Burgin v. Madden, Unpublished Decision (5-24-2002)

CourtOhio Court of Appeals
DecidedMay 24, 2002
DocketCourt of Appeals No. L-01-1267, Trial Court No. CVF-98-3706.
StatusUnpublished

This text of Burgin v. Madden, Unpublished Decision (5-24-2002) (Burgin v. Madden, Unpublished Decision (5-24-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burgin v. Madden, Unpublished Decision (5-24-2002), (Ohio Ct. App. 2002).

Opinion

DECISION AND JUDGMENT ENTRY
This is an appeal from a judgment of the Toledo Municipal Court awarding plaintiff-appellee, Ed Burgin, $13,500 for heating systems he installed in four newly constructed homes. The court found that defendants-appellants, DJT, Inc. and Duane J. Tillimon, were solely responsible for the payment of that award. Therefore, the trial court also found in favor of defendant-appellee, Michael Madden, on his motion to dismiss Burgin's claim against him for those same monies. In addition, the court determined that appellants owed Madden $10,500 on his cross-claim against DJT, Inc. and Duane J. Tillimon for the duties Madden performed as the construction supervisor. Finally, the municipal court found in favor of Madden on appellants' cross-claim for damages in the amount of $14,474.84 that resulted from alleged overruns in construction costs and costs incurred due to delays in the sale of the new houses.

Appellants appeal the trial court's judgment and assert the following assignment of error:

"Both as to liability and as to the liability of Duane J. Tillimon, the judgment is against the manifest weight of the evidence."

On April 18, 1997, DJT, Inc. obtained financing, in the amount of $203,000, from National City Bank for the construction of four new houses in Byrne-Hill Estates. Duane J. Tillimon was the guarantor of the loan. The disbursing agreement named DJT, Inc. the general contractor of the project.

On April 30, 1997, Duane J. Tillimon, DJT, Inc., Thomas B. Crawford and Michael Pantanella, d.b.a. as Panford Homes ("Panford"), Michael Madden, d.b.a. Michael's Construction ("Madden"), and Equity Preservation, Inc. ("Equity"), entered into a contract for the construction and sale of houses (Contract I"). The original intent of the parties was to construct twenty homes in the Byrne-Hill Estates subdivision. Pursuant to the terms of Contract I, Panford was designated as the general contractor for and seller of the houses, Madden was the construction supervisor, Equity was the real estate broker, Duane J. Tillimon was to obtain financing of the project, and DJT, Inc. was to pay construction related expenses of up to $46,000 per house.

Contract I stated that DJI, Inc., was responsible for the payment of monies owed to the individual subcontractors. It added, however, that DJT, Inc. was acting solely as a "paymaster" for Panford and would not be "personally liable for payment of labor, material, commissions, or financing expenses to anyone." The contract expressly stated that Panford "shall have a separate agreement with Madden regarding the construction of the homes." It was signed by Duane J. Tillimon, Duane J. Tillimon as President of DJT, Inc., Duane J. Tillimon as President of Equity, Crawford and Pantanella as officers of Panford, and Michael Madden.

Madden and Panford entered into a separate home construction contract ("Contract II") for the building of four houses at Byrne-Hill Estates on May 6, 1997. Contract II set forth subcontractors' estimates for the costs of the different aspects, e.g., electrical work, of building the houses with a total of $46,000 per house. This amount included Madden's $6,000 per house fee for construction supervision. Contract II also specified that Madden would construct the four homes for Panford "in accordance with the plans and specifications submitted to National City Bank." These plans and specifications contained added costs for labor and/or materials that were not listed in Contract II.

On May 24, 1997, Duane J. Tillimon, in his individual capacity, sent a letter to Panford and Madden indicating that he no longer wished to participate in the building of any additional homes beyond the four already under construction under the April 30, 1997 contract. He claimed that there was no "meeting of the minds" in interpreting Contract I.

On May 29, 1997, Tillimon, again in his individual capacity, "terminated" Contract I between Duane J. Tillimon, DJT, Inc., Equity and Panford. In the letter sent to Panford, Tillimon stated that there was no meeting of the minds between the parties. The letter indicated that Tillimon was allowing Madden and the various subcontractors hired by Madden for Panford to complete the four houses. Panford, while indicating that the action by Tillimon constituted a breach of contract, withdrew from the project.

According to Tillimon, he believed that he and Madden reached a verbal agreement under which Michael's Construction would finish the project pursuant to the Panford/Madden contract. Madden testified, nonetheless, that his position as construction supervisor was unchanged.

In paying the subcontractors for their work, Madden would submit the subcontractor's invoice to Tillimon for each construction expense, and Tillimon, acting as President of DJT, Inc. would issue a check to Madden for the amount or amounts needed to pay the expense or expenses. At times, DJT, Inc. would issue a single check to Madden for the payment of more than one expense; therefore, Madden would be responsible for the payment of the individual subcontractors.

It is undisputed that, before May 29, 1997, Burgin was subcontracted to install a heating system in each of the new houses at a cost of $3,600 each. He was paid $900 in May 1997, but never received any further payment after he completed installing the heating systems on October 14, 1997. Burgin believed that Madden's position was "superintendent" of the project and that DJT, Inc. controlled the finances. He therefore sent his final bill to that entity.

It is also undisputed that the $46,000 allotted for the construction of each house was disbursed by DJT/Tillimon. According to Michael Madden, however, the final amount that he received from Tillimon was insufficient to pay the $13,500 owed to Burgin and the $10,500 owed to Madden in his capacity as the construction supervisor. In addition, there was no money available to pay another subcontractor, Jennite Company.

Michael Madden attributed the deficiency to the cost of the upgrades requested by Tillimon. For example, Madden indicated that the original Madden/Panford quote for the electrical work for all four houses was $7,200. But, according to Madden, due to "extras" requested by Tillimon, the actual amount expended was $15,646. Tillimon, on the other hand, asserted that all of the alleged upgrades were part of the plans and specifications submitted to National City Bank in the loan process as incorporated into the contract between Madden and Panford. Therefore, Tillimon concluded, in essence, that Madden was required to construct the four houses with these extras or upgrades and stay within the stated limit of $46,000 per house.

Because he never received the final payment, Burgin initiated the instant action, naming Duane J. Tillimon; DJT, Inc.; Crawford and his spouse and Pantanella, d.b.a. Panford; and Michael Madden, d.b.a. Michael's Construction as defendants. Madden filed his cross-claim against DJT, Inc., and Duane J. Tillimon and DJT, Inc. filed its cross-claim against Madden. The Crawfords and Pantanella, d.b.a. Panford Homes, were later dismissed from these proceedings.

In this appeal, appellants challenge specified findings made by the trial court, arguing that they are against the manifest weight of the evidence.

Judgments supported by some competent, credible evidence going to all essential elements of a cause shall not be reversed on appeal as being against the manifest weight of the evidence. C.E. Morris Co. v. FoleyConstr. Co. (1978), 54 Ohio St.2d 279, 279.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campanella v. Commerce Exchange Bank
745 N.E.2d 1087 (Ohio Court of Appeals, 2000)
Lucas v. Costantini
469 N.E.2d 927 (Ohio Court of Appeals, 1983)
Hummel v. Hummel
14 N.E.2d 923 (Ohio Supreme Court, 1938)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Hambleton v. R.G. Barry Corp.
465 N.E.2d 1298 (Ohio Supreme Court, 1984)
Legros v. Tarr
540 N.E.2d 257 (Ohio Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Burgin v. Madden, Unpublished Decision (5-24-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/burgin-v-madden-unpublished-decision-5-24-2002-ohioctapp-2002.