Busbee v. Gagnon Co.

146 P. 275, 50 Mont. 203, 1915 Mont. LEXIS 7
Montana Supreme Court·Decided January 23, 1915·No. No. 3,449·Published

Opinion

MR. CHIEF JUSTICE BRANTDY

delivered the opinion of the court.

' This action was brought to recover a judgment for damages for breach of a contract. On May 12, 1912, the defendant having theretofore secured a contract for the erection of a courthouse for Granite county, the plaintiff entered into a contract with it to manufacture and deliver to it at the courthouse site “400,000 brick or more,” as required by the defendant, at an agreed price of $10.50 per thousand. The defendant was to notify the plaintiff of the approximate number .required, “not later than the time for the burning of the last kiln.” It was stipulated that the plaintiff should “commence delivering the brick not later than July 1 in sufficient quantities to keep the work going,” but that a delay not to exceed a week later than that date, resulting from bad weather or other unavoidable cause stopping the work of brickmaking, the plaintiff using due diligence, should not be deemed a violation of the contract. On the 10th day of each month the plaintiff was to receive payment in full, at the stipulated price, for all brick delivered during the previous month. As a ground for recovery it is alleged, in substance, that the plaintiff between July 1 and September 15, 1912, manufactured 400,000 brick and delivered to the defendant according to the terms of the contract’ 313,622, for which he received the contract price per thousand; that he thereafter offered to deliver the balance of 86,378, in such numbers and at such times as the defendant might ■ require, and demanded that the defendant inform the plaintiff as to the number required and the time of delivery; and that he was [209] informed by the- agents of defendant that it would not accept further delivery from him. It is further alleged that the plaintiff has duly performed all the conditions of the contract to be performed by him; that he is ready and willing to deliver the balance due, and that by defendant’s refusal to accept delivery thereof and pay the purchase price, he has been damaged in the sum of $909. Defendant’s answer, besides making denial of some of the allegations of the complaint presenting issues which it is not now necessary to notice, alleged the following counterclaims as defenses: (1) That the plaintiff violated the contract in failing to deliver brick during the month of- July in quantities sufficient to keep the work going; that defendant was compelled to purchase brick elsewhere to the number of 36,000, at a cost of $3 per thousand higher than the contract price; and that by reason of the premises the defendant was damaged in the sum of $108. (2) That the plaintiff failed to deliver brick sufficient to keep the work going, whereby the defendant was compelled to lay off men and delay the work of erection for more, than, twenty days, at a cost of $20 per day, thus suffering damage in the sum of $400. And (3) that large numbers of the brick furnished by the plaintiff were unsuitable for use and unfit to be put into the walls of the building because they were broken into pieces at the time of delivery; that because of their broken condition the cost of laying the whole number delivered by plaintiff was $1.50 per thousand over and above what the cost would have been had plaintiff delivered them in' suitable condition; and that defendant thereby suffered damage in the sum of $470.43. Judgment is demanded for these several fl.mnnnt.s- Upon all of these defenses there was issue by reply. The court made findings in favor of plaintiff on all the issues, except those arising upon the first counterclaim. In this behalf it found that the defendant was entitled to a credit of the amount paid for the 36,000 brick at the price of $13.50 per thousand, and that for the balance the plaintiff was entitled to recover at the price stipulated in the contract, less $1.75 per thousand,-the cost of hauling from the kiln to the courthouse [210] site. It ordered judgment for tbe plaintiff for tbe balance thus ascertained, amounting to $332.80, together with costs of the action. The defendant has appealed from the judgment and the order denying its motion for a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Busbee v. Gagnon Co., 146 P. 275, 50 Mont. 203, 1915 Mont. LEXIS 7 (Mo. 1915).

146 P. 275 (Busbee v. Gagnon Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Best Manufacturing Co. v. Hutton
141 P. 653 (Montana Supreme Court, 1914)
Ashley v. Rocky Mountain Bell Telephone Co.
64 P. 765 (Montana Supreme Court, 1901)
Murray v. City of Butte
88 P. 789 (Montana Supreme Court, 1907)
Raiche v. Morrison
130 P. 1074 (Montana Supreme Court, 1913)
Wallace v. Weaver
133 P. 1099 (Montana Supreme Court, 1913)
Hillman v. Luzon Cafe Co.
142 P. 641 (Montana Supreme Court, 1914)