Burley v. Benson-Seeney

Superior Court of Delaware·Decided December 3, 2021·No. N19C-07-001 DJB·Published

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

)

TIMOTHY BURLEY, )

)

Plaintiff, )

)

v. ) C.A. No. N19C-07-001 DJB )

GERALD BENSON-SEENEY & KIANA )

WATSON, )

Defendants. )

Decided: December 3, 2021

DECISION AFTER TRIAL

TIMOTHY BURLEY, Plaintiff, pro se.

GERALD BENSON-SEENEY, Defendant, pro se KIANA WATSON, Defendant, pro se

BRENNAN, J.

I. FACTUAL AND PROCEDURAL BACKGROUND This is a breach-of-contract action through which Plaintiff Timothy Burley (hereinafter “Burley”) seeks damages from Defendants Gerald Seeney-Benson (hereinafter “Seeney-Benson”) and Kiana Watson (hereinafter “Watson”) (collectively, “Defendants”), for the latter’s failure to pay the amount owed pursuant to the contract for sale of a house located at 2236 North Pine Street, Wilmington, Delaware 19802 (hereinafter “the Pine Street home”).1 On March 3, 2017, the parties engaged in a contract for the sale of the Pine Street home in the amount of Forty Thousand Dollars ($40,000.00), with the agreement that a Five Thousand Dollar ($5,000.00) down payment would be made initially and then payments of Six Hundred and Fifty Dollars ($650.00) would be made in each consecutive month until the total sale amount was paid in full.2 Per the contract, a breach would occur if Defendants were to fall behind sixty (60) days in payments, and if that occurred, Burley would be able to seek repossession of the

1 Compl. ¶¶ 1-6, July 1, 2019 (D.I. 1). While the pro se Complaint does not specify the cause of action, the Court, after hearing the testimony and reading the filings in this case, has determined this to be a breach of contract action. Browns v. Saunders, 2001 WL 138497, at *1 (Del. Feb. 14, 2001) (“As a general rule, we interpret pleading requirements liberally where the plaintiff appears pro se.”. 2 Id. ¶ 1; see also Trial Testimony pp. 25-27; Plaintiff Exhibit 1.

property.3 At the time the agreement was signed, the contract, which was incorporated into the deed for the Pine Street Home, was recorded with the Recorder of Deeds in and for New Castle County. At that point, title to the Pine Street home transferred to the Defendants.4 The initial payment pursuant to the contract was made only by Defendant Watson in the amount of the $5,000.00 on March 2, 2017,5 and Defendant Watson, solely, continued to make the successive monthly payments pursuant to the contract of $650.00 until June 2018.6 Thereafter, Defendant Watson made partial payments in July, August and September, 2018.7 Thereafter, no payments have been made by either Defendant.8 It is undisputed that all payments were made by Defendant Watson and at no point did Defendant Seeney-Benson contribute financially to any of the payments under the contract.9 As of the date of trial, Defendants were $19,833.00 in arrears.10

3 Plaintiff Exhibit 1/Exhibit A to Complaint. (D.I. 4), see also Trial Testimony p. 26. 4 Trial Transcript, p. 34 5 Trial Transcript p. 31 6 Trial Transcript p. 53 7 See Plaintiff Exhibit 1, p. 3. 8 Compl. ¶¶ 80-82, July 12, 2019 (D.I. 1), Trial Transcript, p. 53. 9 Trial Transcript p. 51-53, 66-68 10 Trial Transcript p. 50

Plaintiff filed the instant lawsuit, seeking to repossess the Pine Street home following failed attempts to resolve the issue outside of court involvement.11 A bench trial was held on August 30, 2021, where each party represented themselves. The Court reserved decision and allowed parties to submit post-trial exhibits, at their request. This is the Court’s decision.

