Bulletproof Plumbing Corp. v. Ohlson

2025 IL App (1st) 232007-U
CourtAppellate Court of Illinois
DecidedJune 20, 2025
Docket1-23-2007
StatusUnpublished

This text of 2025 IL App (1st) 232007-U (Bulletproof Plumbing Corp. v. Ohlson) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bulletproof Plumbing Corp. v. Ohlson, 2025 IL App (1st) 232007-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (1st) 232007-U

SIXTH DIVISION June 20, 2025

No. 1-23-2007

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT

BULLETPROOF PLUMBING CORP, ) Appeal from the ) Circuit Court of Plaintiff-Appellant and Cross-Appellee, ) Cook County ) v. ) No. 20 CH 1724 ) THOMAS OLHSON, et al., ) The Honorable ) Lewis Nixon, Defendants-Appellees and Cross-Appellants. ) Judge Presiding.

PRESIDING JUSTICE TAILOR delivered the judgment of the court. Justices Hyman and Gamrath concurred in the judgment.

ORDER

¶1 Held: The circuit court erred in granting defendants-owners’ motion for judgment on the pleadings on plaintiff-subcontractor’s claim to foreclose on its lien. Because plaintiff ultimately sought to foreclose its lien only against defendants-owners and no third party had an interest in the property, plaintiff-subcontractor simply had to bring suit within two years of its last date of work, which it did. Any alleged deficiency in its recorded lien had no effect on its lien foreclosure claim against defendants-owners.

¶2 I. BACKGROUND

¶3 Plaintiffs Bulletproof Plumbing Corp. (Bulletproof) and James D’Amico (D’Amico),

doing business as Custom Cut Construction, were subcontractors on a construction project for a

residential property owned by Thomas and Paula Ohlson (Ohlsons). Bulletproof and D’Amico No. 1-23-2007

were not paid for their work and filed this action to foreclose on their mechanic’s liens and for

other relief. The circuit court entered judgment on the pleadings against Bulletproof on its lien

foreclosure claim against the Ohlsons, and denied the Ohlsons’s motion for judgment on the

pleadings on D’Amico’s lien foreclosure claim. Both orders have been appealed. We reverse the

judgment against Bulletproof and dismiss the Ohlsons’s cross-appeal of the order denying their

motion for judgment on the pleadings on D’Amico’s lien foreclosure claim for lack of jurisdiction.

¶4 The complaint alleges that the Ohlsons hired general contractor 4TGC, LLC (4TGC) on or

before July 2018 to extensively remodel their home in LaGrange, Illinois. 4TGC and Bulletproof

entered into a verbal contract for Bulletproof to perform plumbing work. Bulletproof was to be

paid based on the number of hours worked and the value of the materials used. Bulletproof worked

on the project until November 18, 2018, when it substantially completed the rough plumbing work,

and asserted that it was owed $32,265 for its services. 4TGC and D’Amico, doing business as

Custom Cut Construction, also entered into a subcontract for D’Amico to provide carpentry

services for the remodeling project. D’Amico substantially completed his work on January 22,

2019, and claimed he was owed $19,424 for his work.

¶5 On January 25, 2019, Bulletproof learned that the Ohlsons had terminated their relationship

with 4TGC. Bulletproof had not been paid for its work so on February 8, 2019, it provided notice

of its lien claim to the Ohlsons and to J.P. Morgan Chase Bank (Chase), which at the time held a

mortgage on the Ohlsons’s property. On April 2, 2019, Bulletproof recorded its notice and lien

claim with the Cook County Recorder of Deeds. The lien claim did not include the November 18,

2018, work completion date but did state that 4TGC entered into a contract for the construction

project with Bulletproof on or about July 31, 2018. D’Amico filed and recorded his lien claim with

2 No. 1-23-2007

the Cook County Recorder of Deeds on February 11, 2019. D’Amico’s lien claim included the

January 22, 2019, date on which he had substantially completed work under his subcontract.

¶6 On February 11, 2020, Bulletproof and D’Amico filed a complaint against the Ohlsons and

Chase to foreclose on their liens under the Mechanics Lien Act (770 ILCS 60/1 (West 2020) (Act))

for breach of contract, and for relief under the equitable doctrine of quantum meruit. On March

24, 2020, Chase moved to dismiss the complaint against it. It argued that because it had released

its mortgage on the Ohlsons’s property in January 2020, before the complaint was even filed, it

“no longer ha[d] an interest in the subject property,” and was “no longer a necessary party to this

action and should be dismissed.” A stipulation and agreement between Chase, Bulletproof, and

D’Amico was filed in circuit court in May 2020. It noted that Chase was initially “included as a

defendant by virtue of its [m]ortgage [on the Ohlson’s property]” but stated that because the

mortgage was released on January 10, 2020, before suit was filed, the parties agreed to dismiss

Chase from the suit. On July 22, 2021, after it failed to appear and respond, the circuit court entered

judgment against 4TGC.

