Burns Concrete v. Teton County

CourtIdaho Supreme Court
DecidedNovember 2, 2020
Docket46827
StatusPublished

This text of Burns Concrete v. Teton County (Burns Concrete v. Teton County) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burns Concrete v. Teton County, (Idaho 2020).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket Nos. 46827/47496

BURNS CONCRETE, INC., an Idaho ) Corporation, and BURNS HOLDINGS, LLC, ) an Idaho limited liability company, ) ) Plaintiffs-Counterdefendants- ) Respondents-Cross Appellants, ) Boise, June 2020 Term ) v. ) Opinion Filed: November 2, 2020 ) TETON COUNTY, a political subdivision of ) Melanie Gagnepain, Clerk the State of Idaho, ) ) Defendant-Counterclaimant- ) Appellant-Cross Respondent. ) _______________________________________ )

Appeal from the District Court of the Seventh Judicial District of the State of Idaho, Teton County. Dane H. Watkins, Jr., District Judge.

The district court’s grant of partial summary judgment on the issue of breach of contract is affirmed. The judgment of the district court is vacated. The district court’s orders on attorney fees are vacated. The case is remanded for a recalculation of damages and an explanation of the attorney fee award.

Billie J. Siddoway, Teton County Prosecuting Attorney, Driggs, for appellant-cross respondent. Billie Siddoway argued.

Parsons Behle & Latimer, Boise, for respondents-cross appellants. Robert Burns argued. ___________________

BRODY, Justice. This appeal arises from a dispute over the construction of a ready-mix concrete manufacturing facility in Teton County. In 2007, Burns Holdings entered into a development agreement with Teton County regarding property owned by Burns Concrete. The development agreement required the construction of a permanent concrete manufacturing facility on the property within 18 months of the execution of the agreement, but allowed operation of a temporary facility in the meantime. Burns Concrete, the concrete company that would operate the facility, and Burns

1 Holdings, a holding company that was to eventually take title to the property, wanted to build a permanent facility that was 75-feet tall, but the applicable zoning ordinance limited building heights to 45-feet. The County denied Burns Holdings’ application for a conditional use permit and its subsequent application for a variance to exceed the height limit. The Burns Companies operated the temporary facility for several years but never constructed the permanent facility. In 2012, the County sent written notice revoking the authority to operate the temporary facility and demanding that the temporary facility be removed. The Burns Companies subsequently filed this action, stating claims for breach of contract, declaratory judgment, and unjust enrichment. The County counterclaimed, alleging breach of contract and seeking declaratory judgment for the removal of the temporary facility. This began a multi-year period of litigation that included two appeals to this Court, each followed by a remand to the district court. This case has returned to us again, this time as a result of the parties’ cross-appeals from the district court’s grant of partial summary judgment in favor of the Burns Companies on their breach of contract claim, its award of $1,049.250.90 in damages, and its award of attorney fees. We affirm the district court’s grant of partial summary judgment on the issue of breach of contract, but vacate the district court’s judgment for a recalculation of damages. In its recalculation of damages, the district court is instructed to reverse its reduction of damages by the difference between the Temporary Facility’s sales and cost of sales. We vacate the district court’s award of attorney fees and remand the matter for an explanation of the district court’s reduction of requested attorney fees. I. FACTUAL AND PROCEDURAL BACKROUND A. Factual Background Burns Holdings, LLC and Burns Concrete, Inc. are Idaho business entities. Kirk Burns is the president of Burns Concrete and the manager of Burns Holdings. Burns Holdings and Burns Concrete are referred to together as “the Burns Companies.” In 2006, Burns Concrete purchased a 6.5-acre property (“the Property”) in Teton County. Burns Holdings applied to change the zoning of the Property from C-3 (commercial) to M-1 (light industrial) in order to build and operate a ready-mix concrete manufacturing facility on the Property. On February 26, 2007, the County approved the zone change with certain conditions, including that Burns Holdings enter into a development agreement with the County pursuant to Idaho Code section 67-6511A. The Property was located within the City of Driggs’ impact area, where the County and