II. THE TRIAL

The Court conducted a one-day bench trial.12 During trial, the Court heard from and considered the testimony of the following witnesses: Timothy Burley, Gerald Seeney-Benson and Kiana Watson. The parties also each submitted respective exhibits, most of which were admitted without objection and are cited herein by their given trial designations. The case was deemed fully submitted for decision after the parties submitted their post-trial documents to supplement the

11 Id. An initial lawsuit was filed by Plaintiff in the Justice of the Peace Court #13 as a landlord/tenant eviction action, however, following a three-judge panel review, it was determined that this was not a landlord/tenant action and the Justice of the Peace Court did not have proper jurisdiction to hear the case. At that hearing, Defendant Watson appeared, as well as Plaintiff, however Defendant Seeney- Benson failed to either Answer the Complaint or appear at the hearing. The case was then appealed to the Court of Common Pleas, at which time it was likewise dismissed, for a want of jurisdiction. 12 Before the trial began, the Court inquired into each party’s pro se status and whether each party fully understood what it meant to proceed at trial pro se. Following that discussion, each party represented to the Court that it was their intention to proceed to trial pro se. Trial Transcript at 17-20.

record on the issue of whether the water bill and/or tax bill had been paid at the time of making the contract for the Pine Street home.14 III. FINDINGS OF FACT

It is difficult at times in the trial of certain actions to fully and cleanly segregate findings of fact from conclusions of law. To the extent any one of the Court’s findings of fact here might be more appropriately viewed as a conclusion of law, that finding of fact may be considered the Court’s conclusion of law on that point.15 A. THE EXISTENCE OF A CONTRACT.

It is undisputed by all parties that a valid contract for the sale of the Pine Street Home existed.16 Neither during the responsive pleadings or at any time during the trial, did any party contest the validity of the contract at issue. In fact, each Defendant, in their respective testimony, specifically stated that they agreed that there was a valid contract and that Plaintiff was correct in his recitation of the terms of the agreement.17 Additionally, both Defendants acknowledged that the remedy for breach of this contract was that Plaintiff would seek immediate possession of the

14 D.I. 76.

15 See Facchina Constr. Litigs., 2020 WL 6363678, at *2 n.12 (Del. Super. Ct. Oct.

29, 2020) (collecting authority). 16 Id. at 121-22, 197.

17 Trial Transcript p. 77-78; 114

property.18 Therefore, the Court finds that a valid contract existed, and the terms were as follows: Defendants were to pay a total of $40,000 for the Pine Street Home by paying an initial $5,000 down payment to Plaintiff. Thereafter, Defendants were to pay monthly, in the amount of $650.00. Defendant Watson paid the down payment at the time the contract was recorded.. Thereafter, Defendant Watson satisfied the terms by paying the agreed upon monthly payments until September, 2018.

B. BREACH OF CONTRACT.

It is uncontested that the contract has been breached insofar as Defendants both admit that there has been no payment since September, 2018. Defendant Seeney- Benson testified that he was aware the deed was in his name and consulted with an attorney about that fact and decided to stop making payments because the house was already deeded to him.19 Defendant Watson testified that she was the sole person making payments according to the contract until September 2018, despite her having moved out of the house in June 2018.20 When Defendant Watson could no longer afford to make the payments for the house, she stopped making payments as she was no longer living there and she and Defendant Seeney-Benson had orally agreed that

18 Trial Transcript, p. 117. 19 Trial Transcript, p. 89. 20 Trial Transcript, p. 67.

he would take over payments.21 He failed to do so. There is no evidence in the record that Defendant Seeney-Benson ever made a payment towards the house, nor that he denied being in breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Burley v. Benson-Seeney, (Del. Ct. App. 2021).

Burley v. Benson-Seeney (Burley v. Benson-Seeney) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burge v. Fidelity Bond and Mortg. Co.
648 A.2d 414 (Supreme Court of Delaware, 1994)
Reynolds v. Reynolds
237 A.2d 708 (Supreme Court of Delaware, 1967)
VLIW TECHNOLOGY, LLC v. Hewlett-Packard Co.
840 A.2d 606 (Supreme Court of Delaware, 2003)
Oberly v. Howard Hughes Medical Institute
472 A.2d 366 (Court of Chancery of Delaware, 1984)
Danville Silk Co. v. Unemployment Compensation Board of Review
155 A.2d 223 (Superior Court of Pennsylvania, 1959)