Burkey v. Ellis

483 F. Supp. 897, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 5 Fed. R. Serv. 518, 1979 U.S. Dist. LEXIS 9969
CourtDistrict Court, N.D. Alabama
DecidedSeptember 6, 1979
DocketCiv. A. 71-G-644-E
StatusPublished
Cited by4 cases

This text of 483 F. Supp. 897 (Burkey v. Ellis) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burkey v. Ellis, 483 F. Supp. 897, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 5 Fed. R. Serv. 518, 1979 U.S. Dist. LEXIS 9969 (N.D. Ala. 1979).

Opinion

OPINION

GUIN, District Judge.

This action was brought to enjoin the defendants, both state and federal, from constructing, installing or further authorizing or financing any stream modification or channelization of Blue-Eye Creek, a tributary of the Coosa River in Talladega County, Alabama. That project was proposed by the Soil Conservation Service of the U. S. Department of Agriculture (“SCS”) and the Blue-Eye Creek Watershed Conservancy District (“the District”). Defendants in 1968 and 1969 had installed two small dams or flood water retention structures in the upstream reaches of Blue-Eye Creek and since then have implemented a plan for conservation land treatment of lands in the watershed designed to control rainfall runoff and promote land stabilization. At the time of the earlier hearing of this case in 1973, defendants were, in addition, proceeding with plans to channelize eight miles of the creek, including that portion running through lands owned by Mr. Earle Montgomery, now deceased, for whose estate the present plaintiff is administratrix. By its Order of September 11, 1973, this Court enjoined that channelization project, 364 F.Supp. 517. In that decision, it was found that the proposal to proceed with channelization constituted an arbitrary decision in violation of provisions of the National Environmental Policy Act of 1969 (42 U.S.C.A. § 4321 et seq.) (“NEPA”), particularly in employing the artificially low interest rate of 3V4% and long 100-year project life in formulating the plan for the project and in combining, for evaluation purposes, the channel work with the then already constructed small dams. 1

Since 1973, defendants have reworked the project and filed a revised environmental impact statement (“the REIS”). The new project is designed to protect rural areas only against a 0.75-year storm (i. e. a storm of a frequency that will occur more often than once a year), which is estimated in the REIS to be protection against 40-50% of projected flooding, and will cost approximately $72,000/mile. In addition, defendants have, in the revised project, omitted channelization of an intermediate stretch of the creek passing through plaintiff’s and some other lands. Thus, this fragmentation of the channelization will place those lands not only immediately below a channelized portion but also upstream from another channelized portion, a situation plaintiff claims will subject the intervening segment to resultant downstream flooding and bank erosion from the upstream channelization and also resultant bank erosion caused by increased velocity of stream flow from the downstream channelization.

Much emphasis has been placed in the REIS on the need to decrease projected flooding in the Town of Lincoln, which is situated at the downstream end of the project. However, SCS in its own reports (such as the excerpt from its 1971 Annual Report previously submitted in this cause) has stated that, even in times of heavy rainfall, flooding is reduced and the water retention structures are all functioning properly. The affidavit of Mr. Montgomery heretofore filed states it has been noted that flooding upstream from Lincoln has *904 been substantially reduced since completion of the water retention structures in 1968 and 1969. That effect has been further confirmed by affidavit submitted this year that, in the heavy rainfall of March 30-31, 1977, and in the recent heavy (but not as heavy) rainfall at the beginning of March, 1979, the channel of Blue-Eye Creek in Lincoln was substantially containing the flood waters of the creek and there was no flooding of the principal business streets in Lincoln, notwithstanding that there were substantial increases in the water level of Lake Logan Martin on the Coosa River into which Blue-Eye Creek flows.

On the basis of the REIS, both the federal and state defendants have filed motions to dissolve the previous injunction. The Court has heard argument on those motions and received several briefs and numerous affidavits in behalf of all parties. It is the Court’s opinion that the decision of the defendants to proceed with the revised project is reviewable as being arbitrary and an abuse of administrative discretion under the Administrative Procedure Act (5 U.S. C.A. § 701 et seq.) and in violation of the substantive, procedural and disclosure requirements of NEPA, in particular because of the necessity of relying on one or more of the following factors in order to achieve a favorable benefit-cost ratio: Combination of the dams and channelization (with low historic costs allocated to the former, but computation of benefits at current prices), use of the unduly long 100-year project life, and use of the arbitrarily low ZlU% interest rate, as well as the other deficiencies set forth below. Consequently, defendants’ motions to dissolve the injunction are due to be overruled.

The Court’s ruling was announced in open court on July 30, 1979; the alternative reasons supporting it are set forth in greater detail in the following parts of this opinion:

I. Invalid Benefit-Cost Ratio

It is necessary for a stream channelization project to have a favorable benefit-cost (“B/C”) ratio in order to fall under the authorizing statute, 16 U.S.C.A. § 1005. In addition, NEPA requires a balancing of claimed economic benefits from a project against costs — see, for example, the leading case of Calvert Cliffs Coordinating Comm. v. AEC, 146 U.S.App.D.C. 33, 449 F.2d 1109 (D.C.Cir. 1971), especially the portion at 146 U.S.App.D.C. 47 at 449 F.2d 1123 quoted in this Court’s earlier opinion at 364 F.Supp. 524, and also the decision of this District Court in State ex rel. Baxley v. Corps of Engineers (Luxapalila Creek), 411 F.Supp. 1261 at 1268 (N.D.Ala.1976).

NEPA is more than an environmental full disclosure law; it also requires the substantive review of agency determinations. This Court has so held in its previous opinion, citing Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971). That holding was approved by the Fifth Circuit in Environmental Defense Fund v. Corps of Engineers, 492 F.2d 1123 (1974), and Sierra Club v. Callaway, 499 F.2d 982 (1974). To the same effect are Environmental Defense Fund v. Froehlke (Cache River), 473 F.2d 346 (8th Cir. 1972), and Conservation Council of North Carolina v. Froehlke (New Hope Dam), 473 F.2d 664 (4th Cir. 1973). Consequently, if defendants’ decision to proceed is based upon arbitrarily constructed elements of the B/C ratio,- or if it is otherwise capricious, an abuse of discretion, or fails, under NEPA, to give sufficient weight to environmental factors, that decision is subject to review and reversal by the courts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flag Fables, Inc. v. Jean Ann's Country Flags & Crafts, Inc.
730 F. Supp. 1165 (D. Massachusetts, 1990)
United States v. D.K.G. Appaloosas, Inc.
630 F. Supp. 1540 (E.D. Texas, 1986)
Johnston v. Davis
698 F.2d 1088 (Tenth Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
483 F. Supp. 897, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20305, 5 Fed. R. Serv. 518, 1979 U.S. Dist. LEXIS 9969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burkey-v-ellis-alnd-1979.