Buoy v. Clyde Milling & Elevator Co.

75 P. 466, 68 Kan. 436, 1904 Kan. LEXIS 124
CourtSupreme Court of Kansas
DecidedFebruary 6, 1904
DocketNo. 13,458
StatusPublished
Cited by21 cases

This text of 75 P. 466 (Buoy v. Clyde Milling & Elevator Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buoy v. Clyde Milling & Elevator Co., 75 P. 466, 68 Kan. 436, 1904 Kan. LEXIS 124 (kan 1904).

Opinion

The opinion of the court was delivered by

Johnston, C. J. :

James Buoy, an employee of the Clyde Milling and Elevator Co'mpany, who was assisting in the construction of a warehouse, was injured by the fall of a negligently constructed scaffold. Engaged in the work at the same time were Richa, a carpenter receiving $2.50 per day, and Buoy, a man of all work who received only $1.15 per day. Miller, the general manager of the company, employed Richa to complete the building, and told him that he would send Buoy around to help him. According to plaintiff’s testimony, Richa. had worked some time and had practically completed the scaffold when Buoy arrived at the building. Buoy inquired if the scaffold was safe, and the reply of Richa was that it could not be pulled down with a team. Plaintiff went upon the scaffold with Richa and within a few minutes it fell to the ground and the plaintiff was seriously injured.

In this action for damages the plaintiff alleged that the injury was caused by the negligence óf the defendant and its. employees in the unsafe and defective way in which the scaffold was built; that plaintiff had nothing to do with the construction of the scaffold and had no knowledge of its defective and insecure condition. The defendant pleaded that the injury was the result of plaintiff’s negligence and not [438]*438that of the defendant, and farther, that his injury had been greatly increased by the failure to take proper care in the treatment of his injury. There was conflicting testimony as to the experience of plaintiff, his knowledge of existing conditions, and whether he was subordinate to Richa, the carpenter.’- There was conflict, too, as to whether plaintiff assisted in the erection of the scaffold and should have known of its defective condition. When plaintiff had introduced his testimony, a demurrer thereto was interposed by the defendant which the court, after consideration, ■overruled. The defendant’s testimony was then introduced, and also some by the plaintiff in rebuttal, when the court submitted the case on instructions, with special questions which the jury were required to answer. The jury found in favor of the plaintiff, awarding him $1069 as damages, and returned answers to the special questions as follows :

“1. Were not the brackets, the braces, the pickets and the plank or planks used as flooring on the scaffold in question all of good, safe, sound material and fit for the purpose for which they were used ? A. Yes.”

“3. Was not the plaintiff present and assisting in completing and erection of the scaffold in question ? A. No.

”4. Did not the plaintiff have ample opportunity to examine and inspect the scaffold as erected, and every part thereof, to ascertain as to its condition and the manner in which it was erected and was standing, before going to work thereon ? A. Yes.

“5. Was any officer or agent of the defendant corporation present at the time the scaffold was erected and before the accident? A. Yes.

”6. If you answer the preceding question in the affirmative, state what officer of the corporation. A. Richa, vice-principal.

“7. Was not the witness Richa an experienced, [439]*439competent and skilful mechanic or carpenter? A. Yes.'”

“9. Did the witness Richa have any supervision or control over the plaintiff in the work that they were doing on the day of the accident. A. Yes.

“10. If you answer the last question in the affirmative, state what supervision or control said Richa had of the plaintiff, and from what source or authority he procured the right to such supervision or control. A. Vice-principalship, from Miller.

“11. Did not the plaintiff receive his orders as to the work done or to be done on the day of the accident from Miller, the manager of the defendant, and from no other person ? A. Yes.

“12. Did either the plaintiff or the witness Richa have any authority or control over the other? A. Yes.

“13. If you answer the last question in the affirmative, then state what such authority or control was and from what source it originated. A. As vice-principal, from Miller.

“14. Did the defendant or any of its officers or agents in any way direct, superintend or have charge of the erection of the scaffold in question? A. Yes.

“15. If you answer the previous question in the affirmative, then state which officer of the defendant, and what such officer did' towards directing, controlling or superintending the erection of the scaffold in question. A. Vice-principal Richa erected the scaffold.

“16. Was not such scaffold, erected in the manner in which this scaffold was erected, an ordinarily safe place upon which to perform the work necessary to be done at that time? A. No.

