Burrell Industries v. Harrison Processing, Unpublished Decision (6-24-1999)

CourtOhio Court of Appeals
DecidedJune 24, 1999
DocketCase No. 503
StatusUnpublished

This text of Burrell Industries v. Harrison Processing, Unpublished Decision (6-24-1999) (Burrell Industries v. Harrison Processing, Unpublished Decision (6-24-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burrell Industries v. Harrison Processing, Unpublished Decision (6-24-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
Plaintiff-appellant, Burrell Industries, Inc., appeals the decision of the Harrison County Court of Common Pleas, finding in favor of defendant-appellee, Harrison Processing Corporation, in its counterclaim for damages.

On March 11, 1994, Burrell Industries, Inc. (hereinafter "Burrell") filed a complaint in the Harrison County Court of Common Pleas, seeking the amount owed on an account with Harrison Processing Corporation (hereinafter "HPC") for the delivery of concrete. HPC's answer alleged that the concrete provided by Burrell was inferior and defective. In addition, HPC filed a counterclaim alleging that Burrell's defective product had caused damage to HPC in an amount exceeding $9,300.

A bench trial was held on October 20, 1997. The testimony at trial revealed the following. In the summer of 1993, Harrison began work on a railroad car unloading facility in Harrison County, Ohio. In order to accommodate the weight of railroad cars filled with coal, the foundation for the facility required concrete with a compressive strength of 3,000 psi (pounds per square inch). Mark McIntyre, plant manager for HPC, testified at trial that he telephoned A-1 Concrete, a division of Burrell, and inquired as to whether Burrell could supply five-hundred yards of 3,000 psi concrete. McIntyre was informed that such an order would not be a problem, but was advised to submit a purchase order. McIntyre issued the purchase order requesting five-hundred yards of 3,000 psi concrete.

Edward Goettel, the superintendent of Lone Pine Construction, the construction company hired by HPC, testified that when the concrete arrived on July 12, 1993, it did not look right. Goettel questioned Burrell's delivery driver who called his office to make sure the concrete was 3,000 psi. The driver reported back that the office had informed him the concrete was 3,000 psi. Still unsatisfied, Goettel then personally called Burrell and was assured by Kevin Richards, an employee of Burrell, that the concrete was indeed 3,000 psi. The concrete was then poured into the foundation.

At the time the concrete was poured, several test cylinders were made for use in subsequent strength testing on the concrete. The samples were tested by Ray McFeaters, a laboratory supervisor for Construction Engineering Consultants. McFeaters testified that all of the samples revealed that the concrete had failed to cure with the required compressive strength and was therefore substandard.

Although HPC paid for the concrete delivered on July 12, 1993, a number of subsequent deliveries were not paid for. According to George Landers, the credit manager for Burrell, at the time of trial HPC had an outstanding balance of $10,602.49, and owed an additional $7,633.97 in account service charges. Following the filing of post trial briefs, the trial court entered its judgment on April 29, 1998. At the same time, the trial court filed lengthy findings of fact and conclusions of law. Specifically, the trial court found that HPC had ordered 3,000 psi concrete, that Burrell had repeatedly assured HPC that the concrete was 3,000 psi, that testing had showed the concrete to be substandard and defective, that HPC had stopped payment on its account with Burrell only after the test results had confirmed the substandard concrete, and that HPC had been damaged in the amount of $15,000. In addition, the trial court found that down time in order to repair the facility would cost HPC an additional $14,000. Accordingly, the trial court awarded $29,000 to HPC, which amount was offset by the $10,602.49 owed on the account, for a total judgment of $19,397.51.

Burrell filed a timely notice of appeal on May 15, 1998 and brings four assignments of error, the first of which states:

"The Trial Court erred in striking the testimony of Burrell's rebuttal expert whose testimony was presented in response to Harrison's expert who testified with regard to the [sic] Harrison's counterclaim."

