Bushnell Steel Co. v. United States

91 F. Supp. 576, 117 Ct. Cl. 348, 1950 U.S. Ct. Cl. LEXIS 23
CourtUnited States Court of Claims
DecidedJuly 10, 1950
DocketNo. 47534
StatusPublished

This text of 91 F. Supp. 576 (Bushnell Steel Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bushnell Steel Co. v. United States, 91 F. Supp. 576, 117 Ct. Cl. 348, 1950 U.S. Ct. Cl. LEXIS 23 (cc 1950).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff sues for extra costs incurred by reason of delays on the part of the Navy Department of the United States in furnishing it with certain information which it had to have before it could ship ten barges ordered by the Navy.

In August 1944 plaintiff had entered into a contract with the United States Army Transportation Corps to construct for it 11 crane barges. After the cessation of hostilities in Europe this contract was terminated, to wit, on June 13, 1945, whereupon plaintiff closed its plant, discharged its personnel, and cancelled all of its subcontracts in connection with the construction of the barges. When the contract was terminated one barge had been shipped, leaving 10 to be delivered under the Army contract. Apparently, this was the only work upon which plaintiff was engaged at the time.

A little less than a week later, the United States Navy Department notified plaintiff that the Navy wanted the remaining 10 barges which the Army had previously ordered, and on the following day it sent plaintiff a telegram reading in part:

[359]*359ENTER OUR ORDER * * * POR TEN KD STEEL BARGES WHICH ARE BEING TERMINATED ON ARMY TRANSPORTATION CORP CONTRACT W33-092 TO-2818 FOR SHIPMENT TO ADVANCE BASE DEPOT GULFPORT MISSISSIPPI PRICES AND TERMS TO BÍB NEGOTIATED NAVAL INSPECTION WILL BE REQUIRED WIRE ACKNOWLEDGMENT CONFIRMATIONS' TO FOLLOW

On the same day plaintiff • wrote the Navy Department proposing to furnish the ten uncompleted barges previously ordered by the Army for $54,530.00 each.

Plaintiff’s executive vice president then went to Chicago to confer with the Navy Department relative to prices and terms for the remaining 10 barges! It was there agreed that no change would be made in the design of them, but that there would be certain changes in marking and shipping instructions, which were to be forwarded to plaintiff immediately by air mail. It was agreed that one barge would be shipped within a week from receipt of defendant’s order, two within the following 30 days, and three every 30 days thereafter until the contract had been fully performed. It was also agreed that in order to avoid delay in resuming production for the Navy that $4,000 per barge would be added to the price at which plaintiff had agreed to furnish the barges to the Army, in order to cover all expenses and damages suffered by plaintiff as a result of the termination of the Army contract. A formal purchase order was to be prepared and furnished the plaintiff.

■ This agreement was confirmed by letters exchanged between the parties, wherein the plaintiff agreed to furnish the 10 remaining barges at $54,530.00 each, and to relieve the Government from any liability on account of the termination of the Army contract.

The Navy had immediate need for the barges and urged plaintiff to expedite delivery as much as possible, even in advance of the agreed delivery dates if it was possible to do so.

When the Army terminated its contract with plaintiff, plaintiff had completed the second barge and was ready to ship it. It could have shipped this barge under its contract with the Navy almost immediately upon receiving the Navy’s [360]*360order, except for the fact that it had to await marking and shipping instructions from the Navy. While awaiting these instructions plaintiff proceeded with fabrication of the parts for the remaining barges. It resumed fabrication of these remaining parts on Monday, June 25, on which day there was expended 853 man-hours of labor, 528 man-hours of which were direct labor on the barges. From this time on, until July 12, it spent approximately 900 man-hours per day. During all this time it was awaiting marking and shipping instructions from the Navy. On June 28, 1945, six days after the conclusion of plaintiff’s conference with the Navy in Chicago, the Navy wired plaintiff that the painting specifications for the barges as set out in the Army contract were to be used and that marking instructions “should be available tomorrow; will advise further.”

Since, when plaintiff entered into the contract with the Navy it already had on hand one barge ready for shipment, and since under the urgings of the Navy it was expending every possible effort to complete the remaining barges, and since it had not received marking and shipping instructions for any of the barges, its plant became congested with the parts already fabricated and being fabricated; hence, on July 2 it sent the Navy Department a telegram reading in part:

COMPLETED CRANE BARGE HAS OUR FACILITIES BLOCKED IMPEDING PRODUCTION. URGENT WE RECEIVE IMMEDIATE MARKING INFORMATION ENABLING US TO MAKE SHIPMENT. PLEASE WIRE WHEN CAN EXPECT.

Three days later the Navy Department in Chicago wrote plaintiff transmitting packing specifications and marking instructions, but there was not enclosed therein a certain ■“shipping symbol”, which the instructions called for. Plaintiff did not receive this until July 11, 1945. Until this was received none of the parts could be shipped.1

Defendant does not dispute plaintiff’s assertion that its plant was seriously congested during this period, nor that this congestion substantially increased plaintiff’s cost of production.

[361]*361■ It seems that plaintiff had a ten-ton crane which ran alongside its plant and which was used for the transportation of materials, first from the point where they were received from the railroad siding on the east side of plaintiff’s plant, and then to the various jigs where work was done upon them, and then to the west of plaintiff’s plant where they were painted.and packed, and from which they were then moved by the crane back to the railroad siding for loading. When the Army contract was terminated quite a lot of the parts for the barges were stored in the west portion of the crane runway and in intermediate places along this runway between the west end and the east end, and, as production continued, additional parts had to be stored in this area while awaiting shipping instructions for the parts already fabricated. This resulted in the storage of parts out of order and required handling and rehandling of the parts, which would not have been necessary except for the congestion. All of this apparently considerably increased plaintiff’s costs.

Had defendant promptly given plaintiff marking and shipping instructions, much of this congestion would not have developed. Nor was plaintiff at fault for continuing to fabricate other parts, which of course increased the congestion, since the defendant had urged plaintiff to speed production as much as possible, and since at the conference in Chicago on June 20-22 it had promised to send marking and shipping instructions immediately by air mail, and on June 28 it had advised plaintiff that marking instructions should be available the following day. Plaintiff had a right to expect that the necessary instructions for shipment of the parts for the barges would be in hand at any moment, and, hence, it would seem that it was justified in continuing production, even though this aggravated the congestion.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
91 F. Supp. 576, 117 Ct. Cl. 348, 1950 U.S. Ct. Cl. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bushnell-steel-co-v-united-states-cc-1950.