“17. If you answer the preceding question in the negative, in what respect was such scaffold unsafe ? A. Defective in bracing.

“18. Did not the defendant and its officers and agents use all proper and reasonable care in providing for the safety of the plaintiff in doing the work that he was to do on the day of the accident? A. No.

“19. If you answer the preceding question in the [440]*440negative, then state fully in what respect you find the defendant or its officers guilty of negligence. A. In defective bracing of scaffold.

“20. Under the instructions under which the plaintiff and the witness Richa were, working on the day of the accident, was it any more the duty of one than the other to erect any scaffold that might be needed for use in the work which they were to do ? A. Yes.

“21. If you answer the preceding question in the affirmative, then state which one, and why. A. Richa, vice-principal.

“22. Was it not necessary, in order to do the work which plaintiff and the witness Richa had been ordered to do on .the day of the accident, that a scaffold-be erected? A. Yes.

“23. If you-find for the plaintiff, state how much, if any, you allow for medical attendance and treatment ; how much, if any, you allow for physical suffering ; how much, if any, you allow for mental suffering how much, if any, you allow for loss of time, and how much, if any, for permanent injuries. A. 1st, $5.90; 2d, $100;' 3d, ,$50; 4th, $69; 5th, $844.10. Total amount allowed, $1069.

“24. Was not the plaintiff just prior to the accident standing on the plank beyond and outside of the west bracket ? A. No.”'.

The defendant objected to the answers made to- . several questions which were all overruled except as to No. 10, which, under the direction of the court, was reconsidered and a modified answer returned, striking out “Yice-principalship, from Miller,” and inserting “By being a superior workman.” The defendant asked that certain of the findings be set aside because they were not sustained by the evidence, not responsive to the questions, and were contrary to the law and the instructions of the court. This motion was overruled ; whereupon they asked for judgment in favor of the defendant on the findings, but this motion was likewise overruled. A motion- for a new [441]*441trial was then made on six different grounds, one of which was that the verdict and special findings were not sustained by sufficient evidence and were contrary to law; also, errors of law occurring at the trial. The motion for a new trial was allowed, as is recited in the entry,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Massey-Ferguson, Inc.
883 P.2d 1120 (Supreme Court of Kansas, 1994)
Conboy v. Crofoot
397 P.2d 326 (Supreme Court of Kansas, 1964)
Fishburn v. International Harvester Co.
138 P.2d 471 (Supreme Court of Kansas, 1943)
Mitchener v. City Com'rs, City of Okmulgee
1924 OK 645 (Supreme Court of Oklahoma, 1924)
Stice v. Hines
205 P. 616 (Supreme Court of Kansas, 1922)
Federal Refining Co. v. Fortuna Oil Co.
1919 OK 365 (Supreme Court of Oklahoma, 1919)
Custer v. Royse
179 P. 353 (Supreme Court of Kansas, 1919)
Mentze v. Rice
172 P. 516 (Supreme Court of Kansas, 1918)
State ex rel. McGill v. Gerhards
162 P. 1149 (Supreme Court of Kansas, 1917)
Thurston v. Fritz
138 P. 625 (Supreme Court of Kansas, 1914)
Ardmore Oil & Milling Co. v. Doggett Grain Co.
1912 OK 159 (Supreme Court of Oklahoma, 1912)
Maw v. Coast Lumber Co.
114 P. 9 (Idaho Supreme Court, 1911)
Murphy v. Edgar Zinc Co.
112 P. 109 (Supreme Court of Kansas, 1910)
Sutter v. International Harvester Co. of America
106 P. 29 (Supreme Court of Kansas, 1910)
Missouri, Kansas & Texas Railway Co. v. Quinlan
93 P. 632 (Supreme Court of Kansas, 1908)
Jones v. Adair
91 P. 78 (Supreme Court of Kansas, 1907)
Gillaspie v. United Iron-works Co.
90 P. 760 (Supreme Court of Kansas, 1907)
Acker v. Norman
84 P. 531 (Supreme Court of Kansas, 1906)
Wilder ex rel. Wilder v. Great Western Cereal Co.
104 N.W. 434 (Supreme Court of Iowa, 1905)
Clyde Milling & Elevator Co. v. Buoy
80 P. 591 (Supreme Court of Kansas, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
75 P. 466, 68 Kan. 436, 1904 Kan. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buoy-v-clyde-milling-elevator-co-kan-1904.