2 Driggs had agreed, pursuant to Idaho Code § 67-6526, that the Driggs zoning laws would apply. Driggs’ zoning ordinance provided that “any building or structure or portion thereof” could not exceed 45 feet in height unless approved by conditional use permit (CUP). On June 13, 2007, Burns Holdings applied for a CUP to build a permanent facility (the “Permanent Facility”) 75 feet in height. The application was first reviewed by Driggs’ planning and zoning department, which unanimously recommended approval by the County. The application was sent to the County. On August 31, 2007, Burns Holdings and the County entered into a development agreement (the “Development Agreement”). Paragraph 2.b of the Development Agreement required construction of the Permanent Facility to commence immediately upon execution. Importantly, Paragraph 2.b also required the construction of the Permanent Facility in accordance with elevation schematics showing a building 75 feet in height. It further required construction to be completed within 18 months, subject to acts of force majeure beyond Burns Holdings’ control. Paragraph 2.b also required the construction of a temporary facility (the “Temporary Facility”). The County had the authority to revoke the authority to operate the Temporary Facility if the Permanent Facility was not completed within the allowable time period. Paragraph 9 provided that the Development Agreement could be terminated, and the Property’s zoning reverted, if Burns Holdings or its successor failed to comply with the terms of the Development Agreement. Paragraph 10 required Burns Holdings to comply with all applicable laws. Paragraph 12 provided that the Development Agreement would run with the land. On November 15, 2007, the County denied Burns Holdings’ CUP application. Burns Holdings sought judicial review of the denial. The district court upheld the County’s CUP denial and Burns Holdings appealed. This Court affirmed on the alternative ground that the Local Land Use Planning Act (“LLUPA”) required a variance, not a CUP, to modify the height requirements in a zoning ordinance. Burns Holdings, LLC v. Teton Cnty. Bd. of Comm’rs, 152 Idaho 440, 272 P.3d 412 (2012) (“Burns 2012”). Subsequently, Burns Holdings applied for a zoning variance to build the Permanent Facility to a height of 75 feet. The County denied this request as well. By letter dated April 9, 2012, the County revoked the authority to operate the Temporary Facility and demanded that the Temporary Facility be removed by July 1, 2012. On October 4, 2012, the County sent another letter to Kirk Burns reminding him of the April 9 demand to remove the Temporary Facility and requesting removal activity to begin immediately. In response, counsel for

3 the Burns Companies sent a letter to the County asserting that the County’s October 4 letter constituted a breach of the Development Agreement because the Burns Companies’ time limit for constructing the Permanent Facility was tolled by the Development Agreement’s force majeure clause and the County had failed to provide the requisite notice of default and opportunity to cure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burns Holdings, LLC v. Teton County Board of Commissioners
272 P.3d 412 (Idaho Supreme Court, 2012)
French v. Nabob Silver-Lead Company
350 P.2d 206 (Idaho Supreme Court, 1960)
Beco Construction Co. v. Harper Contracting, Inc.
936 P.2d 202 (Idaho Court of Appeals, 1997)
Springwell Dispensers, Inc. v. Hall China Company
419 S.E.2d 112 (Court of Appeals of Georgia, 1992)
King v. Beatrice Foods Company
402 P.2d 966 (Idaho Supreme Court, 1965)
First State Bank of Eldorado v. Rowe
130 P.3d 1146 (Idaho Supreme Court, 2006)
Parsons v. Mutual of Enumclaw Insurance
152 P.3d 614 (Idaho Supreme Court, 2007)
Burns Concrete, Inc. v. Teton County
384 P.3d 364 (Idaho Supreme Court, 2016)
Michael L. Kelly v. Pamela Wagner
393 P.3d 566 (Idaho Supreme Court, 2017)
Bret and Marti Kunz v. Nield, Inc.
398 P.3d 165 (Idaho Supreme Court, 2017)
Med. Recovery Servs., LLC v. Neumeier
415 P.3d 372 (Idaho Supreme Court, 2018)
Lunneborg v. My Fun Life, Corp.
421 P.3d 187 (Idaho Supreme Court, 2018)
H2O Envtl., Inc. v. Farm Supply Distribs., Inc.
429 P.3d 183 (Idaho Supreme Court, 2018)
Ciraolo v. Miller
138 A.D.2d 443 (Appellate Division of the Supreme Court of New York, 1988)
Silverwing At Sandpoint, LLC v. Bonner Cnty.
435 P.3d 1106 (Idaho Supreme Court, 2019)
Sec. Investor Fund LLC v. Crumb
443 P.3d 1036 (Idaho Supreme Court, 2019)
Merry Gentleman, LLC v. George & Leona Productions, Inc.
76 F. Supp. 3d 756 (N.D. Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Burns Concrete v. Teton County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burns-concrete-v-teton-county-idaho-2020.