Burnham v. Royal Insurance

75 Mo. App. 394, 1898 Mo. App. LEXIS 443
Missouri Court of Appeals·Decided May 10, 1898·Published·Cited by 8 cases

Opinion

Biggs, J. —

Statement. In 1893 the plaintiff constructed a dwelling house on certain lots owned by him in the city of Popular Bluff. The firm of Linton & Tetwiler had the contract for building the house. On November 3, 1893, the plaintiff negotiated a loan of $2,000 from the Missouri Guarantee Savings and Buildings Association of Hannibal (hereinafter designated as the building association), and to secure this loan the plaintiff executed a mortgage on the house and lots. The loan was to • be paid in instalments so as to enable the plaintiff to meet the demands of Linton & Tetwiler for the construction of the building. On November 15 and while the building was unfinished, the defendant issued to plaintiff a . policy of insurance, by wm.cn it undertook to insure the house against destruction by fire in the sum of $1,500 for a period of five years, loss, if any, payable to the building association (mortgagee) as its interest might appear. At the time the policy was issued the building association and the defendant entered into a separate agreement, which contained among other provisions, the following: “This insurance, as to the interest of the mortgagee or trustee [398] only therein, shall not be invalidated by any act or neglect of the mortgagor or owner of the property insured.” Among the printed conditions of the policy the following appear: “This entire policy unless otherwise provided by agreement indorsed hereon or added hereto,- shall be void * * * if mechanics be employed in building, altering or repairing the within described premises for more than fifteen days at any one time, * * * or if a building herein described, whether intended for occupancy by owner or tenant, be or become vacant or unoccupied and so remain for ten days.” A slip of paper was attached to the face of the policy, on which was written the following:

Conditions of s!urancecy of in" “Thirty days, granted to complete construction and occupy as dwelling the insured building.” The policy also contains the following: “If fire occur the insured shall give immediate notice of any loss ... thereby m writing to this company, * * * and within sixty days after the fire, unless such time is extended in writing by this company, shall render a statement to this company, signed and sworn to by said insured, stating the knowledge and belief of the insured, as to the time and origin of the fire; the interest of the assured and all others in the property; * * * by whom and for what purpose the building was occupied at the time of the fire.”

The house was burned on the eighteenth day of December, 1893. The defendant having refused to pay the loss, the plaintiff paid its debt to the building association, and thereupon instituted the present action on the policy. The defendant admitted the issuance of the policy, and the destruction of the building, but defended the action on the grounds that the plaintiff had failed to give immediate notice of the loss; had failed to furnish proofs of loss, and [399] also that the house had not been completed and occupied as a dwelling within thirty days of the date of the policy, and that the house was complete and unoccupied at the time of the fire. In the reply the plaintiff averred that due and timely notice of the fire was given. He admitted that proofs of loss were not furnished, but pleaded a waiver of them. He also admitted that the house was not completed and occupied within thirty days of the date of the policy, but he averred that under the terms of the policy he had forty-five instead of thirty days within which to complete and occupy the house. At the close of the evidence the circuit court instructed the jury to return a verdict for the defendant, whereupon the plaintiff submitted to an involuntary nonsuit. The court having refused to set aside the nonsuit the plaintiff has brought the case here by appeal.

immediate notÍCe* It is conceded that the first and only notice of the fire received by the defendant was sent by its own agents at Hannibal, Missouri, and was received at defendant’s office in Chicago, Illinois, on the fifth day of January, 1894. Waiving the question of the right of the plaintiff to avail himself of this notice, we must, in the absence of any testimony excusing delay, hold that the notice was not in J ' mi , , . time. The policy required %mmemate notice. The fire occurred on December 18, 1893, and the notice was sent January 4, 1894. Compliance with this condition of the policy was important and was a condition .precedent to the right of plaintiff to sue, and unless the defendant waived a compliance with it, its violation afforded sufficient ground for the action of the circuit court in directing a verdict for the defendant. LaForce v. Ins. Co., 43 Mo. App. 518. It is conceded that the plaintiff failed to furnish proofs of loss, therefore the nonsuit was properly granted for [400] that reason, unless this requirement was also waived. (Leigh v. Ins. Co., 37 Mo. App. 542.) It is also undisputed that the house was not completed and occupied at the time it was burned, which was more than thirty days after the date of the policy. We hold that a violation of such a condition, where there is no waiver, invalidates the contract of insurance. Bank v. Royal Ins. Co., 23 N. E. Rep. (Mass.) 210.

As to the question of failure to occupy, the plaintiff makes two contentions, first, that by the terms of the policy he had forty-five days to complete and occupy the house, instead of thirty, as contended by the defendant; or, second, if the defendant is right in its construction, then by its acts and conduct it likewise waived a breach of this condition or requirement. As to the first contention the plaintiff is wrong. The written indorsement allowing thirty days for the construction of the house superseded the printed conditions of the policy until the- house was completed and occupied. (1 May on Insurance [3 Ed.], sec. 177.) The printed requirements as to vacancies and the making of repairs are applicable to ordinary policies — that is, to houses that are completed and occupied. As to such risks a vacancy of more than ten days avoids the policy, and the making of repairs which extend beyond fifteen days likewise avoids it. Here the house was unfinished and by special agreement the plaintiff was given thirty days to complete and occupy it. The other conditions or limitations referred to were only intended to apply after the house had been completed and occupied according to the special contract. It would, in our opinion,, be a forced and unreasonable construction of the policy to allow the limit of thirty 'days to be extended by tacking onto it either of the other limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Burnham v. Royal Insurance, 75 Mo. App. 394, 1898 Mo. App. LEXIS 443 (Mo. Ct. App. 1898).

75 Mo. App. 394 (Burnham v. Royal Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Schultz v. Queen Insurance Company
399 S.W.2d 230 (Missouri Court of Appeals, 1965)
Young v. Fidelity & Casualty Co.
215 S.W. 496 (Missouri Court of Appeals, 1919)
Hilburn v. Phoenix Insurance
108 S.W. 576 (Missouri Court of Appeals, 1908)
Davis v. Northwestern Mutual Fire Ass'n
92 P. 881 (Washington Supreme Court, 1907)
Myers v. Maryland Casualty Co.
101 S.W. 124 (Missouri Court of Appeals, 1907)
Adams v. Farmers' Mutual Fire Insurance
90 S.W. 747 (Missouri Court of Appeals, 1905)
Clanton v. Travelers' Protective Ass'n
74 S.W. 510 (Missouri Court of Appeals, 1903)