Burrell argues that the trial court erred in striking the testimony of Joe Belot, an expert for Burrell. Belot was called by Burrell as a rebuttal witness at the conclusion of HPC's case-in-chief. After Belot began testifying, counsel for HPC objected on the grounds that Belot was not rebutting facts elicited during HPC's case-in-chief, but, rather, was offering an expert opinion that should have been presented during Burrell's case-in-chief. Burrell responded that Belot had been called to rebut the testimony of Regis Leach, whose deposition had been admitted into evidence for the trial court to read at a later time. The trial court reserved ruling on the objection and permitted Belot to testify.

In its findings of fact and conclusions of law issued after the trial, the trial court stated as follows:

"20. Mr. Belot's testimony was objected to as not being proper rebuttal. The Court reserved ruling until he had read Mr. Leach's testimony. the [sic] purpose of Rebuttal is to contradict facts, not to give expert opinions in chief. That should have been put in in [sic] Burrell's main case. Plaintiff had deposed Mr. Leach and knew what his testimony would be. Therefore, all of Mr. Belot's testimony is objectionable and is stricken as not proper rebuttal."

HPC argues this conclusion by the trial court was error because HPC was only required to present evidence of its account claim during its case-in-chief. According to Burrell, because Belot was used in responding to HPC's counterclaim, Burrell was not obliged to present his testimony during its case-in-chief.

A party has an unconditional right to present rebuttal testimony on matters which are first addressed in an opponent's case-in-chief and should not be brought in the rebutting party's case-in-chief. Phung v. Waste Mgt., Inc. (1994), 71 Ohio St.3d 408,410. Matters which the plaintiff bears the burden of proving are properly presented in plaintiff's case-in-chief. Id. It is error for a court to deny a plaintiff the right to explain or rebut testimony concerning a material issue which is introduced for the first time during the defendant's case-in-chief. State v. Grinnell (1996), 112 Ohio App.3d 124,147.

Burrell's complaint was an action on an account. An action on an account is appropriate where the parties have conducted a series of transactions for which a balance remains to be paid.Blanchester Lumber Supply, Inc. v. Coleman (1990), 69 Ohio App.3d 263,265. Where the defendant enters a general denial to the allegations of the complaint, the plaintiff must prove all the elements of a cause of action for breach of contract. Id. The elements of a breach of contract claim include the existence of a contract, performance by the plaintiff, breach by the defendant, and damage or loss to the plaintiff. Doner v. Snapp (1994), 98 Ohio App.3d 597, 600.

As part of its case in chief, Burrell was only required to prove that it had delivered the concrete in question. The issue of whether the concrete in question was so defective as to constitute non-performance was an issue for HPC to prove during its case in chief, asserted as it was as an affirmative defense in its answer and counterclaim. Because the condition of the concrete was first raised by HPC and was not required to be raised during Burrell's case in chief on the account, it was error to strike Belot's testimony as improper rebuttal.

However, this is not a case where the witness at issue was precluded from testifying.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fada v. Information Systems & Networks Corp.
649 N.E.2d 904 (Ohio Court of Appeals, 1994)
Blanchester Lumber Supply, Inc. v. Coleman
590 N.E.2d 770 (Ohio Court of Appeals, 1990)
State v. Grinnell
678 N.E.2d 231 (Ohio Court of Appeals, 1996)
Doner v. Snapp
649 N.E.2d 42 (Ohio Court of Appeals, 1994)
Malone v. Courtyard by Marriott Limited Partnership
641 N.E.2d 1159 (Ohio Court of Appeals, 1994)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Bishop v. Grdina
485 N.E.2d 704 (Ohio Supreme Court, 1985)
Phung v. Waste Management, Inc.
644 N.E.2d 286 (Ohio Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Burrell Industries v. Harrison Processing, Unpublished Decision (6-24-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/burrell-industries-v-harrison-processing-unpublished-decision-6-24-1999-ohioctapp-1999.