupported" and added that Bushra never gave her a "dollar amount of the claim" (R4, tab 11 ).

9. There, things laid for a little more than a year, until 28 October 2014, when Bushra sent another email to the Army, essentially resubmitting the identical claim, dated 10 September 2013, that Ms. Wysoske had earlier "reject[ed]" (R4, tab 13). The Army responded on the same date, explaining that it had reviewed the documentation provided by Bushra and that "[n]o payment will be made" (R4, tab 12 at 1). On 5 January 2015, Bushra again sent an email to the Army attaching the same claim and requesting a response (R4, tab 14).

10. On 8 January 2015, CO Thomas Petkunas issued what he characterized as a "final decision," rejecting the claim (R4, tab 15 at 1). This "final decision" noted that the claim was "untimely and unsupported" and that Bushra never gave a dollar amount for the claim (id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Bushra Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bushra-company-asbca-2016.