Burns v. Exxon Corp.

892 F. Supp. 914, 1995 U.S. Dist. LEXIS 10292, 1995 WL 431204
CourtDistrict Court, S.D. Texas
DecidedApril 11, 1995
DocketCiv. A. No. C-85-47
StatusPublished

This text of 892 F. Supp. 914 (Burns v. Exxon Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burns v. Exxon Corp., 892 F. Supp. 914, 1995 U.S. Dist. LEXIS 10292, 1995 WL 431204 (S.D. Tex. 1995).

Opinion

MEMORANDUM AND ORDER

KAZEN, District Judge.

Pending before the Court is Exxon’s opposed Motion for Summary Judgment Regarding the Applicability of the Processing Agreement. In 1992, Plaintiffs sought leave to file a cross-motion for partial summary judgment on the same issue. The request was represented to be unopposed, and since then the parties have apparently assumed that the cross-motion is pending. There being no record that leave was ever granted, the Court now ORDERS that leave to file Plaintiffs’ Cross-Motion for Partial Summary Judgment is GRANTED.

The central issue is whether the King Ranch Processing Agreement (“Agreement”) controls royalty payments on liquid products obtained from gas initially processed at the Kelsey Gas Plant but fractionated at the King Ranch Plant.

Plaintiffs are royalty interest owners under two oil and gas leases executed with Exxon (originally Humble Oil & Refining Co.). On June 20, 1960, Plaintiffs and Exxon, by written agreement, amended the royalty provisions of these leases to require payment of specified royalties on plant products extracted from gas processed at a plant then under construction, the King Ranch Gas Plant. For approximately five years, Exxon processed the gas, fractionated the liquid raw make into individual liquid plant products, and sold the residue gas and liquid plant products at the King Ranch Plant. During these five years, the residue gas from Plaintiffs’ leaseholds was marketed in the favorable intrastate market.

On January 29, 1965, Exxon entered into an interstate gas sales contract with Trunk-line Gas Company (“Trunkline”) obligating Exxon to deliver to Trunkline, for a period of twenty years, gas produced from Plaintiffs’ property. In order to avoid commingling gas sold in the interstate and intrastate markets, and thereby subjecting all gas processed at the King Ranch Plant to federal pricing controls, Exxon constructed the Kelsey Gas Plant at a location physically separate from the King Ranch Plant. Plaintiffs facilitated this operational change by granting Exxon a surface lease to construct the Kelsey Plant and granting Trunkline a right-of-way to lay its pipe and buy the gas. See Joint Pretrial Order, Admission p. 57. At the Kelsey Plant, gas from Plaintiffs’ property underwent absorption and refrigeration, the residue methane gas was sold to Trunkline, and the extracted liquid raw make was stored and then transported by pipeline to the King Ranch Plant. There it was fractionated into individual plant products. The plant products were, at all times, fractionated and sold only at the King Ranch Plant.

The Agreement states it is applicable “to any gas produced [from the Plaintiffs’ leases] which may be processed in the [King Ranch] plant.” Agreement, p. 1. Plaintiffs’ central contention is that during the relevant period, gas from Plaintiffs’ leaseholds was being processed only at the Kelsey Plant. At the King Ranch Plant, according to Plaintiffs, what was happening was the fractionation of liquids, not the processing of gas. Therefore, they maintain that the Agreement was inapplicable and that they should have been compensated under the original leases. Exxon replies that fractionation is only a part of the processing procedure and that, under Texas law, “gas” includes all its constituent elements, including liquid hydrocarbons recovered therefrom.

The crux of the dispute is easier to describe than to resolve. Nevertheless, both parties insist that the Agreement is unambiguous and that the controversy should be resolved as a matter of law. See Technical Consultant Services v. Lakewood Pipe, 861 F.2d 1357 (5th Cir.1988) (interpretation of unambiguous contract is question of law). A contract is not ambiguous merely because the parties disagree on the correct interpretation of it. REO Industries v. Natural Gas Pipeline Co., 932 F.2d 447, 453 (5th Cir.1991), citing, Sun Oil Co. (Del.) v. Madeley, [916]*916626 S.W.2d 726, 727 (Tex.1981). The entire contract must be examined to give effect to all provisions so that none will be rendered meaningless. Coker v. Coker, 650 S.W.2d 891, 393 (Tex.1983). No single provision of the contract can be given controlling effect; rather, all the provisions must be considered with reference to the whole. Id.

Article II of the Agreement provides that Exxon “in its discretion may limit or curtail, cease entirely, or recommence its gas processing operations (or any portion of such operations).” Article IV provides that the Agreement shall remain in effect for twenty years. As a whole, therefore, this was an agreement whereby for twenty years the Plaintiffs specifically allowed Exxon the flexibility to conduct some or all of its gas processing operations at the King Ranch Plant. Initially, the parties clearly understood the term “processing” to include not only production of the residue gas but also fractionation of the liquid make into plant products, since that is what was happening at that plant. The Agreement then provided that Exxon could limit, curtail, or cease entirely “any portion of’ its gas processing operations. This language clearly suggests that the fractionation of the liquid make was considered part of the processing procedure and not something totally different. The processing of gas is a multiple-phase endeavor:

The gas, which is carried full stream to the plant, is first sent through the inlet separator which removes the condensate from this full stream gas. After the condensate is removed by the inlet separator, the separator gas is sent to absorption towers where additional liquids are absorbed from such gas. The residue gas remaining after the absorption tower process is then sent through a dehydrator and is delivered to the pipe line company or is returned to the cycling unit by the producers. All liquids recovered, both from the inlet separator and from the absorption tower process, are then further processed to obtain propanes, butanes, motor fuel and other products.

Freeland v. Sun Oil Co., 184 F.Supp. 754, 756 (D.C.La.1959), aff'd, 277 F.2d 154 (5th Cir.1960), cert. denied, 364 U.S. 826, 81 S.Ct. 64, 5 L.Ed.2d 55 (1960), quoted in Williams and Meyers, 8 OIL AND GAS LAW 955 (Matthew Bender 1992) (definition of “processing plant”). The Court concludes that the fractionation of liquid make was part of the “gas processing operations” within the meaning of the Agreement.

The Court further concludes that the term “gas” includes all constituent elements contained therein, including liquid hydrocarbons recovered from the gas stream. Sowell v. Natural Gas Pipeline Co., 789 F.2d 1151, 1157 (5th Cir.1986); Lone Star Gas Co. v. Stine, 41 S.W.2d 48, 49 (Tex.Comm’n App. 1931, judgment adopted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County Management, Inc. v. Butler
650 S.W.2d 888 (Court of Appeals of Texas, 1983)
Sun Oil Co. (Delaware) v. Madeley
626 S.W.2d 726 (Texas Supreme Court, 1981)
Lone Star Gas Co. v. Stine
41 S.W.2d 48 (Texas Commission of Appeals, 1931)
Freeland v. Sun Oil Co.
184 F. Supp. 754 (W.D. Louisiana, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
892 F. Supp. 914, 1995 U.S. Dist. LEXIS 10292, 1995 WL 431204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burns-v-exxon-corp-txsd-1995.