Buono v. Petrazzuoli, No. 30 27 91 (Jan. 11, 1993)

1993 Conn. Super. Ct. 955
CourtConnecticut Superior Court
DecidedJanuary 11, 1993
DocketNo. 30 27 91
StatusUnpublished

This text of 1993 Conn. Super. Ct. 955 (Buono v. Petrazzuoli, No. 30 27 91 (Jan. 11, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buono v. Petrazzuoli, No. 30 27 91 (Jan. 11, 1993), 1993 Conn. Super. Ct. 955 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff, Lawrence P. Buono, seeks damages and/or the foreclosure of a mechanic's lien on the home owned by defendants, Mario Petroazzuoli and Maria Petrazzuoli, on which he built an addition. The plaintiff claims that the defendants did not allow him to complete the project and that he is owed $19,462.00 for work performed before he was barred from the work site. The defendants have filed two special defenses. In their first special defense they claim that the plaintiff's work was not performed in accordance with the written agreement and that much of the work was completed in an unskillful and unworkmanlike manner.

In their second special defense, the defendants invoke20-429 C.G.S. and take the position that the plaintiff cannot recover damages or other remedies because a) the written contract did not contain a notice of cancellation rights, b) the contractor was not registered in accordance with 20-429 C.G.S. and c) the contract did not contain a starting date and completion date.

In a cross claim, the defendants allege that the plaintiff's performance was so deficient that they had to hire others to correct and/or complete the project, and they seek money damages.

THE HOME IMPROVEMENT ACT DEFENSE

The court finds that the written contract for the building of an addition to the defendants' home at 34 Cortina Road, East Haven, was signed by all parties on August 6, 1988. The contract requires the builder to install a foundation and construct an addition "in accordance to plans submitted to contractor." The CT Page 956 defendants purchased these plans from an architect, with no involvement by the builder. The architect's drawings and specifications were incorporated into the contract, which further provided that "[a]ll materials and work will meet city and building codes as contracted." The plans as a whole were not presented into evidence by any party, with the exception of certain excerpts filed in connection with an application for a building permit.

The contract price for the work set forth was $64,000.00, to be paid in four payments of $16,000.00 upon completion of various stages of the work. The contract provides for extra charges for "additional excavating" if the builder encountered problems such as ledge or a high water table upon excavating, and dollar amounts are set forth as the allowances for paint, tile, and light fixtures, with amounts beyond the allowances to be paid by the homeowners.

The defendants did not establish that the plaintiff was not a registered home improvement contractor.

The contract, on its face, contains a starting date of August 8, 1988 and a completion date of November 5, 1988. It contains no notice of the right to cancel. The defendants claim that this deficiency renders the contract unenforceable pursuant to 20-429(a) C.G.S. The bar to enforcement invoked by the defendants was enacted in P.A. 88-269, Sec. 9, which was approved on June 2, 1988. That public act contains no specific effective date. Therefore by operation of 2-32 C.G.S., it took effect on October 1, 1988, and the requirement of a cancellation notice is inapplicable to a contract entered into on August 6, 1988.

The defendants note that a motion to strike their second special defense was denied by another judge of this court. That adjudication was not accompanied by any memorandum of decision, and no legal reasoning appears in the file regarding the denial of the motion. Under the circumstances, this court finds it appropriate to depart from that interlocutory ruling. State v. Almeda, 211 Conn. 441, 453 (1989); Breen v. Phelps, 186 Conn. 86 (1982). The requirements of the Home Improvement Act invoked by the defendants are inapplicable to the contract at issue, which was signed before the effective date of the enactment.

THE PLAINTIFF'S CLAIM CT Page 957

The relationship between the plaintiff and the defendants became a difficult one as the construction project proceeded. Mario Petrazzuoli, who was home all day, closely monitored each of the plaintiff's activities and frequently found fault. Where his architect's plans failed to provide detail, he expected the builder to supply additional features at no additional cost, notably in the case of the driveway. The plans called for a double garage beneath the addition. As a condition of paying a quarterly payment, the homeowner required the builder to excavate the driveway and move the earth to another part of his property for possible sale. The contract states "driveway not contracted to Carpentry Service."

The homeowner changed some materials, changed the size of windows, and rejected the shower stall the builder ordered without recognizing that late changes of detail must delay the work, and that added features were expenses that had not been the basis of the contract price. The builder was in the position of needing to complete various phases in order to receive the money necessary to pay his subcontractors and to pay for materials, while being subject to changes and objections that impaired his ability to complete each phase. Instead of being able to complete the addition by November 1988, the builder was still working on the premises in April 1989, even though he had not received any payment since December 1988. The transaction reached an impasse in April 1989, at which time the homeowners were dissatisfied and reluctant to pay the last installment and the builder was reluctant to keep working when full payment was unlikely.

Mr. Petrazzuoli indicated to his architect that he wished to fire the plaintiff and hire someone else to complete the project, and the transaction broke down. The court finds that although the defendants caused their attorney to send letters accusing the builder of breach, the defendants, by their conduct, failed to permit the builder to complete the contracted-for work and set a standard of perfect performance that was tantamount to refusing to allow completion. In such a situation, the builder is entitled to recover the value of the work performed to the point he is precluded from completion. Simonetti v. Lovermi, 15 Conn. App. 722,725 (1988).

The court finds that the following items required by the contract were not completed by the plaintiff CT Page 958

1. venting furnace $400.00

2. connect fuel hose 180.00

3. punch list of repair of nail holes and clean-up 200.00

The final payment installment, minus the cost of completion of these items, would be $15,220.00. (Cost of completion has been extrapolated from bills for work by subsequent builders. Since these are not itemized, the court has had to make inferences as to the amount attributable to these items, based on the witnesses' description of the work.)

The plaintiff is also entitled to recover for the following items that were either specifically identified as "extra" in the contract or were extra work performed at the insistence of the homeowners as a condition to payment of the installments due. Though the Supreme Court held in Caulkins v. Petrillo, 200 Conn. 713 (1986) that agreements for extras should be reduced to writing, it recognized in Habetz v. Condon, 224 Conn. 231

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Breen v. Phelps
439 A.2d 1066 (Supreme Court of Connecticut, 1982)
Caulkins v. Petrillo
513 A.2d 43 (Supreme Court of Connecticut, 1986)
State v. Almeda
560 A.2d 389 (Supreme Court of Connecticut, 1989)
Habetz v. Condon
618 A.2d 501 (Supreme Court of Connecticut, 1992)
Simonetti v. Lovermi
546 A.2d 331 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 955, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buono-v-petrazzuoli-no-30-27-91-jan-11-1993-connsuperct-1993.