Building Mart, Inc. v. Allison Steel Manufacturing Co.

380 F.2d 196, 1967 U.S. App. LEXIS 5656
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 12, 1967
Docket8891_1
StatusPublished
Cited by16 cases

This text of 380 F.2d 196 (Building Mart, Inc. v. Allison Steel Manufacturing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Building Mart, Inc. v. Allison Steel Manufacturing Co., 380 F.2d 196, 1967 U.S. App. LEXIS 5656 (10th Cir. 1967).

Opinion

PER CURIAM.

This action was removed to the United States District Court for the District of New Mexico by reason of requisite diversity of citizenship and amount in controversy. After written interrogatories were served and answered and depositions had been taken the district court granted the motion for summary judgment of defendant (appellee) Allison Steel Manufacturing Co., denied the motion for partial summary judgment on the issue of liability of the plaintiff (appellant) Building Mart, Inc., and dismissed the complaint with prejudice. Appellant has appealed from the summary judgment against it.

The record, viewed in the light most favorable to appellant, as we are required to do in passing upon the propriety of summary judgment, 1 tends to establish the following facts, most of which appear without substantial conflict.

*197 Appellant (Building Mart, Inc.) became the general contractor for the construction of the Amrad Radar Shield at White Sands, New Mexico, by virtue of a United States contract formally awarded on November 6, 1964. Prior to that date appellee (Allison Steel), through its New Mexico branch manager, Vance Fagan, 2 contacted appellant by telephone and requested an appointment to discuss the possibility of his company’s being named subcontractor for the supply and erection of the structural steel for the project. Discussions between Fagan and Glazer, vice president of appellant, were held between November 2 and 4, 1964, during which time appellee orally proposed to do the structural steel portion of the radar shield at a price of $250,000. The terms and conditions of the oral proposal were accepted by Glazer. When the negotiations were concluded Fagan was told, “You have the job”, and Kelley Hunt, general manager of appellant, upon entering the office and being informed that they— Fagan and Glazer — had “worked out an understanding or an agreement”, shook hands with Fagan “and told him we were glad to see him, glad that we were going to be working together and hoped that all turned out fine * * 3

The negotiations of November 2-4 and subsequent phone conversations resulted in a letter from Glazer to Fagan dated November 8, 1964. It read in part:

“From phone conversation and your visit to El Paso I interpret your offer as follows: * * * ” (Nine items then follow relating to general and special conditions, preparation of work site, and furnishing and erection of structural steel.)

In his deposition Glazer testified that the letter “attempted to set out all the terms of the contract” they had negotiated, that they represented what he felt they previously “had agreed upon; and (he) * * * was just getting it down so that when (he) * * * wrote the contract it would be acceptable to both parties.” Following this letter were three conversations between Glazer and Fagan which mainly concerned setting up the contract.

Next in chronology, and in answer to Glazer’s letter of November 8, is a letter from Fagan dated November 11, 1964, portions of which read as follows:

“In order to clarify the significant terms of our proposal to furnish and erect steel on the Amrad project I am listing the following general terms we would require in our contract. * * * ” (Twelve items, similar but more detailed than those contained in Glazer’s letter of November 8, then follow.)
“I hope that this proposal is in substantial agreement with our verbal understandings and that a contract can be drawn up incorporating these provisions where applicable in the very near future. Several of the steel items required for this contract are only available from the mills during limited rolling order dates and an immediant (sic) order must be placed for some items if delivery is to be made within the desired time period. For this reason this offer is of very limited duration and should be acted upon immedi-antly (sic).
“We look forward to a pleasant and profitable relationship with your firm.”

Between November 11, 1964, and November 17,1964, additional conversations were had between Glazer and Fagan. On November 16 Fagan was called in Phoenix and because of a sales tax problem it was agreed that the contract price should be increased to $253,000. Glazer testified that it was during this con *198 versation, when the contract price adjustment was negotiated, that “the terms of the contract were finalized * * * ”, that the terms of Fagan’s letter of November 11 were “acceptable and were accepted”, and that he “went over the subcontract as (he) * * * intended to write it, and (showed) * * * that it met all the conditions of the letter of November the 11th.” Glazer then hand-wrote the formal subcontract as it had been agreed upon. On November 17 he called Fagan and went over the entire handwritten form, explaining point by-point that it covered all the terms required by his November 11 letter. It was agreed that it did meet those terms, and then Glazer had the contract typed and a copy sent to appellee’s home office in Phoenix for signing. 4

On December 4, 1964, appellant wrote appellee a letter which was received on December 8. It read:

“On November 18th we mailed two copies of contract to furnish and erect steel for Amrad Clutter Shield. One copy was to be executed and returned for our files. To date we have not received this copy.
“I have a monster IBM system blinking and chattering and raring to process data on this project, but unsigned contracts don’t count. Please help me and LBJ keep the lights turned out by expediting return of signed contract.” 5

On December 5, 1964, appellee wrote appellant:

“After serious consideration, we regret to advise that we cannot accept your subcontract No. 360-170-1118 covering the reinforcing and structural steel for the Amrad Radar Shield at White Sands, New Mexico. The Subcontract submitted did not meet even our requirements expressed to you in prior negotiations, and we do not believe that further negotiations could result in our reaching any agreement.”

There is evidence tending to show that this letter was written because of ap-pellee’s ultimate conclusion that the subcontract was underbid, and that no claimed uncertainty in the prior understanding between the parties was responsible for appellee’s new posture.

The record contains evidence of additional conduct indicating that the parties understood that a subcontract had been entered into theretofore. On the 13th of November, 1964, Fagan and Glazer met at the job site at White Sands and discussed job progress, laid out where ap-pellee’s fabrication yard was to be cleared, and agreed on a clearing for appellee’s crane. Glazer also testified that Fagan visited the site a second time but he was uncertain of the date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
380 F.2d 196, 1967 U.S. App. LEXIS 5656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/building-mart-inc-v-allison-steel-manufacturing-co-ca10-1967.