Burfeind v. People's Surety Co.

139 A.D. 762, 124 N.Y.S. 385, 1910 N.Y. App. Div. LEXIS 2296
Appellate Division of the Supreme Court of the State of New York·Decided July 29, 1910·Published·Cited by 1 cases

Opinion

Burr, J.:

On May 22, 1907, the Hudson River Concrete Company, plaintiff's assignor, and one Seligman, entered into a contract which related to filling, regulating and grading East Twenty-sixth street, between Avenue D and Clarendon road, and to the laying of concrete sidewalk and curb. Concurrently therewith a bond was executed by Seligman as principal, and appellant as surety, for the faithful performance of the conditions and covenants of said contract on Seligman’s part. This action is brought upon said bond. [763] The contract provided that a portion of the work should be completed within twenty working days from the date of the' contract, and that it should all be completed within a reasonable time, not. later than July 15, 1907. The complaint alleges fuff performance of the contract on the part of the concrete company, except that completion of the work was delayed until August fourteenth by the fault of said Seligman. Appellant pleads a general denial, with no affirmative defenses.

There is abundant evidence that the work was properly done, so far as the character and quality of it were concerned. The city inspector, called as a witness for defendant, so testified. His only objection to it was that the concreting was to be placed upon new fill, and under such circumstances there would be some sinking and cracking. But the putting of concrete on this new fill was the very thing that the parties to the contract agreed should be done. The portion of the work that was to be done within twenty days was substantially completed on June twenty-sixth, and the entire contract was substantially completed on August seventh; although there was some little work that was not done until August fourteenth. There is also abundant evidence that the delay in the prosecution of the work was due to the act of Seligman in obstructing the street, and also because, in the first instance, the city inspector refused to allow either of the parties to the contract to do that which they had agreed to do, viz., put concrete sidewalk and curb Upon a new fill. There is also uncontradicted evidence of some delay on the part of the carriers in delivering gravel, which was, within the terms of the contract, to be furnished by Seligman. The jury were justified in finding that the plaintiff was in no wise responsible for this delay, but the fault, so far as it was a fault, was that of Seligman or his employees.

The only exceptions in the case which require consideration relate to the charge. In the main charge the court said: “ He [referring to the concrete company] must satisfy you by evidence that he complied faithfully with every requirement of the contract except as to time, and as to that he had to do it in time unless he satisfies you- that was waived by Seligman, or that the performance in time was interfered with by Seligman.” At the close of the charge appellant’s counsel asked the court to charge “that [764] in order for the plaintiff to excuse any delay he must first prove that it was caused by acts of the defendant or could have been prevented by the defendant. The Court: I so charge. Upon that branch of the^case there is another position taken by the plain'tiff, that Seligman, the person with whom he contracted, by accepting the work waived the provision as to time. Defendant’s counsel: I except.” It is not entirely clear what counsel for the surety company intended to except to in the court’s 'response to his request to charge. But the appellant’s counsel subsequently said: I except .to that portion of your charge in which' yon stated that the jury may find a waiver of the. right of the obligation to perform at a Certain time by the acceptance of the work by Seligman — unless they also find that the People’s Surety Company agreed to allow Seligman to waive it. The Court: I decline- to charge that. Defendant’s counsel: I except.” The . previous statement of counsel was. not in the nature of a request to ' charge, and it did not accurately state what the court had said in its main charge. • If, however, it be considered as a request to charge, and a declination by the court, the request was inaccurate. Seligman might either waive performance of the con tract.or alter the ' provisions of it without the consent of the surety company, and that, would be ‘binding uj>on him whatever the effect might be upon that defendant. The court then, at the request of appellant’s counsel, expressly charged the jury that if any material change in the contract was made between Seligman and the Hudson Concrete Company; the surety company was released unless it consented to such change, and with that charge it seemed content. Finally appellant’s counsel asked the court to charge that Seligman had no power to bind the People’s Surety Company or create any' liability on the part of the People’s Surety Company by waiving performance of any obligations on the part of the Hudson River Company, and the court ■ declined to charge other than it had charged, and appellant’s- counsel took an exception. Again, the request was inaccurate in form because it should have included the words “ without the consent of the said Surety Company.” But taking the language of the request and refusal in its broadest form, we think that no error was committed.. ■ There is no evidence in the case on the part of either plaintiff or defendant of an express waiver by Seligman of any breach

Free access — add to your briefcase to read the full text and ask questions with AI

Burfeind v. People's Surety Co., 139 A.D. 762, 124 N.Y.S. 385, 1910 N.Y. App. Div. LEXIS 2296 (N.Y. Ct. App. 1910).

139 A.D. 762 (Burfeind v. People's Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ocean Operating Corp. v. Capital City Surety Co.
135 Misc. 359 (New York Supreme Court, 1929)