Burt v. Garden City Sand Co.

141 Ill. App. 603, 1908 Ill. App. LEXIS 729
CourtAppellate Court of Illinois
DecidedJune 16, 1908
DocketGen. No. 14,070
StatusPublished
Cited by2 cases

This text of 141 Ill. App. 603 (Burt v. Garden City Sand Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burt v. Garden City Sand Co., 141 Ill. App. 603, 1908 Ill. App. LEXIS 729 (Ill. Ct. App. 1908).

Opinion

Mr. Justice Smith

delivered the opinion of the court.

It was contended on the trial by appellant that the careless, negligent and indifferent operation of appellee’s plant prior to October 15, 1906, and the communications received by it from appellee to the effect that he expected to close his plant, and that the same would probably remain closed for a period of sixty days, and that he did not know that he would be able to operate it again, justified appellant in declining to pay the amount of money due October 15, 1906, until such time as an estimate of the damage which such course would entail upon it could be made, to the end that it might recoup such damages out of the amount so found due to appellee for cement delivered under the contract at that time.

It was further claimed by appellant that the contract required a reasonable and continued operation of the plant by appellee during the year, and that appellee failed to fulfill his contract in this regard, and consequently fell behind in his shipments on orders from appellant.

At the beginning of the trial it was agreed in substance between the parties that $50,082.31 worth of cement had been shipped by appellee to appellant in August, September and October, 1906, none of which had been paid’for by appellant; that appellant had returned sacks, etc., to the amount of $16,735.29 and that there was due appellee from appellant the sum of $34,317.48 with interest, subject to such set-off as appellant might prove, if any, and subject also to appellant’s further right to disprove the correctness of any items in appellee’s claim if it should be able to do so.

From these contentions and the stipulation of the parties it appears that the dispute between the parties depends in great, measure upon the construction of the contract set out in the statement preceding this opinion. The theory on which the trial court proceeded, apparently, was that appellee under the contract was bound to run his mill at its reasonable capacity throughout the year, or to use all reasonable effort to do so; and on this theory much irrelevant and immaterial evidence was introduced by appellant.

Our opinion is that the court erred in adopting appellant’s view of the contract. By the terms of the contract appellant agreed “to buy the entire output of cement manufactured during the year 1906 by the party of the first part at their cement plant, located at Bellevue, Michigan.” No specific amount of cement was mentioned in the contract except the 65,000 barrels which were to be manufactured and ordered out at once. There is no dispute that this quantity of cement was manufactured by appellee, but it was not ordered to be shipped by appellant for several months, for some reason not made to appear in the record. The contract in terms did not require appellee to manufacture and ship any other specific amount of cement, nor did it require appellee to run his plant in any particular way or prohibit him from closing his plant whenever he might find it desirable or necessary so to do in the prosecution of his business. If the contract contains any provision which obligated appellee to keep his mill running at its reasonable capacity throughout the year, regardless of whether it would be profitable, or otherwise convenient for him to do so, it is by implication from extraneous facts and not by any express provision. A court is not justified in reading into a written contract a provision which the parties to it have failed to insert, simply because from one point of view it would have been reasonable or desirable.

In the leading case of Aspdin v. Austin, 5 Ad. & El. (N. S.) 67, the doctrine and the reasons therefor are stated with great clearness as follows:

“Where parties have entered into written engagements, with express stipulations, it is manifestly not desirable to extend them by implication; the presumption is, that having expressed some, they have expressed all the conditions by which they intend to be bound under the instrument. It is possible that each party to the instrument may have contracted on the supposition that the business would in fact be carried on, and the service in fact continued, during the three years, and yet neither party might have been willing to bind themselves to that effect; and it is one thing for the court to effectuate the intention of the parties to the extent to which they have, even imperfectly, expressed themselves, and another to add to the instrument all such covenants as upon full consideration the court may deem fitting for completing the intention "of the parties, but which they, either purposely or unintentionally, have omitted. The former is but the application of a rule of construction to that which is written; the latter adds to the obligation by which the parties have bound themselves, and is, of course, quite unauthorized, as well as liable to great practical injustice in the application.”

This is the well-settled law of construction and interpretation of contracts as announced in all the authorities on this subject; and it forbids the court to add to the provisions expressed in the contract before us a new and distinct undertaking.

There is no controversy in the record that appellant refused to make the payment due, under the contract, on October 15,1906. In our opinion, this was a breach of a material condition of the contract which entitled appellée to terminate the contract. Keeler v. Clifford, 165 Ill. 544; Dobbins et al. v. Higgins et al., 78 id. 440; L. S. & M. S. Ry. Co. v. Richards, 152 id. 59.

Appellant assigns error in the giving of the following instruction to the jury:

6 ‘ The court instructs the jury that the refusal on the part of the defendant to make payment on the 15th day of October, 1906, in accordance with the terms of the contract entered into by and between the parties amounted to a breach of said contract on its part.

“And you are further instructed, as a matter of law, that such breach "of the contract on its part entitled the plaintiff to refuse to make any further shipments of cement under said contract.

“And the court further instructs the jury that the plaintiff, having elected to abandon the contract by reason of such breach on the part of the defendant on and after October 27, 1906, the jury should consider the contract as rightfully terminated on and after said last, mentioned date.”

The objections made to this instruction are that it assumed that the conduct of appellee did not authorize the action of appellant in withholding the payment due October 15, 1906; and it also assumed that notwithstanding the violation of the terms of the contract by appellee in closing his plant, or so representing to appellant, the contract was still in full force, had not been violated, and that closing the mill was not a breach on the part of appellee which justified the course pursued by appellant.

For reasons given above we think the instruction was proper, and we see no serious objection to it. The law is well settled that the non-payment of the instalment named in the instruction was a breach of a material condition of the contract, and entitled appellee to abandon the contract and sue for the amount actually due thereunder. Keeler v. Clifford, supra; Dobbins v. Higgins, supra; L. S. & M. S. Ry. Co. v. Richards, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rubin Bros. Mfg. Co. v. A. J. Johnson & Sons Furniture Co.
167 Ill. App. 622 (Appellate Court of Illinois, 1912)
Robidoux v. Baltz
153 Ill. App. 100 (Appellate Court of Illinois, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
141 Ill. App. 603, 1908 Ill. App. LEXIS 729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burt-v-garden-city-sand-co-illappct-1908.