Building Supply Co. of Englewood, New Jersey, Inc. v. Greenberg

153 A. 581, 107 N.J.L. 361, 1931 N.J. LEXIS 166
CourtSupreme Court of New Jersey
DecidedFebruary 2, 1931
StatusPublished
Cited by1 cases

This text of 153 A. 581 (Building Supply Co. of Englewood, New Jersey, Inc. v. Greenberg) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Supply Co. of Englewood, New Jersey, Inc. v. Greenberg, 153 A. 581, 107 N.J.L. 361, 1931 N.J. LEXIS 166 (N.J. 1931).

Opinion

The opinion of the court was delivered by

Wells, J.

This is a mechanics’ lien suit and out of it arises a dispute between a holder of advance-money mortgages and a materialman as to the priority of their respective claims.

The plaintiff supplied between September 28th, 1928, and January 18th, 1929, certain building materials to the Tea-neck Building Corporation used by it in-the construction of three one-family dwelling houses on a tract of land owned by it in the township of Teaneck, Bergen county, aggregating $6,782.75. Subsequently the Teaneck Building Corporation paid $2,500 on account, leaving a balance of $4,282.75, for which plaintiff brings this suit.

On February 25th, 1929, the Teaneck Building Corporation was declared insolvent and Joseph Greenberg and N. J. *363 Cafarelli were appointed receivers by the Court of Chancery, which gave plaintiff leave to bring this suit.

The appellant, The East Rutherford Savings, Loan and Building Association, agreed to loan the Teaneck Building Corporation the sum of $5,000 on each of said three lots of land, taking three bonds and advance-money mortgages, dated December 7th, 1928, and duly recorded in the Bergen county clerk’s office.

The sum of $4,900 was actually advanced by the appellant to the Teaneck Building Corporation on each of these three mortgages.

The lien claim of plaintiff was filed March 11th, 1929, and in the suit brought on said lien claim by the plaintiff-respondent against the receivers of the Teaneck Building Corporation, the East Rutherford Savings, Loan and Building Association (the appellant herein) was made a party defendant, as the holder of said mortgages.

The Circuit Court judge, before whom the case came up for trial, referred it to a referee to take and state the account between the parties and to report the same back to the Circuit Court. The referee found first, that the sum of $4,900 advanced by appellant on each of the three mortgages of $5,000, was entitled to priority in payment over the lien claim of the plaintiff; second, that plaintiff was entitled to a special lien against the premises described in the lien •claim, subject to the lien of the appellant’s mortgages.

ISTo exceptions were filed by the defendant-appellant to any part of the referee’s report.

The plaintiff-respondent, however, excepted to the report for the following reasons:

1. That the referee did not allow plaintiff a priority of its lien claim over the mortgages of appellant.

2. That the findings of the referee were errors in law with reference to the priority of the mechanics lien of the plaintiff over the mortgages of appellant.

And plaintiff prayed that the report of the referee be revised, in favor of the plaintiff in so far as priority of its *364 lien claim over the mortgages of the appellant, as a matter of law.

The matter came on before the Circuit Court judge on the exceptions to the referee’s report. Counsel of appellant and respondent both argued orally and by briefs to the judge, the question of whether or not the appellant, to obtain a priority of its mortgage over respondent’s lien claim, was obliged to trace the mortgage-money into the building — the judge, having found as a matter of law that it was necessary so to do, ordered the referee’s report to be amended accordingly.

An order was thereupon entered giving the respondent a priority of its lien claims over the mortgages of the appellant, after the first payment of $3,000 made on each of said three mortgages — the respondent having given its consent to the appellant, making said payments to the builder and owner and having waived its claim to priority over said mortgages to the extent of the $3,000 so advanced on each mortgage.

The first contention on the part of the appellant is that there was harmful error in the action of the Circuit Court in amending the referee’s report, and confirming the same after it was amended.

It may be that a careful examination of the “Practice act” of 1903, under which appellant claims this reference was made, will not disclose any power in the Circuit Court to amend the referee’s report, in the manner attempted, and that the only remedy for erroneous decisions of the referee is on motion to set aside the report and grant a new trial, as suggested by appellant. We do not think it necessary to pass upon this interesting question in deciding this case. Both parties here without objection dealt with the matter as if it were being tried by the Circuit Court on exceptions to the report of the referee.

Both the appellant and respondent argued the meritorious questions involved orally before the Circuit judge and by written briefs.

The Circuit judge therefore tried without objection on the part of either party to the litigation, the meritorious ques- *365 lions involved and a rule for judgment was entered accordingly.

In Kapherr v. Schmidt, 98 N. J. L. 803, this court held that:

“Where parties to an action try and submit the question ■at issue upon a theory apparently satisfactory to themselves, and suffer the case to go to the jury upon the legal theory thus adopted, it is too late, upon appeal, for either party, for the first time, to question the legal propriety of the course pursued.”

It seems to us, therefore, that the first contention of appellant is without merit.

It is next contended that on the merits of the ease, the judgment of the Circuit Court should be reversed.

Appellant claims that the referee was right in finding that the amount of $4,900 actually advanced on each of the $5,000 mortgages was prior to the lien claim of respondent.

The referee found that the claim of the plaintiff in this suit rested upon section 14 of the Mechanics’ Lien act (Pamph. L. 1898, p. 538; 3 Comp. Stat., pp. 3302, 3303), and that under this section, advance-money mortgages were prior to mechanics’ lien claims to the extent of all moneys advanced prior to the time when the lien claims are filed. He cites the case of Franklin Society v. Thornton, 85 N. J. Eq. 525, decided by this court, as authority for his conclusion.

In our opinion section 15 and not section 14 of the Mechanics’ Lien act is applicable to the ease sub judice.

Section 14 has to do with purchase-money mortgages which are also advance-money mortgages, and Mr. Justice Swayze, in the case of Franklin Society v.' Thornton, was dealing with a combination purchase-money and advance-money mortgage, and very properly held that in such a situation the right of the mortgagee under section 14 of the Mechanics’ Lien act was superior to the mechanics’ lien claim, to the extent of the amount actually advanced on the mortgage prior to the time of the filing of the lien claims.

Section 15 of the Mechanics’ Lien act (Pamph. L. 1898, p. 538; 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hasbrouck Heights Hospital v. Stuart
166 A. 697 (Supreme Court of New Jersey, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
153 A. 581, 107 N.J.L. 361, 1931 N.J. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-supply-co-of-englewood-new-jersey-inc-v-greenberg-nj-1931.