¶7 On February 8, 2022, Bulletproof and D’Amico filed an amended complaint. The Ohlsons

filed a motion for judgment on the pleadings under section 2-615(e) of the Civil Practice Law (735

ILCS 5/2-615(e) (West 2022)), arguing, inter alia, that Bulletproof’s and D’Amico’s recorded

liens were invalid because they did not indicate their last date of work. Bulletproof and D’Amico

argued in response that because no third-party purchasers or incumbrancers were involved in this

case, no work completion date was required. On April 21, 2022, the circuit court entered judgment

on the pleadings against Bulletproof and D’Amico on their lien foreclosure claims under counts I

and IV of the amended complaint, respectively. It found that their claims were defective because

their recorded liens failed to include their work completion dates. Bulletproof and D’Amico moved

3 No. 1-23-2007

the court to reconsider, stating that “[d]iligent research has disclosed no case holding that a section

7 recorded lien is required to enforce a claimant’s rights under the Act solely against the owner.”

They argued that section 7’s requirements apply only when a claimant seeks to enforce the lien to

the prejudice of a third-party lender or purchaser, whereas a claimant’s lien is “perfected” as to an

owner as long as it is filed within two years after the lien claimant’s work is completed. In addition,

D’Amico noted that the court “apparently overlooked” the fact that his recorded lien did include

his last day of work, January 22, 2019.

¶8 On September 28, 2023, the circuit court acknowledged that D’Amico’s recorded lien did

state the date his work was substantially completed and therefore reinstated his lien foreclosure

claim. However, it confirmed its earlier decision that Bulletproof’s claim was barred because its

recorded lien did not recite the date it last performed work on the project. In rejecting Bulletproof’s

claim under the Act, the circuit court focused on the words “or” and “prejudice” in the phrase “[n]o

contractor shall be allowed to enforce such a lien against or to the prejudice of any other creditor,

incumbrancer or purchaser, unless within 4 months after completion *** [they] bring an action to

enforce *** or file in the office of the recorder ***a claim for lien[.]” The court found that as long

as a creditor, incumbrancer, or purchaser may be prejudiced by a failure to comply with the four-

month deadline to file a lien claim or record a lien with the county recorder of deeds, the claim

would fail as to the owner also.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stafford -Smith, Inc. v. Intercontinental River East, LLC
881 N.E.2d 534 (Appellate Court of Illinois, 2007)
Mutual Services, Inc. v. Ballantrae Development Co.
510 N.E.2d 1219 (Appellate Court of Illinois, 1987)
First Federal Savings & Loan Ass'n v. Connelly
454 N.E.2d 314 (Illinois Supreme Court, 1983)
U. S. Air, Inc. v. Prestige Tours, Inc.
512 N.E.2d 68 (Appellate Court of Illinois, 1987)
Behl v. Gingerich
920 N.E.2d 665 (Appellate Court of Illinois, 2009)
Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership
731 N.E.2d 394 (Appellate Court of Illinois, 2000)
Crossroads Ford Truck Sales, Inc. v. Sterling Truck Corp.
792 N.E.2d 488 (Appellate Court of Illinois, 2003)
National City Mortgage v. Bergman
939 N.E.2d 1 (Appellate Court of Illinois, 2010)
Bennett v. Chicago Title and Trust Co.
936 N.E.2d 1068 (Appellate Court of Illinois, 2010)
Palmolive Tower Condominiums, LLC v. Simon
949 N.E.2d 723 (Appellate Court of Illinois, 2011)
Pedersen & Houpt, P.C. v. Main Street Village West, Part 1, LLC
2012 IL App (1st) 112971 (Appellate Court of Illinois, 2014)
Father & Sons Home Improvement II, Inc. v. Stuart
2016 IL App (1st) 143666 (Appellate Court of Illinois, 2016)
Springer v. Kroeschell
43 N.E. 1084 (Illinois Supreme Court, 1896)
Blumenthal v. Brewer
2016 IL 118781 (Illinois Supreme Court, 2017)
Carle Foundation v. Cunningham Township
2017 IL 120427 (Illinois Supreme Court, 2018)
State ex rel. Leibowitz v. Family Vision Care, LLC
2020 IL 124754 (Illinois Supreme Court, 2020)
Mayle v. Urban Realty Works, LLC
2020 IL App (1st) 191018 (Appellate Court of Illinois, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (1st) 232007-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bulletproof-plumbing-corp-v-ohlson-illappct-2025.