Burlew v. Fidelity & Casualty Co.

64 F.2d 976, 1933 U.S. App. LEXIS 4278
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 12, 1933
Docket6221
StatusPublished
Cited by9 cases

This text of 64 F.2d 976 (Burlew v. Fidelity & Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burlew v. Fidelity & Casualty Co., 64 F.2d 976, 1933 U.S. App. LEXIS 4278 (6th Cir. 1933).

Opinion

SIMONS, Circuit Judge.

The proceeding below was a suit by the owner against the surety on a building contractor’s bond for the construction of a residence and garage. He appeals from a decree dismissing the petition.

On November 12,1927, the owner entered into a written contract with one L. A. Monarch, contractor, for the construction of a residence and garage in Owensboro, Ky., for the sum of $34,000. On the same day the contractor furnished a bond, with the surety as indemnitor, in the sum of $34,000, conditioned upon the faithful performance of the building contract incorporated in and made part of the bond. After the completion of the buildings, and their occupancy by the owner, minor defects began to appear therein, which were called) to the attention of the contractor, who undertook to remedy them. No notice was given to the surety. In the spring of 1929 more serious weaknesses developed. The owner then had the buildings examined by experts, and it was discovered that the contractor had entirely omitted installation of certain materials, substituted cheaper and inferior material for that called for, performed in an unworkmanlike manner, and otherwise failed to comply with the contract. The owner thereupon notified the surety in writing on April 5,1929, of the conditions disclosed, and called upon it to indemnify. After a number of conferences and inspections of the premises, the surety made an offer of settlement, which was declined. The controversy was then submitted by the owner to the architect as arbitrator. The latter made a finding that the contract had not been performed according to its terms, and that the owner was entitled to recover $23,-347.00 as damages. The surety refused to recognize the award, and suit followed.

The first question to be decided, and, if the court below is correct, the only question, *977 is whether the owner’s suit was timely within the terms of clause 4 of the bond, which provides: “Legal proceedings for recovery hereunder may not be brought unless begun within twelve months from the time of the discovery of the aets or omission of the principal on account of which claim is made.”

Disregarding minor defects, of which no notice was given to the surety, April 5, 1929, is conceded] y the latest date which can be claimed by the owner as the time oE discovery of the contractor’s breach. Suit was brought August 7, 1930, approximately sixteen months thereafter. • The owner contends that the limitation period was waived, or at least that the surety is estopped by its conduct from relying upon the limita,tion clause in the bond. The surety, he says, lulled him into a sense of security that the limitation of time for bringing suit would not be relied upon by entering into negotiation for settlement, and causing its representatives to state that the matter would be settled.

The validity of provisions such as the one here involved, and the principles governing their waiver, were carefully considered by this court in Reynolds v. Detroit Fidelity & Surety Co., 19 F.(2d) 110. The conclusions there reached were that reasonable provisions limiting the time for suit are valid, and, unless waived, are binding upon the parties; that the burden of proof is upon the party claiming a waiver; that, in the absence of conduct creating an estoppel, the waiver must be supported by an agreement founded upon, a valuable consideration; that there can he no waiver unless so intended by one party and so understood by the other. But, when a party has so acted as to mislead the other, he is estopped thereby, provided such conduct is the cause of delay in commencing suit.

Both parties pay the tribute of citation to Judge Knappen’s opinion in the Reynolds Case as containing a correct statement of the law with regard to estoppel. They differ upon the application of the law to the facts. In support of his claim of waiver, the owner relies upon the following circumstances: In reply to his notice of April 5, 1929, advising it of the breach, the surety, by letter of April 25> 1929, advised the owner that it had referred the complaint to its representative, Mr. J. A. Hogan, of Louisville, for attention, and that Mr. Hogan had been instructed to arrange a meeting with the owner and contractor for the purpose of making inspection and investigation. Thereafter the owner called upon Mr. Hogan and conferred with Mm and Mr. Quick, another representative of the surety. At this conference Mr. Hogan advised him that “they (the surety) wanted to settle the thing — if there was any damage they would satisfy it.” This was in May of 1929. In June Mr. Littell, a local contractor, made an inspection for the surety. In September Mr. Nelson, the surety’s resident manager, wrote J. C. Rudd Son & Co., its local agents at Owensboro, that he and Mr. Hogan would come to Owensboro and make a complete investigation of the matter and see what was necessary to he done; that it seemed to him that the contractor, architect, owner, and surety should get together, see what the trouble was, and endeavor to straighten it out. This letter was shown to the owner by Rudd. Pursuant to the letter Mr. Nelson came to Owensboro in October and made inspection. Upon returning to Louisville, he wrote the owner that ho had sent a memorandum to the surety’s claim department, and that he expected reply the following week, when the matter would receive attention. On November 8, 1929, Mr. Quick came to Owensboro and arranged for a meeting at the hotel with the owner, contractor, architect, and a Mr. Hoffman, who had inspected the buildings. On November 23, 1929, the owner received a letter from the surety’s attorney in Owens-boro proposing that another contractor make an inspection of the buildings for the surety, and that, after receiving report, “the probabilities are that they would be in a position to get rid of this matter.” Upon the owner's objection to the surety’s choice, another architect was sent to make examination. Following his report, the surety in March, 1930, offered to settle for $1,000, which offer was rejected. Shortly thereafter the period of limitation expired, but negotiations for settlement continued. The matter was referred by the owner to the architect as arbitrator some time in June, 1930. Report was máde on July 29th, repudiated by the surety on August 1st, and suit begun August 7th. Upon the basis of these circumstances the owner claims that the surety (l)-held out reasonable hopes of adjustment, (2) left the question of settlement an open one, (3) and induced the owner to delay in bringing suit to enable it to investigate the claim, and that by such conduct an estoppel was created within the rule of the Reynolds Case.

The appellant contends that the circumstances thus enumerated establish estoppel. Philadelphia Company v. Thacher, 236 F. 869 (C. C. A. 1); United States v. Fidelity & Deposit Co. (C. C. A. 2) 224 F. 866; Green Star S. S. Co. v. Nanyang, 3 F.(2d) 369 (C. C. A. 9); Lynchburg, etc., Co. v. Travelers’ *978 Insurance Co., 149 F. 954, 9 L. R. A. (N. S.) 654 (C. C. A. 4); De Farconnet v. Western Insurance Co. (D. C.) 110 F. 405. But compare Southern Pacific Co. v. Stewart, 248 U. S. 446, 39 S. Ct. 139, 63 L. Ed. 350. These circumstances are to he considered, too, in connection with other pertinent facts now to be stated. In September, 1929, the owner withdrew all of his insurance business from the surety.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
64 F.2d 976, 1933 U.S. App. LEXIS 4278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burlew-v-fidelity-casualty-co-ca6-1933.