Bullock v. Horn

44 Ohio St. (N.S.) 420
Ohio Supreme Court·Decided January 15, 1886·Published

Opinion

Spear, J.

It is not claimed in this case that the defendant’s assiguor, the lumber company, had, by virtue of its claim against the contractor, any lien upon the premises; nor is it denied that the plaintiff' had complied with the law entitling him to recover against the defendant, and to a lien. The only question is as to the right of set-off in favor of the defendant and against the plaintiff. The proposition may be stated thus: Can the owner of premises, having knowledge that a mechanic has performed work upon a building thereon, under employment of the principal contractor, set off against a claim for work, so done, a claim against such contractor, not arising out of the contract under which the building is constructed, or in any way having relation thereto, and acquired by such owner after the labor was performed by the mechanic, but before the owner had notice that the mechanic had not been paid ?

[423]*423The question is to be determined by a consideration of the several sections of our statute relating to mechanics’ liens. Without quoting at length from these sections, their effect, so far as they apply to the question here, may be stated. Sections 3184-3192, Revised Statutes, provide for the taking of a lien upon the premises by the contractor. Section 3193, and following, give the right to a lien to any sub-contractor, laborer, or mechanic, who, under employment of the head contractor, performs labor or furnishes material for the improvement, and who has not been paid. He may file with the owner a sworn and itemized account of the amount and value of the labor or material, with all credits and set-offs, and upon receiving such notice the owner shall detain in his hands all subsequent payments from the principal contractor upon the contract in an amount, sufficient to satisfy the claim. Within five days after receiving such account the owner is required to notify the contractor, and if within five days thereafter he does not notify the owner of his intention to dispute or commence an action to adjust the account, he is deemed to assent to its correctness, and thereupon such subsequent payment shall be applied by such owner to the account. If the contractor neglect to pay within five days after such assent to the correctness of the account, the owner shall pay, when due, the whole, or, in case other claims have been filed, a pro rata amount, as the case may be, out of subsequent payments owing to the contractor, and on his failure for ten days, the sub-contractor, workman, or material-man may recover against the owner in an action for money had and received, when' due, the whole, or a pro rata amount, as the case may be, not exceeding in any case the balance due to the principal contractor.

In addition to this remedy, the workman or material-man, by complying with subsequent provisions, may have a lien upon the premises which shall date back from the date of performing the first item of labor, or of the first material furnished, which shall have the same operation, effect, and duration, and be subject to the same obligations [424]*424with respect to the owner, as the lien of the head-contractor in similar cases. Such lien shall take precedence over and lien already taken or to be taken by the contractor, and an 'assignment or transfer by such contractor of his contract with the owner, as well as proceedings in attachment, or otherwise, against such contractor, to subject or incumber his interest in such contract, shall save and be subject to the claim of every laborer, mechanic, or material-man who has furnished labor or material toward the erection or repair of the structure.

The 'statute is highly remedial in its character, and should receive such liberal construction as will carry out the purpose of the legislature in its enactment. The labbr of the workman and the material of the material-man having contributed to the erection of the structure; having, indeed, created, in part the very property on which the lien is sought to be attached, che purpose of the law is to give to such parties the right, where the contractor refuses to pay, to be paid for their labor and material out of the fund which has been earned under the contract, and out of the structure, and the land upon which it stands, such claim, as to amount, not to be in excess of the claim of the contractor as measured alone by the contract and his performance of it.

In giving a construction to this statute, by fair inference it may be assumed that the rights of the workman and material-man, as against the owner, are based upon the latter’s contract with the contractor, and while they are subordinate to the contract, and are to be worked out through it, those parties have the right to rest in security upon it and the means provided by law to secure its application to their demands. In the absence of fraud they are presumed to have notice of the terms of the original contract. Hence, if the original contract showed that pay-' ment had been made in advance to the contractor, or if it contemplated the allowance, by the contractor, of set-off theu held or to be acquired by the owner as payment, such provisions would bind the workmen and material-men, as they would be held to have accepted employment of the [425]*425contractor with an implied assent to such terms. But, where the contract was silent as to advance payments, and as to claims of the owner against the contractor, the Avorkmen and material-men could not be held to have accepted employment with a vie\v to such contingencies.

The purpose of laAvs of this character is, .as stated by Phillips, in his work on Mechanic’s Liens, “ to take from the owner money actually owing by him upon his contract and apply it in payment for the labor and material which the Avorkmen and material-men have contributed tOAvard the performance of the same contract.” And, where it is provided, as in our statute, that an assignment or transfer by the contractor of his contract with the owner shall save and be subject to the claims of the workmen and material-men who have furnished labor or material toAvard the construction of the improvement, such provisions operate as an equitable transfer to the workmen and material-men of the money due to the contractor by the owner, subject only to such obligations as spring out of.the contract itself. This construction is believed to be founded in reason and to be supported by the holdings of courts in other states upon the subject. The amount owing to the contractor under the contract being thus found to be transferred to the AAorkmen and material-men, it would seem to follow that any process, proceeding, or device Avhich has for its object the Avresting from the Avorkmen and material-men of their equitable hold upon the amount due under the contract, being the result of and produced by their labor and material, would be directly against the spirit of the law, if not against the very letter itself. All proceedings by attachment, or otheiwise, to subject or incumber the contractor’s interest in the contract, are to save and be subject to the claims of the workmen and material-men, and it is difficult to perceive why the allowance of a set-off against the contractor acquired by the OAvner, after the labor is performed or the material is furnished, would not work the same substantial result that Avould be reached by attachment, nor Avhy it would not divert the security afforded [426]*426by the contract from those whom the statute contemplate, shall have the benefit of it, and thus accomplish, indirectly, in favor of the owner, that which the statute provides shall not be done by any one, directly.

Free access — add to your briefcase to read the full text and ask questions with AI

Bullock v. Horn, 44 Ohio St. (N.S.) 420 (Ohio 1886).

44 Ohio St. (N.S.) 420 (Bullock v. Horn) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.