Busbee v. Gagnon Co.

146 P. 275, 50 Mont. 203, 1915 Mont. LEXIS 7
CourtMontana Supreme Court
DecidedJanuary 23, 1915
DocketNo. 3,449
StatusPublished

This text of 146 P. 275 (Busbee v. Gagnon Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Busbee v. Gagnon Co., 146 P. 275, 50 Mont. 203, 1915 Mont. LEXIS 7 (Mo. 1915).

Opinion

MR. CHIEF JUSTICE BRANTDY

delivered the opinion of the court.

' This action was brought to recover a judgment for damages for breach of a contract. On May 12, 1912, the defendant having theretofore secured a contract for the erection of a courthouse for Granite county, the plaintiff entered into a contract with it to manufacture and deliver to it at the courthouse site “400,000 brick or more,” as required by the defendant, at an agreed price of $10.50 per thousand. The defendant was to notify the plaintiff of the approximate number .required, “not later than the time for the burning of the last kiln.” It was stipulated that the plaintiff should “commence delivering the brick not later than July 1 in sufficient quantities to keep the work going,” but that a delay not to exceed a week later than that date, resulting from bad weather or other unavoidable cause stopping the work of brickmaking, the plaintiff using due diligence, should not be deemed a violation of the contract. On the 10th day of each month the plaintiff was to receive payment in full, at the stipulated price, for all brick delivered during the previous month. As a ground for recovery it is alleged, in substance, that the plaintiff between July 1 and September 15, 1912, manufactured 400,000 brick and delivered to the defendant according to the terms of the contract’ 313,622, for which he received the contract price per thousand; that he thereafter offered to deliver the balance of 86,378, in such numbers and at such times as the defendant might ■ require, and demanded that the defendant inform the plaintiff as to the number required and the time of delivery; and that he was [209]*209informed by the- agents of defendant that it would not accept further delivery from him. It is further alleged that the plaintiff has duly performed all the conditions of the contract to be performed by him; that he is ready and willing to deliver the balance due, and that by defendant’s refusal to accept delivery thereof and pay the purchase price, he has been damaged in the sum of $909. Defendant’s answer, besides making denial of some of the allegations of the complaint presenting issues which it is not now necessary to notice, alleged the following counterclaims as defenses: (1) That the plaintiff violated the contract in failing to deliver brick during the month of- July in quantities sufficient to keep the work going; that defendant was compelled to purchase brick elsewhere to the number of 36,000, at a cost of $3 per thousand higher than the contract price; and that by reason of the premises the defendant was damaged in the sum of $108. (2) That the plaintiff failed to deliver brick sufficient to keep the work going, whereby the defendant was compelled to lay off men and delay the work of erection for more, than, twenty days, at a cost of $20 per day, thus suffering damage in the sum of $400. And (3) that large numbers of the brick furnished by the plaintiff were unsuitable for use and unfit to be put into the walls of the building because they were broken into pieces at the time of delivery; that because of their broken condition the cost of laying the whole number delivered by plaintiff was $1.50 per thousand over and above what the cost would have been had plaintiff delivered them in' suitable condition; and that defendant thereby suffered damage in the sum of $470.43. Judgment is demanded for these several fl.mnnnt.s- Upon all of these defenses there was issue by reply. The court made findings in favor of plaintiff on all the issues, except those arising upon the first counterclaim. In this behalf it found that the defendant was entitled to a credit of the amount paid for the 36,000 brick at the price of $13.50 per thousand, and that for the balance the plaintiff was entitled to recover at the price stipulated in the contract, less $1.75 per thousand,-the cost of hauling from the kiln to the courthouse [210]*210site. It ordered judgment for tbe plaintiff for tbe balance thus ascertained, amounting to $332.80, together with costs of the action. The defendant has appealed from the judgment and the order denying its motion for a new trial.

That the findings and decision of the trial court upon the first counterclaim were correct is not now questioned. The only contention made is that the findings upon the issues relating to the second and third are not justified by the evidence. As to the second, the evidence discloses these facts: The plaintiff, having finished the burning of his first kiln containing 100,000 brick, began and continued deliveries until July 31, when delivery of the entire number of 100,000 was completed. The plaintiff was then engaged in burning a second kiln containing 200,000, having been delayed in completing it because of his inability to procure wood. On August 4, Mr. Hebb, the agent of defendant in charge of the construction work, was at the brickyards of plaintiff. Upon inquiry of plaintiff, he found that the burning would not be completed before August 12, and hence that the work of construction would be delayed until that time. Immediately thereafter he purchased 36,000 brick from a manufacturer in Missoula. There were then at the building site enough brick of those theretofore delivered by plaintiff to keep the work going for one more day. A part of those already delivered had been, by consent of defendant, diverted to a building in course of construction near by, by another contractor. Delivery of these was considered by defendant a delivery to it under the contract. It afterward paid for them. No complaint was made of the delay between August 4 and August 12, and as soon as the kiln was finished, and on August 12, plaintiff resumed and continued deliveries until the brickwork on the building was completed. Payments were punctually made by defendant as stipulated, in the contract, without notice to plaintiff that he would be held accountable for his failure to deliver brick sufficient to keep the work going. As to these facts there is no controversy, except as to the extent of the delay. Mr. Hebb testified that the construction work was delayed, for want of [211]*211brick, from July 20 to August 12. While admitting that during July he diverted some brick to another building, he stated that the number was only 3,000. Plaintiff had fixed the number at 5,700. Mr. Suiter, another witness and an employee of defendant, said that the delay covered three or four weeks. Both stated, by way of conclusion, that the delay caused the defendant a daily loss of $20. There was no evidence showing, or tending to show, that the defendant was compelled to lay off any men as alleged in the answer, or to retain any in idleness for any number of days or at all. Nor did it appear that the defendant had to pay -the county a penalty for delay in the completion of the building. Neither of these witnesses — who were the only ones who testified on the subject — undertook to contradict the statement of the plaintiff as to what the condition of the supply of brick was on August 4, when the purchase was made at Missoula; nor is there any evidence tending to show that the bricklayers were not kept busily employed in laying these brick during every day from August 4 to August 12, when [1-3] plain-tiff resumed deliveries. In view of the admitted facts and the lack of definite statement by either witness justifying an inference that the defendant suffered damage, its claim for damages in a substantial amount was properly considered without foundation in the evidence. “No damages can be recovered for a breach of contract which are not clearly ascertainable, in both their nature and origin.” (Rev. Codes, sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Best Manufacturing Co. v. Hutton
141 P. 653 (Montana Supreme Court, 1914)
Ashley v. Rocky Mountain Bell Telephone Co.
64 P. 765 (Montana Supreme Court, 1901)
Murray v. City of Butte
88 P. 789 (Montana Supreme Court, 1907)
Raiche v. Morrison
130 P. 1074 (Montana Supreme Court, 1913)
Wallace v. Weaver
133 P. 1099 (Montana Supreme Court, 1913)
Hillman v. Luzon Cafe Co.
142 P. 641 (Montana Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
146 P. 275, 50 Mont. 203, 1915 Mont. LEXIS 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/busbee-v-gagnon-co-mont-1915.